Civil Work & Finishes Services

Electrical accessories Work


Home automation cabling
Plumbing piping-Drainage
Sitout area- flooring work

Fixing & Testing & Comm.


Waterproofing final coat-

Wifi conduiting & cabling


Waterproofing final coat-

automation Screen Work


Waterproofing basecoat-

Waterproofing basecoat-

Automation LCD Screen

Electrical Fixtures Home


Gypsum plaster- Wall &

Toilet- Flooring & Dado

Marble & Tile polishing

Plumbing piping-Water
Sitout railing & pergola

Flat area-flooring work

Electrical conduiting in

Fire Alaram - Detector

Handing Over
CP & Sanitary Fittings
Primer,Putty 1st coat

Fire Alarm Cabeling


Electrical chasing &

AC IDU Installation
Door Shutter work

False ceiling work

Fire fighting work


Plumbing chasing
Internal Painting-
Doors & Window
Door frame work

AC ducting work

Electrical wiring
Flat Tile skirting
Internal plaster

AC piping work

fixing & testing


Toilet exhaust

& DB dressing
LV cabeling
conduiting
Ceiling
Toilets

Toilets

supply

supply
Sitout

Sitout
BBM

floor
Sr. No. FLAT NO.

402 C C C C C C C C C C C C WIP C C C C C C C C C C C
1 (4BHK) 1/15/2022
Shortage of manpower is there for electrical wiring work (Ashirvad electricals)
501 C C C C C C C C C C C C WIP C C C C C C C C C WIP C C
2 (3BHK) 1/15/2022
Shortage of manpower is there for electrical wiring work (Ashirvad electricals)
502 C C C C C C C C C C C C WIP C C C C C C C C C C C
3 (4BHK) 1/15/2022
Shortage of manpower is there for electrical wiring work (Ashirvad electricals)
601 C C C C C C C C WIP C C C C C C C C C C C C WIP C C
4 (3BHK) Servant toilet flooring & dado balance due to MEP balance work 1/15/2022
Shortage of manpower is there for electrical wiring work (Ashirvad electricals)
602 C C C C C C C WIP C WIP CS C C WIP CS C C C C C C
5 (4BHK) Shortage of manpower is there for toilet flooring work (Artistic) 3/30/2022

701 C C C C C C C C WIP C WIP WIP C C C C C C C C C C C


6 (3BHK) Shortage of manpower is there for toilet flooring & flat area flooring work (Artistic- Only 1 mason is there) 1/15/2022

702 C C C C C C C C WIP C WIP WIP C C WIP WIP C C C C C C C


7 (4BHK) Kitchen flooring work is balance due to MEP work, MEP clearance awaited for Bedroom-3 toilet 3/30/2022
Shortage of manpower is there for plumbing work (Venkatesh Sanitation)
8 802 C C C C C C C CS CS C CS CS CS CS CS CS CS CS CS C CS CS CS C CS CS CS CS CS CS C CS CS CS CS CS CS
(4BHK)
803
9 (DUPLEX) C C C C C C C CS CS C CS CS CS CS CS CS CS CS CS C CS CS CS C CS CS CS CS CS CS C CS CS CS CS CS CS

10 902 C C C C CDA C CDA CDA CDA C CDA CDA CDA CDA CDA CDA CDA CDA CDA C CDA CDA CDA C CDA CDA CDA CDA CDA CDA C CDA CDA CDA CDA CDA CDA
(4BHK)
1002
11 (4BHK) C C C C C CDA CDA C CDA CDA CDA CDA CDA CDA CDA CDA CDA C CDA CDA CDA C CDA CDA CDA CDA CDA CDA C CDA CDA CDA CDA CDA CDA

12 1003 CS CS WIP CS CS CS C CS CS CS CS CS CS C CS CS CS CS CS CS 3/30/2022


(DUPLEX)
1102 C C C C C WIP CS C CS CS CS CS CS CS CS C CS C CS CS CS C CS CS CS CS CS CS C CS CS CS CS CS CS
13 (4BHK) MEP clearance awaited for waterproofing work, Gypsum work is on hold by client
1202 C C C C C C C C C WIP C C C CDA C WIP C C C C WIP
14 (4BHK) Work is on hold by client 3/30/2022
Work is on hold by client
1402 C C C C C WIP C C C WIP WIP C C
15 (4BHK) Shortage of manpower is there for gypsum work (Artistic) 2/28/2022
Shortage of material (AC IDU units) , Shortage of manpower is there for plumbing work (Venkatesh Sanitation)
1501 C C C C WIP WIP C C
16 (3BHK) Gypsum work will start after electrical chasing & conduiting work 2/28/2022
Shortage of manpower is there for plumbing work (Venkatesh Sanitation)