STATUS OF PROGRESS OF TRT-3 AND TRT-4 TRT-4 Status

Activity Total Scope Executed Balance


Heading 1116 1116 0
Benching 1116 1092 25
Invert 1116 874 242
Heading & Benching Completed RD:0 Heading & Benching Completed Overt 1116 662 455
RD:212.35 RD:0 RD:670.25

Invert Completed
RD:212.35 RD:8.35 RD:7.4 Invert Completed
RD:667

Overt Completed Overt Completed


RD:212 RD:15.1 RD:11.8 RD:464.30

TRT-4

0 180 345 667 670 871.5 903.4


212 RM 180 RM

311

15 M BAL
528 m 58 RM

LINK TUNNEL
125 89RM 15.1 723.5 RM
EA-7

EA-8

OUT LET
M
328 650

R
.5
63
101 Rm
10.35 M BAL

211 RM

149 RM 160 RM 700 m


RD:0

TRT-3
6 27 135 160 515 m 858.6 860

Heading & Benching Completed 319

RD:148.05 Heading & Benching Completed TRT-3 Status


Activity Total Scope Executed Balance
Invert Completed Invert Completed
RD:5
RD:650 Heading 1007 1001.7 5
RD:148.05 RD:8.35
Benching 1007 1001.7 5
Invert 1007 225.0 782
Overt Completed RD:6 Overt Completed RD:650
Overt 1007 587.2 420
RD:147.33 RD:10.35 RD:6 RD:449.40

Heading Completed
Heading + Benching Completed
Invert Lining Completed
Invert + overt Lining Completed
Balance to be Excavation (H+B)
Contact Grouting