Assembled structural section (4 legs) will be lifted with tailing support of farana F21
60ton crane
EL+21.50M
(T.O.S)
02
Farana F21
1WFR35
02
02
EL+11.250M
(T.O.S) 02
1WVBR149 1WVBR149
1WFR35
EL+5.000M EL+5.000M
(U/S OF BASE (U/S OF BASE
PLATE) PLATE)
D E
Tailing crane slings will be disconnected after lifting the assembled structural section (4 legs)
60ton crane
02
1WFR35 1WFR35
02
Manlift position-01
Crane
02
EL+11.250M
(T.O.S) 02
1WVBR149
EL+5.000M
(U/S OF BASE
PLATE)
D E
After positioning of the 4 leg section Bolting shall be done with the support of manlift/Boom lift
60ton crane
EL+21.50M
(T.O.S)
02
1WFR35 1WFR35
02
Manlift position-02
Manlift position-01
crane
02
EL+11.250M
(T.O.S) 02
1WVBR149 1WVBR149
EL+5.000M
(U/S OF BASE
PLATE)
D E
Once 4 leg section Bolted and stabled, crane shall be lift another column (2 leg section) and the same will be connected with
base plate for bolting and tied with wire ropes until completion of full quantity of bracing erection.
EL+21.50M
(T.O.S)
02
02
EL+11.250M
(T.O.S) 02
1WVBR149 1WVBR149
EL+5.000M
(U/S OF BASE
PLATE)
D E