Review Contract Plans & Proposal, Specs. and DOT approved Shop Drawings (Sections 603 &
604). All Shop drawings should be submitted with calculations by the contractor for approval by
Regional and MO Materials.
Ensure that the shop drawings are approved by the Regional Design,Geotechnical, and
Materials groups prior to sending it to MO materials and Geotechnical group.
Review Standard Sheets for installation details (203-4, 203-5, 603-1R1, 604-5R1, etc.).
Make sure all utility mark-outs have been completed and proper Dig Safe calls have been made
prior to allowing any excavations.
Review plans for conflicts with existing utilities and make sure any test holes have been done to
determine vertical and horizontal conflicts.
Review Drainage sheets/tables to determine correct locations to achieve proper curb offset or
pavement/shoulder width.
Review contractors Lifting Plan. (Do not require a PE certified Lifting Plan unless it is required
as per plans)
MATERIALS
CONSTRUCTION DETAILS -
CHECKBOX