Professional Documents
Culture Documents
2016
Declaration
I hereby declare that the project work entitled “REPORT ON THE INTERNSHIP
PROGRAM FOR FOUR MONTHES ON ALMACON BUILDING
CONTRACTOR " submitted to the AASTU School of civil and construction
technology and management engineering, is a record of original work done by me under
the guidance of my esteemed advisor Mr.Yohannes Hagose and my site supervisor
Eng.Maerege. And this project work is submitted in the partial fulfillment of the
requirements for the internship session of 2016 held for 4th year student of AASTU
School of civil and construction technology and management engineering. The results
embodied in this report have not been submitted to any other University or Institute for
the award of any type of work.
ABBROVED BY
Acknowledgment
First of all I would like to thank every families and friends that participate on my life and
get me in this intensity and individuals who support and share idea and also helping me to
be like this.
I am very thankful ALMACON BUILDNG CONTRACTOR for having given me the
opportunity to undertake my four month internship class in their working area. It was
Avery good learning experience for me to have worked at this area. I would like to
convey my heartiest thanks to site engineer Eng.Maerege Moges, General Forman Mr.
Metagesha and all staff member works in Dessie branch.
I would also thank advisors Mr.Yonas Hagose for his endless support by consulting me
how to write this report in outstanding manner, all teachers of civil engineering who
brought me to my present performance and shape me like this during the last three
successive years.
Before I finish I would like to give my deepest thanks to all workers from the contractor
and the consultant side starting from engineers to daily laborers. Also for those who do
not listed in the above but support me in different areas I would like thank all.
Internship certificate
Executive summery
This internship report contains six chapters in which I try to explain my four month
experience in my hosting company. The content of all chapters is broadly explained and
it is constructed from the practical basis of the site work ended all months.
In the first chapter I give details to the project background, company background
including its mission, vision and objective of the project. In this chapter I put all record or
history and futurity of my hosting company. So, it is give details of the company in terms
of reader can easily know.
The second chapter deals about how I performed the program shortly. And how I record
the work I have executed.
The third chapter is the most hunted chapter which explains my overall internship
familiarity in the last successive months. This chapter is the main chapter and I record on
it the overall work I have been executing. It gives a high light what I have been doing and
main works of the construction industry.
After all those chapters explained above I goes to the fourth chapter and explains the
assessment of the internship class in terms of different aspects and areas. It is obvious
that the internship has a plus in terms of improving skills and different abilities as a
whole. The advantages and gains of the internship putted in short and prices way to grasp
the attention of readers and evaluators.
The final and fifth chapter explains about the winding up and suggestion on the project
that our company runs. Inside the site we get many things which are appropriate and
inappropriate for work in building construction, thus I comment and give my
commendation in some conditions and working.
Table of Contents
Declaration............................................................................................................................i
Acknowledgment.................................................................................................................ii
Internship certificate...........................................................................................................iii
Executive summery............................................................................................................iv
List of figures.......................................................................................................................v
List of tables........................................................................................................................v
Acronym...........................................................................................................................viii
Chapter one..........................................................................................................................1
1. Introduction......................................................................................................................1
1.1. Background of the project.........................................................................................1
1.2. Overview of the company.........................................................................................1
1.3. Overall Structure of the Company............................................................................2
1.4. Objective of the project.............................................................................................4
1.4.1 General objective.................................................................................................5
1.4.2 Specific objective................................................................................................5
1.5 Problem statement......................................................................................................5
Chapter two..........................................................................................................................6
2. Material and Methodology Used.....................................................................................6
2.1 Material and Methodology Used................................................................................6
Chapter three........................................................................................................................7
3. Accomplishments of Activities........................................................................................7
3.1. Office work...............................................................................................................7
3.2. Site work...................................................................................................................9
Chapter four.......................................................................................................................22
4. Assessment of the internship.........................................................................................22
4.1. Improving practical skill.........................................................................................22
4.2. Upgrading the theoretical knowledge.....................................................................23
4.3. Upgrading interpersonal communication skill........................................................23
4.4. Work ethics and related issues................................................................................23
List of figures
List of tables
Acronym
ADA Amhara development agency
ANRS Amhara National Development
Cm Centimeter
C-5 Concrete that have 5mpa compressive strength
C-20 Concrete that have 20mpa compressive strength
EBCS Ethiopian Buildings Code Standards
Mm Millimeter
OPC Ordinary Portland Cement
UIL University Industry Linkage
Chapter one
1. Introduction
1.1. Background of the project
ALMACON building contractor is currently working on different projects in Dessie,
Bahir Dar, and Debre Markos in Amhara region. These project B+G+9 is apartment
building which is going to be constructed in Dessie town and owned by ANRS Housing
Development Agency.
The project consist B+G+9 low cost apartment building. The building is designed by
ANRS Housing Development Agency. It covers an area of about 1910 m 2 and takes a
total cost of 54,724,906.24birr with vat exclusive.
The building is a multipurpose building with cafeterias; shop, offices and living
apartment have three and four bed room. The basement mainly used for car parking. The
first and second floors also used for cafeterias, super market and shop. The rest is used
for living apartments. It has numerous structures like mat and strap foundation, beam,
parapet, tie beam, shear wall, retaining wall, ramp, etc. It was estimated the building will
be completed December 2018.
At the start of the internship program, the construction process was at the ground floor
level along the course of the internship program; the construction process has reached a
fifth level.
Vision
Provide quality construction, economical and to satisfy the demand of the people within
the short period of time in the country.
Mission
Quality of construction
Honesty
Adding value to clients.
Nurturing and promoting talents.
Respecting employees‘ intense efforts and contribution
Project manager
The project manager, in the broadest sense of the term, is the most important person for
the failure and success of the project. The project manager is responsible for planning,
organizing and controlling the project. In turn, the project manager receives authority
from the management of the organizational to mobilize the necessary resources to
complete the project. The project manager must be able to exert interpersonal influence in
order to lead the project team. He must possess leadership quality and the ability to
handle intricate interpersonal relationships effective within an organization.
Office engineer the main responsibility of the office engineers are:-
Prepare material lists for the project and ensuring deployment.
Preparing payment certificates for sub contract works based on actual quantity
executed. Keeps records of payments certificates related to the sub contract
works.
Documentation.
Keeping contract documents and drawing.
Keeping proper documents of corresponding variables order.
Under taking other responsibilities assigned by the project manager. Working
under the office engineer, the quantity surveyor has similar duties. But the
quantity surveyors work is approved by the office engineer. The data collectors
assemble different reports and compile them into Weekly and monthly reports.
Construction engineer a construction engineers that works together with the site
engineers to supervise the construction work. The construction engineers give solutions
to practical problems that might occur during the process of the work.
Site engineer the site engineer has the foreman under him and he details of the work. In
addition he advises the foreman on the course of action. The site engineer also makes
sure that the work is done according to the design. During the course of construction
foreman and site engineer will make decisions about work to be undertaken at particular
times of the day based up on the availability of the necessary resource of laborers,
materials and equipment’s. Without coordination among these necessary inputs, the
construction process will be inefficient
Acts as the agent’s right hand man for the execution of the work at the field, his duty is to
keep the work moving ahead as the agent has planned it. He often has much authority on
the site, and is often astonishingly capable from their long experience of construction. For
instance, their familiarity with the soil characteristics enables them to judge by eye that
some foundation or fill material is „no good‟, long before the site engineer’s testes prove
it so.
Forman the main aim of the Forman is manages and supervise manual works. In this
particular site there are different foramens having their own skills. Each foreman has
responsibility to done any work according to the site engineer order. Their work always
checked by the site engineer
Trade Forman’s
Controls most of the skilled (masons, carpenters, plumber…) and unskilled (gang
leaders) labors by giving directions that he receive from the general Forman or the site
engineer.
Mason; a production worker responsible for production of masonry. He is the
main construction worker for the structural shell.
Carpenter; is a craft responsible for making wood structures for supporting
different structural components like beams and columns, formworks, and chip
wood works.
Plumber; responsible for installing, repairing and maintaining pipes and
other construction materials used for water supply and waste water disposal.
Electricians; perform works required for the repair, maintenance,
installation and modernization of electrical systems.
Machine operators; operate, fix and maintain different machineries on the
site like, vibrator, mixer, and damper.
Metal workers; assemble, install and repair sheet metal products and
equipment’s.
Gang leaders; controls the distribution of labor forces throughout by taking
orders from the trade Forman’s. He controls the number of laborers at each
work place; transfer labor workers from one place to other place in the site,
and check whether laborers are performing their job properly.
Finance The finance takes care of monthly salary (fee) of the employees;
finance the purchasing of requested materials.
Store keepers Control the amount and type of materials entering and leaving
the store.
Data collector the data collector collects daily work activities carried out on
the site.
Chapter two
Chapter three
3. Accomplishments of Activities
Up on my arrival at the site I was assigned to observe and carry out tasks. I was work bar
schedule, take off sheet, bill of quantity and material brake down. This help to cross
check with my work and got a comment. And also I observe site work like form work,
concrete work, reinforcement work and earth works at others site.
Generally I have been working in the two sections. I sort the work in to office work and
site works, mostly the work I have been executing on the site is supervising, working as a
site engineer and Forman.
The standard form used for entering the dimensions taken or scaled from drawings to
determine the accurate quantity in each trade of work, except reinforcement steel, is
called take off sheet or dimension paper. The main aim of this sheet by taking each item
of work and calculating the quantities in detail is for payment and cost estimation for
purchasing and preparing bill of quantity.
The dimension paper used for taking off is double – ruledA4 size paper as shown below.
T D S D T D S D
Bar schedule is used to estimating the quantity of reinforcement bars required for a given
project. A complete set of structural drawings is necessary to take sizes and shapes of
bars for different members of reinforced concrete structures. In our site we use the
following tables.
no Locat Dia. Shape Lengt No. No. Total no. Total length(m)
ion (mm h of Of Of bar Ф6 Ф8 Ф10 Ф12 Ф14 Ф16 Ф20 Ф24
) (m) Bar/m elem.
Total length(m)
Unite weight(kg/m) 0.222 0.39 0.617 0.888 1.20 1.579 2.467 3.552
5 9
Total weight(kg)
Setting out
The first task before the erection of any building is the proper setting out. Setting out,
which is a task of field surveyors, is a process of putting the exact/actual form of the
building from a plan or map provided to the ground. Given the site plan, the surveyors
will indicate the column edges of the building’s corners using pegs. A building is set out
in order to clearly define the outline of the excavation and the centerline of the walls and
column, so that construction carried out exactly according to the plan. The basic
coordinates of each building will be set in position in accordance to the given benchmark.
Site clearance
After doing setting out the top soil excavation started with machineries the organic top
soil found on the upper layer to an average thickness of 20-25cm removed separately
from the bulk excavation work. Immediate cart away performed following its clearance.
Excavation
Excavation is the first step of construction. It refers to the process of removing soil from
its original location. If the Excavated material required for backfill stockpiled on the site
for subsequent use otherwise it becomes cart away. I have seen bulk excavation, pit
excavation and trench excavation. The main aim of the excavation work is to remove
organic soils or unwanted soil. Excavation shall be carried out to the lines, levels, width,
depth and grades shown on the drawings, directed by the Engineer or as appropriate to
the works to be placed in the excavation.
Bulk excavation
Bulk excavation was carried out after the removal of the top soil is executed. 1m off set
from each side of the site provide for working space and would extend to the outer side
and the work performed for the intended average depth of excavation, in our site the
foundation is mat for this type of foundation excavated around 450 cm excavated from
the reduced ground level including its basement. The removal of the soil was performed
using a machine. The soil excavated immediately taken off from site because the soil has
low bearing capacity ratio.
Mat beam it is a type of huge beam which have a depth is much greater than the width.
In the project site the depth of mat beam is 150cm and 50cm width.
Selected Materials Selected material /Backfill/ is mainly natural material that is used to
fill in some void left after construction or excavation efforts. Usually it is a combination
of stone, soil and other materials that were left over after the main portion the project was
completed. However the back fill may be transported to the building site if necessary.
In the project site they compacted in each 20 cm layer by using plate compactor and
jumping jack type compactor. Each layer shall be compacted to 95 % of the maximum
dry density. Water may be added during the compaction process to assist with
compaction.
3.2.4 Formworks
As fresh concrete is in plastic state when it is placed for construction purpose so, it
becomes necessary to provide some temporary structure to confine and support the
concrete till it gains sufficient strength for self-supporting. This temporary structure is
called formwork. Concrete formwork serves as a mold to produce concrete elements
having a desired size and configuration. It is usually erected for this purpose and then
removed after the concrete has cured to a satisfactory strength. For satisfactory
performance, formwork must be adequately strong and stiff to carry the loads produced
by the concrete, the workers placing and finishing the concrete, and any equipment or
materials supported by the forms.
In the site, the formwork material use wood material.
The general step used to construct a formwork in the site is:
Prepare the false works in the desired position and level.
Preparing the formwork in a desired shape based on the drawing or the size of the
structure that is going to cast.
Painting oil as a releasing agent.
Nailing a formwork with appropriate bracing element and false work.
Formwork for Footing Pads: Most of the pads, which have larger and similar size,
made via wood formworks. Those of pads with a smaller size were made via together
fixed timbers of locally available type. Such formworks was dismantled and directly
fitted to their similar type pads, successively
Formwork for Foundation Columns and elevation column: This consists of a vertical
mold of the desired shape and size. In our site, the formworks used for rectangular
columns, they have used rectangular formwork made of timber to the desired dimension.
Formwork for Beams: This is a three sided box supported and propped in the correct
position and to the desired level. In our site the beam has 500 by 250mm; it cast
monolithically with the slab so they used 35cm side formwork in the internal side and 50
cm in the outer. The 15cm covered by the slab and used 30 cm soffit.
Slab and Beam Formworks
In a building the slabs and beams constructed together since they were designed having a
T-shaped cross section /flanged beams/ which allows the simultaneous construction of
both structural components. The slabs were solid and ribbed slab having a uniform
thickness of 15cm in all the floors while the beams have 500 x 250 dimensions where the
150mm depth constructed together with the slabs.
The following procedures employed in formwork preparation of slabs and beams:
Cristy erected with a maximum spacing of 60cm along the length of the slab.
Bottom portions of the beam formwork or soffit1 laid over the cristies2 prepared
previously.
After finishing the bottom beam formworks; the sides of the formwork placed and
nailed which provide the three dimensions of the final beam structure.
Horizontal members, which are the main components of the slab formwork called
modini, are fitted with the sides of the beam formwork. By considering, the
spacing provided with respect to the final formwork material to be used i.e. metal
sheet or panels.
1
Used as a formwork for beams and slabs at the bottom.
2
Support a formwork of a beam.
and negative bars. Because of uncertainty the direction of moments in columns. Based on
the way in which the bar is provided, the reinforcing bars can also be classified as stirrups
or main reinforcements.
Stirrups will be curtailed for length equal to perimeter of main reinforcements and extra
50mm both ends. Perimeter of main reinforcements is equal with depth or width of
structural member minus two times clear covers each side. Then perimeter equal to the
sum of four sides.
Lapping or Splicing of bars
In column and beams lapping will be at each floor level and in all cases the length
lapping is equal to 4 times the diameter of the bar.
When splicing or overlapping provided in reinforcing steel they must be away from the
section, which have maximum stress. I.e. bar spliced in the site for bottom reinforcement
at the support and for top reinforcement at the center in a length of four times the larger
diameter of bar for every structure.
Sand: the sand to be used for concreting is just chosen as the requirement for and
concrete armata purpose.
Aggregate: the aggregate to be used for concreting again chosen as per the requirement.
This could be 01,02,03,04 aggregates. Here for concreting purpose 02 aggregate is used.
Lean concrete is concrete of 5mm thick with class C-5 with a minimum cement content
of 150kg/m3 of concrete. Approximately at ratio of 1:4:6. The Advantages of lean
concrete is to protect all sub-structure elements from extra moisture and prevents the soil
particles that are present under Substructure from any relative movement. I have seen
lean concrete used for under grade beam, footing pad and masonry.
Mixing of concrete
There are mainly two ways of mixing (mixing by hand and mixing by machine). Here in
our site they use a machine mixer. They use three mixing machines in the project.one
750L mixing machine and the other two are 350 L mixing capacity machine. These
machines can mix one unit of mix, which is 1:2:3 ratios. Here the choice of the mix ratio
comes from already adopted ratio prescribed in the codes. The choice of concrete strength
depends on the design.in our site they use C-25 concrete with the box size of 20cm x
40cm x 50cm.
Compaction of concrete
The process of compacting concrete essentially comprises the elimination of entrapped
air and achieving maximum density the importance of compaction should not be
undermined. To achieve this vibration is used, when the compaction is done manually it
is called hand compaction and when it is done by using machine vibrator it is called
mechanical compaction. .
Figure 3. 9 Compaction
Curing
Curing in the initial stages of hardening is extremely important and should continue as
long as possible, not less than 7 days. It is the process of preventing the loss of moisture
from the concrete while maintaining a satisfactory temperature regime. In our site, curing
of concrete starts from the finishing of the pouring and ends in a 7 days. Mostly they cure
at morning and nighttime.
Concrete tests Concrete will be tested for its properties in order to know its quality and
strength. I have seen Concrete strength test.
Concrete strength test
Concrete needs to be checked for its flexural resistance, tensile and compression strength.
For compression strength test 150mm dimension of cubes are used. The number of cubes
is mostly six. Then the strength of two of cubes will be tested at the ends of 14 th day and
the remaining two at 28th day.
Generally the strength of concrete will be affected by cement type , quality of sand and
aggregate used, mix ratio and Water content The strength of concrete at 28 th day is used
for design strength and the test strength must be `greater than the minimum required
strength. But if strength fails the structure must be dismantled.
To prevent the reinforcement from bursting out so that it will be retained in its
position.
To protect steel reinforcements from exposer condition such as fire, ground
water and harsh environment.
The thickness of clear cover provided is based on to which structural component it has to
be applied. Accordingly, the provided clear cover for foundation and grade beam is
50mm and for other structural members such as columns, beams, shear wall and slab is
25mm.This difference in thickness for different structural members is based on the
exposure conditions of the members to the environment which adversely affects the
reinforcement and thus the strength of member.
3.2.8. Slab
Slab is a structural part of the building having plate shape and used to cover the distance
between beams and possibly columns. Generally slabs are constructed monolithically
with beams and concreted in one operation for the full depth. The top surface of the slab
is kept rough to create a proper bond with any type of floor finish desired. At our project
site they incorporated solid slab and ribbed slab. It was constructed from a concrete
quality C-25 and its reinforcement details were the same to those of beams. The bottom
reinforcement is continuous over the entire span and top reinforcement is provided at the
support section to take up the tensile forces
.
Figure 3. 11 Erection of solid and ribbed slab
3.2.8. Electrical installation
Electrical installation starts parallel with ground slab work by installing conduits. Starting
from first floor I observed when they install the conduits according to the design, before
slab is filled with concrete. Additionally the conduits are covered before concrete is filled
to prevent clogging of cables. At site, electrical installation is done for different kinds of
utilities such as light bulbs, bells, switches, air conditioners etc.
Chapter four
Different construction equipment and their use in construction site. Many of great
structures before are a product of numerous human power and countless days inspired by
great powers. Machines are capable of handling tough work which may be beyond the
scope of human labor to be performed. They can be expected to work with fair degree of
effectiveness even under adverse weather, climate or topographical conditions. I
generally know how equipment‘s are used in the site including their specific purpose.
Punctuality is one of the major issues that could be raised when talking about work ethics
and on my side I tried meet these criteria by attending to my working station in time so
that there will not be any delay on the activities planned for that day. The behavior that
one shows towards his peers and colleagues is also one manifestation of the concept of
work ethics. Personally, I always respected and gave priority the employers of the
company. Elements of work ethics that worth mentioning are: -punctuality, honesty,
reliability, office discipline, corporation and responsibility.
We us a student should follow the rules and regulations set by the company and avoid
complaining any work load, activity or assignment that may arise on the site or office. It
is a pleasure of supervisors if we have a good work ethics and we are responsible for any
given tasks. Since the aim of internship is to let students know the outside environment
pertinent to their field, which includes of such the above dealt qualities, I was with the
great interest that I tried to meet my responsibilities and work ethics that I suppose to be
fulfill by my side.
Generally, I can say I have gained the potential benefits by taking the Internship Program.
Chapter five
5.2. Recommendation
During my four months of internship experience period I have seen some positive and
negative sides about the internship hosting company. In this part I will try to suggest
some ideas for my internship hosting company and my university.
Giving courses that are appropriate for the internship program before the
internship class is commenced like quantity, integrated etc.
Chapter six
6. References