1 H beam H-152*152 14.27 30.42 434.15 40 17,366.17
2 I beam I-201*101 27.22 26.2 713.11 40 28,524.46
3 C-channel MC 200 16.33 25.3 413.15 40 16,525.96
4 C-channel MC150 6.632 13.8 91.52 40 3,660.86
5 Plate 250*205*20mm 4 9.81 39.24 40 1,569.60
6 Plate 202*150*10mm 64 2.38 152.32 40 6,092.80
7 Handrail Pipe d=50 43.781 3.8 166.37 40 6,654.71
Handrail Pipe D=25 24.32 1.63 39.65 40 1,585.85
Checker Plate 15.51 15.51 23.55 365.26 40 14,610.42
8 Contingency(ladder) 278.96 40 11,158.29
Total 107,749.13
Fabrication and erection Boiler panel board room steel structure with out material cost
1 H beam H-152*152 17.84 30.42 542.69 40.00 21,707.71
2 I beam I-201*101 34.02 26.2 891.39 40.00 35,655.58
3 C-channel MC 200 20.4125 25.3 516.44 40.00 20,657.45
4 C-channel MC150 8.29 13.8 114.40 40.00 4,576.08
5 Plate 250*205*20mm 5 9.81 49.05 40.00 1,962.00
6 Plate 202*150*10mm 64 2.38 152.32 40.00 6,092.80
7 Handrail Pipe d=50 43.781 3.8 166.37 40.00 6,654.71
Handrail Pipe D=25 24.32 1.63 39.65 40.00 1,585.85
9 Grating Stair 650*250*25 18 7.24 130.32 40.00 5212.8
8 Contingency(ladder) 348.70 40.00 13,947.87