Professional Documents
Culture Documents
TOTAL - -
We certify that the Contractor is now entitled to the sum of birr 1,104,004.91
( One Million Four Hundred Seventy Thousand Three Hundred Two Birr and 33/100 Cents Only.)
Checked
by
(Contracto Approved by
Prepared by Serkalem Asfaw r) (Client)
Date Monday, February 14, 2022 Date Monday, February 14, 2022 Date Monday, February 14, 2022
2/33 576392303.xlsx 02/14/2022
PART ONE
MATERIAL PERCENT
Sr. No. LOCATION TAG NO. EQUIPMENT NAME UOM QTY RATE AMOUNT COMPLETION
Erection work
1 Ware House PS-104.1 ERECTION OF EDTA SOLUTION TANK PCS 1 3,185.05 3,185.05
2 Ware House D-126.3 ERECTION OF WATER FEED TANK PCS 1 17,031.17 17,031.17
3 Ware House SM-126.1 ERECTION OF IN-LINE MIXER FOR WASHING LYES PCS 1 442.37 442.37
4 Ware House R-126.2 ERECTION OF TUBULAR REACTOR PCS 1 17,801.63 17,801.63
5 Ware House E-201.1 ERECTION OF HEAT EXCHANGER HE-12-115-60 1 6,386.69 6,386.69
Plate and frame heat exchanger complete with supporting frames. Material of
6 E-206.3 construction: AISI 316 stainless steel (plates) and carbon steel (frame). PCS 1 6,967.30 6,967.30
7 Ware House SD-204.1 ERECTION OF VACUUM CHAMBER ME 1000/1505 PCS 1 14,192.64 14,192.64
8 Ware House DC-205.1 ERECTION OF FINES SEPARATOR " SP-1100 " PCS 1 9,630.72 9,630.72
9 Ware House PL-205.1 ERECTION OF SOAP FINES EXTRUDER PCS 1 3,091.97 3,091.97
10 Ware House DC-205.2 ERECTION OF FINES SEPARATOR " SP-1100 " PCS 1 9,934.85 9,934.85
11 Ware House T-205.2 ERECTION OF SOAP FINES WORM CONVEYOR DSC-158 PCS 1 2,027.52 2,027.52
12 Ware House PL-204.1 ERECTION OF PLODDER PCS 1 76,032.00 76,032.00
13 Ware House ERECTION OF DUCTS pcs 12 2,443.16 29,317.94
14 Ware House E-126.1 ERECTION OF PREHEATING /HEAT EXCHANGER FOR OILS PCS 1 658.94 658.94
15 Ware House E-126.2 ERECTION OF PREHEATING /HEAT EXCHANGER FOR CAUSTIC SODA PCS 1 587.98 587.98
16 Ware House C-206.1 ERECTION OF BAROMETRIC CONDENSER PCS 1 11,658.24 11,658.24
17 Ware House D-121.6A/B Erection BRINE SOLUTION STORAGE TANK PCS 2 18,800.64 37,601.28
18 Ware House PJ-206.1 ERECTION OF THERMOCOMPRESSION PCS 1 27,684.86 27,684.86
19 Ware House PX-249.1A ERECTION OF CHILLER WATER UNIT PCS 1 38,744.06 38,744.06
20 ERECTION HEAT EXCHANGER PCS 1 1,013.76 1,013.76
21 Ware House D-203.1 ERECTION OF SILICATE SOLUTION FEED TANK PCS 1 3,916.80 3,916.80
317,907.76
3 Ware House D-124.3A/B FABRICATION AND ERECTION OF SOAP KETTLE FOR SLOP PCS 2 149,216.17 298,432.35 65%
4 Ware House D-124.6 FABRICATION AND ERECTION OF SPENT LYE TANK PCS 1 104,076.39 104,076.39 90%
5 Ware House D-121.3 FABRICATION AND ERECTION OF BRINE SOLUTION TANK PCS 1 79,419.75 79,419.75 90%
6 Ware House D-121.14 FABRICATION AND ERECTION OF CAUSTIC SODA FEED TANK PCS 1 36,551.71 36,551.71 10%
7 Ware House D-120.5 FABRICATION AND ERECTION OF CONDENSATE TANK PCS 1 88,310.06 88,310.06 75%
8 Ware House FABRICATION AND ERECTION OF PROCESS STEEL STRACTURE price/KG 15000 483,840.00 483,840.00
Ware House and
tank farm (pipe
9 rack) FABRICATION AND ERECTION OF PIPE RACK AND ELECTRICAL SUPORT price/KG 30000 967,680.00 967,680.00
2,165,999.84
64,815.21
Total 2,548,722.81
COMPANY NAME :- REPI SOAP & DETERGENT PLC - ALEMGENA , ETHIOPIA
PROJECT NAME:- SAPONIFICATION PROJECT (TANK FARM)
LOCATION :- ALEMGENA SEBETA AWASE KEBELE 08
PART ONE
MATERIAL
Sr. No. LOCATION TAG NO. EQUIPMENT NAME TOTAL KG QTY RATE AMOUNT
1 Tank Farm UNIT - 1 COMPRESSED AIR PRODUCTION 1.00
1.1 Tank Farm 1.DG.1 ERECTION OF AIR DRYER 2,500.00 1.00 25,344.00 25,344.00
1.2 Tank Farm 1.E.1 ERECTION OF AIR COOLER (INCLUDED IN K1) 1,500.00 1.00 8,363.52 8,363.52
1.4 Tank Farm 1.V.1 ERECTION OF AIR STORAGE TANK 1.00 10,644.48 10,644.48
1.3 Tank Farm 1.K.1 ERECTION AIR COMPRESSOR 2,500.00 1.00 25,344.00 25,344.00
FABRICATION & ERECTION OF ROOFING & WALL CLADDING OF COMPRESSER ROOM INCLUDING TO ALL
STRUCTURE 2,500.00
1.5 Tank Farm 32.26 80,640.00
2 Tank Farm UNIT - 2 WATER TREATMENT / WATER DEMINERALIZATION 1.00 - -
ERECTION OF WATER TREATNENT PLANT PACKAGE EXCLUDING FABRICATION AND ERECTION OF
2.U.1 STORAGE TANKS 1.00
2.1 Tank Farm 159,293.95 159,293.95
_
FABRICATION & ERECTION OF WATER TANK INCLUDING SPARIAL LADDER 2.00
2.2 Tank Farm 314,333.50 628,667.01
2.3 Tank Farm FABRICATION & ERECTION OF WATER TANK INCLUDING SPARIAL LADDER _ 1.00 437,827.90 437,827.90
2.4 Tank Farm FABRICATION & ERECTION OF WATER TANK INCLUDING SPARIAL LADDER _ 1.00 811,429.28 811,429.28
2.5 Tank Farm positioning of PLCand MCC panel for water treatment plant 200.00 19.35 3,870.72
1,000.00
SUPPLY FABRICATION & ERECTION OF MCC AND PLC stand 1,000.00
2.6 Tank Farm 110.59 110,592.00
8,000.00
FABRICATION & ERECTION OF WATER TREATMANT PLANT & UTILITY ROOM 8,000.00
2.7 Tank Farm 32.26 258,048.00
3 Tank Farm UNIT - 3 STEAM PRODUCTION - -
3.1 Tank Farm 3.H.1A ERECTIONOF STEAM BOILER WITH ALL ACESSORY( 10,000.00 1.00 41,472.00 41,472.00
3.2 Tank Farm 3.V.2 FABRICATION AND ERECTION OF CONDENSATE COLLECTING TANK 1.00 44,642.30 44,642.30
4 Tank Farm UNIT - 4 COOLING WATER SYSTEM - -
4.1 Tank Farm 4.CT.1A ERECTION OF COOLING WATER TOWER _ 1.00 33,767.42 33,767.42
4.2 Tank Farm 4.CT.1B ERECTION OF COOLING WATER TOWER _ 1.00 33,767.42 33,767.42
4.3 Tank Farm 4.P.1A ERECTION OF COOLING WATER TRANSFER PUMP WITH SIT STAND 700.00 1.00 2,304.00 2,304.00
4.4 Tank Farm 4.P.1B ERECTION OF COOLING WATER TRANSFER PUMP WITH SIT STAND 700.00 1.00 2,304.00 2,304.00
4.5 Tank Farm 4.P.2A ERECTION OF COOLING WATER TRANSFER PUMP WITH SIT STAND 700.00 1.00 2,304.00 2,304.00
4.6 Tank Farm 4.P.2B ERECTION OF COOLING WATER TRANSFER PUMP WITH SIT STAND 700.00 1.00 2,304.00 2,304.00
4.7 Tank Farm 4.P.3A ERECTION OF COOLING WATER TRANSFER PUMP WITH SIT STAND 700.00 1.00 2,304.00 2,304.00
4.8 Tank Farm 4.P.3B ERECTION OF COOLING WATER TRANSFER PUMP SIT FABRICA5IOB 700.00 1.00 2,304.00 2,304.00
5 Tank Farm UNIT - 5 HOT WATER PRODUCTION - -
5.1 Tank Farm 5.P.1 ERECTION OF HOT WATER RECYCLE PUMP WITH SIT STAND 1.00 2,257.92 2,257.92
5.2 Tank Farm 5.V.1 ERECTION OF HOT WATER TANK WITH STEAM EJECTOR 300.00 1.00 1,935.36 1,935.36
6 Tank Farm UNIT - 6 TANK FARM - -
6.1 Tank Farm 6.P. ERECTIONOF DMFA CHARGING PUMP WITH FABRICATION AND ERECTION OF ITS SIT STAND 250.00 1.00 1,843.20 1,843.20
6.2 Tank Farm 6.P.3 ERECTION OF PFAD CHARGING PUMP WITH FABRICATION AND ERECTION OF ITS SIT STAND 250.00 1.00 1,843.20 1,843.20
6.3 Tank Farm 6.P.4 ERECTIONOF PALM OIL CHARGING PUMP WITH FABRICATION AND ERECTION OF ITS SIT STAND 300.00 1.00 1,843.20 1,843.20
6.4 Tank Farm 6.P.5 ERECTIONOF PKO TRANSFER PUMP WITH FABRICATION AND ERECTION OF ITS SIT STAND 200.00 1.00 1,843.20 1,843.20
200.00
6.P.10B ERECTION OF SODIUM SLICATE TRANSFER PUMP WITH FABRICATION & ERECTION OF ITS SIT STAND 1.00
6.5 Tank Farm 1,843.20 1,843.20
6.6 Tank Farm 6.P.12A ERECTION OF CAUSTIC SODA TRANSFER PUMP WITH FABRICATION & ERECTION OF ITS SIT STAND 300.00 1.00 1,843.20 1,843.20
300.00
6.P.12B ERECTIONOF CAUSTIC SODA TRANSFER PUMP WITH FABRICATION AND ERECTION OF ITS SIT STAND 1.00
6.7 Tank Farm 1,843.20 1,843.20
6.8 Tank Farm 6.V.4 FABRICATION AND ERECTION OF PKO .STORAGETANK WITH Spairal LADDER & ALL ACCESSORIES 2.00 324,288.92 648,577.84
6.9 Tank Farm 6.V.2A/B FABRICATION & ERECTION OF DMFA & PFAD STORAGE TANK WITH LADDER & ALL ACCESSORIES 2.00 1,282,314.24 2,564,628.48
6.1 Tank Farm 6.V.3 FABRICATION & ERECTION OF PALM OIL STORAGE TANK WITH LADDER & ALL ACCESSORIES 1.00 1,356,595.20 1,356,595.20
6.11 Tank Farm 6.V.10 FABRICATION & ERECTION OF CAUSTIC SODA STORAGE TANK WITH LADDER & ALL ACCESSORIES 1.00 243,210.24 243,210.24
6.12 Tank Farm 6.V.14 A ERECTION OF PFAD EMPTYING BASIN WITH GUARD RAIL AND SPARIAL LADDER 1.00 81,561.60 81,561.60
6.13 Tank Farm 6.V.14 B/C/D FABRICATION & ERECTION OF PFAD EMPTYING BASIN WITH GUARD RAIL, & SPARIL LADDER 3.00 71,884.80 215,654.40
6.14 6.V.14 A SUPPLY Fabrication and ERECTION OF ROOFING & WALL CLADDING OF MELTING PIT ROOM 5,000.00 147.46 737,280.00
6.15 Tank Farm 6.V.14 A FABRICATION AND ERECTION OF ROOFING & WALL CLADDING OF MELTING PIT ROOM 5,000.00 32.26 161,280.00
6.16 Ware House POSITIONING OF MCC AND PLC TFOR TANK FARM AND PROCESS 900KG 2.00 5,806.08 11,612.16
6.17 Ware House FABRICATION AND ERECTION OF MCC STAND 3000KG 3,000.00 32.26 96,768.00
6.18 Ware House SUPPLY ,FABRICATION AND ERECTION OF MCC STAND 3000KG 3,000.00 110.59 331,776.00
6.19 Ware House FABRICATION AND ERECTION OF MCC ROOM 4,000.00 32.26 129,024.00
7 Tank Farm UNIT - 7 CAUSTIC SODA DISSOLUTION 1.00 - -
7.1 Tank Farm 123.E.1 ERECTION OFCAUSTIC SODA COOLER (INCL. IN 123 V 1) 900KG 1.00 9,123.84 9,123.84
350.00
123.P.1 ERECTION OF CAUSTIC SODA RECYCLE&TRAN. PUMP WITH FABRICATION AND ERECTION SIT STAND 1.00
7.2 Tank Farm 3,548.16 3,548.16
7.3 Tank Farm 123.V.1 FABRICATION & ERECTION OF CAUSTIC SODA DISSOLVING BASIN 1.00 101,376.00 101,376.00
7.4 Tank Farm FABRICATION & ERECTION OF CAUSTIC SODA HOUSE ROOF & WALL CLADDING 1.00 82,020.56 82,020.56
8 Tank Farm UNIT - 8 SUMP PITS 900KG 1.00 - -
8.1 Tank Farm FABRICATION AND ERECTION OF SUMP PIT TANK 4.00 42,799.66 171,198.63
8.2 FABRICATION AND ERECTION OF DITCH TROUGH 2.00 89,835.72 179,671.45
8.3 Tank Farm Erection of Sump pits pump WITH FABRICATION & ERECTION OF SIR STAND _ 4.00 3,548.16 14,192.64
9 Tank Farm UNIT - 9 FIRE FIGHTING - -
9.1 Tank Farm FABRICATION AND ERECTION OF FIRE FIGHTING WATER TANK 1.00 670,924.80 670,924.80
Total sum 10,554,657.69
Project: Cargill (Alphonso)
Calculations for: MCC ROOM
Civil Bill Of Quantity
Discipline CS Doc no A3530-05-CS-90-BOQ-022
Calc by RS Date 1-Apr-14
Checked by VA Date 1-Apr-14
SUMMARY
SECTION ITEM DESCRIRPTION AMOUNT (RS.)
1 #REF! #REF!
2 #REF! #REF!
3 #REF! #REF!
4 #REF! #REF!
5 Section 5 - Plumbing & Sanitary Work
6 #REF! #REF!
7 #REF! #REF!
8 #REF! #REF!
9 Section 9 - Roads & Storm Water Drain
10 #REF! #REF!
11 #REF! #REF!
12 Section 12 - Miscellaneous
A Total Amount #REF!
B Taxes
C VAT
D Service Tax
E Grand Total (A+B+C+D)
Add labour cess 1%, if applicable
CONTRACT VALUE
F
(Grand Total (E) + Add labour cess 1%, if applicable)
Project: #REF!
Calculations for:
#REF!
Discipline #REF! Job No. #REF!
Calc by #REF! Date #REF!
Checked by #REF! Date #REF!
Section 5 - Plumbing & Sanitary Work
Sr No Item Description Unit Quantity Rate Amount
Same as item no. 5.7 but for providing and fixing S.S.
5.8 Nos 0
circular wash basin 450mm dia .
Same as item no.5.7 with SS sink of size 600 x 450 x
5.9 Nos 0
250 mm deep without drain board.
a) 15 mm dia Nos 0
b) 20 mm dia Nos 0
c) 25 mm dia Nos 0
d) 40 mm dia Nos 0
e) 50 mm dia Nos 0
a) 100mm dia Rm 0
b) 150mm dia Rm 0
c) 230mm dia Rm 0
d) 300mm dia. Rm 0
e) 450mm dia. Rm 0
f) 600mm dia. Rm 0
a) 150mm dia Rm 0
b) 100mm dia Rm 0
c) 75mm dia Rm 0
a) 150mm dia Rm 0
b) 100mm dia Rm 0
c) 80mm dia Rm 0
a) 40mm dia Rm 0
b) 55mm dia Rm 0
c) 82mm dia Rm 0
d) 110mm dia Rm 0
e) 160mm dia Rm 0
a) 110mm dia Rm 0
b) 160mm dia Rm 0
c) 200mm dia. Rm 0
d) 300mm dia. Rm 0
e) 450mm dia. Rm 0
a) 50mm dia Rm 0
b) 40mm dia Rm 0
c) 32mm dia Rm 0
d) 25mm dia Rm 0
e) 20mm dia Rm 0
f) 15mm dia Rm 0
a) 50mm dia Rm 0
b) 38mm dia Rm 0
c) 32mm dia Rm 0
d) 25mm dia Rm 0
Project: #REF!
Calculations for:
#REF!
Discipline #REF! Job No. #REF!
Calc by #REF! Date #REF!
Checked by #REF! Date #REF!
Section 5 - Plumbing & Sanitary Work
Sr No Item Description Unit Quantity Rate Amount
e) 20mm dia Rm 0
f) 15mm dia Rm 0
a) 150 mm diameter Rm 0
b) 100 mm diameter Rm 0
c) 80 mm diameter Rm 0
a) 82 F Nos 0
Project: #REF!
Calculations for:
#REF!
Discipline #REF! Job No. #REF!
Calc by #REF! Date #REF!
Checked by #REF! Date #REF!
Section 5 - Plumbing & Sanitary Work
Sr No Item Description Unit Quantity Rate Amount
b) 110 F Nos 0
c) 160 F Nos 0
Total of Section 5
0
Carried Over to Summary
E-in-C = Engineer In Charge
QRO = Quote Rate only (All the items where Qty is QRO and if they are operated then contractor has to submit
Rate analysis and shall be approved before the rates are accepted)
Project: #REF!
Calculations for:
#REF!
Discipline #REF! Job No. #REF!
Calc by #REF! Date #REF!
Checked by #REF! Date #REF!
Section 9 - Roads & Storm Water Drain
Sr No Item Description Unit Quantity Rate Amount
Extra over item 9.1 for Disposal of surplus earth for lead
9.2 outside the premises and disposed off suitably to Cum 0
approved dumping yards
a) 300mm dia Rm 0
b) 450 mm dia Rm 0
c) 600 mm dia Rm 0
Total of Section 9
0
Carried Over to Summary
E-in-C = Engineer In Charge
QRO = Quote Rate only (All the items where Qty is QRO and if they are operated then contractor has to submit
Rate analysis and shall be approved before the rates are accepted)
Project: #REF!
Calculations for:Admin building
#REF!
Discipline #REF! Job No. #REF!
Calc by #REF! Date #REF!
Checked by #REF! Date #REF!
Section 12 - Miscellaneous
Sr No Item Description Unit Quantity Rate Amount
with 230 mm thk brick work (PCC and RCC required shall
a) Cum 0
be paid as per relevant items)
Same as item No. 12.2 but with fly ash bricks of 230 mm
12.3 thickness (PCC / RCC shall be paid as per the relevant Cum 0
items)
Providing and fixing 150 mm. wide PVC rubber water bar
12.24 of approved make including fixing in position etc. Rm 0
complete.
Project: #REF!
Calculations for:Admin building
#REF!
Discipline #REF! Job No. #REF!
Calc by #REF! Date #REF!
Checked by #REF! Date #REF!
Section 12 - Miscellaneous
Sr No Item Description Unit Quantity Rate Amount
Total of Section 12
0
Carried Over to Summary
E-in-C = Engineer In Charge
QRO = Quote Rate only (All the items where Qty is QRO and if they are operated then contractor has to submit Rate
analysis and shall be approved before the rates are accepted)
Amount
0
Amount
0
Amount
0
Amount
Rate
Project
Tank Details:- ha
Tank Diameter (dia. of ring wall) D =16.000m
NGL
Tank Empty Weight = 1157.0 kN h
Tank wall Load (verti. on ring wall) = 23.0 kN/m
Tank operating Weight = hb kN
32133.0
Surcharge Load (due to tank load) q = 159.8 kN/m2
Moment at the base = 53341.0 kN.m
tf
Total Load on Ring wall P = 288.3 kN/m A
Kagh Ka q
Foundation Dimensions:- 265.30
Maximum Pressure pmax =( P/b) (1+ 6e/b) = #NAME? ### 336 kN/m² #NAME?
Minimum Pressure pmin = (P/b) (1- 6e/b) = #NAME? ### 0 #NAME?
Case II : Dead Load + Live Load:-
Calculations of Forces:
Sr Force Description Force Calculation Vertical Load Point of Application Moment from Point A
No from A
1 Weight of Wall h x tw x gcn 35.44 kN 1.125 m 39.87 kN.m
2 Weight of Footing b x tf x gcn 25.31 kN 1.125 m 28.48 kN.m
3 Silo Surcharge q x ah 143.83 kN 0.450 m 64.73 kN.m
4 Silo Wall Load P 23.02 kN 1.125 m 25.90 kN.m
5 Wt. of Soil on heel h x ah x g 51.03 kN 0.450 m 22.96 kN.m
6 Wt. of Soil on toe hb x at x g 25.11 kN 1.800 m 45.20 kN.m
7 Hori. Earth Pre.
(active) M=Co-eff1 x Ka x g x H3 #NAME?
8 Hori. Press. Due to
Surcharge M=Co-eff2 x Ka x q x H2 #NAME?
9 Hori. Earth
Pressure (passive) -0.5 x Kp x g x hb -41.85 kN 0.517 m -21.62 kN.m
Total Load P = 303.74 kN #NAME?
Maximum Pressure pmax =( P/b) (1+6e/b)= #NAME? ### 276 kN/m² #NAME?
Minimum Pressure pmin = (P/b) (1-6e/b) = #NAME? ### 0 #NAME?
1 TANK LIST
PERCENTAGE
Sr. No. Area TAG NO. EQUIPMENT NAME QTY RATE AMOUNT PERCENT
FROM THE TOTAL COMPLETION AMOUNT
CONTRACT
1 ETP TK1801 Fabrication and Erection Accident Tank and its all accessories (ladder walkway hand 1.00 10% 27,306.36
rail ) 273,063.56 273,063.56 1.29%
2 ETP TK1802 Fabrication and Erection Equalization Tank and its all accessories (ladder walkway hand 1.00 10% 35,166.60
rail ) 351,666.01 351,666.01 1.66%
3 ETP TK1830 Fabrication and Erection Aeration Tank and its all accessories (ladder walkway hand 1.00 10% 59,608.68
rail ) 596,086.75 596,086.75 2.81%
4 ETP TK1850 Fabrication and Erection Sludge Tank and its all accessories (ladder walkway hand rail ) 1.00 10% 20,767.55
207,675.48 207,675.48 0.98%
7 ETP _ FABRICATION AND ERECTION OF STRUCTURE AND ROOF (HOUSE) FOR CAF 40,000.00
774,144.00 774,144.00 3.65%
Total 3,604,940.88 17.01% 391,902.14
33/33 02/14/2022