Professional Documents
Culture Documents
ABSTRACT: The 57 km Gotthard Base Tunnel (GBT) will be the world’s longest railway tunnel. The tunnel
is the central part of the new transalpine rail line in Switzerland. The two single-track tubes are linked by 178
cross passages approximately every 325 m, and two multifunctional stations with an emergency stop station
for each tube located one-third and two-thirds along the base tunnel.
During regular operation, high speed passenger trains with a top speed of 250 km/h as well as slower freight
trains (160 km/h) will run through the tunnel. In the worst case scenario e.g. a fire on a passenger train, the
doors of the cross passages and those of the emergency stations will be essential elements of the safety con-
cept.
This paper gives a short presentation of the safety concept in the case of fire on a passenger train and an over-
view of the most important requirements of the different door-types. It also includes the state of progress of
the special procedure for the commissioning and feed-back from the tests on selected prototypes.
800
suitability criteria in accordance with the Swiss Fed-
eral Law on Government Procurements (BoeB). For
600
this reason, the selection procedure for Lot A is cur-
rently carried out according to the following 9 stages
400 (at the time of the submission of the paper to the edi-
tor, stage 5 has been reached):
200 1. Invitation to tender / Invitation to participate at
the prequalification. On January 10th 2005.
2. Prequalification of applicants according to the
0 weighted suitability criteria. Reduction of the
0
20
40
60
80
100
120
140
160
180
200
220
240
6 FIRST FEED-BACK FROM THE TESTS [1] H.-P. Vetsch, C. Kauer – “Safety of the
Gotthard Base Tunnel” – SIRRT Safety in
At the present time (September 2006) the installation Road and Rail Tunnels, Conference (Madrid)
test, the functionality tests and the endurance tests Spain, April 2001.
have been completed. In October 2006 the fire tests [2] D. Fabbri - "The Gotthard Base Tunnel:
will be carried out and the final reports of the tests Fire / Life Safety System", The 6th Annual
should be completed before the end of the year. Ac- Tunnelling 2004 Conference, Sydney (Austra-
cording to the bidding procedure, and respecting the lia), August 30th & 31st 2004.
copyright of the prototype doors disclosure of the re- [3] AlpTransit Ltd./JV- Gotthard Base Tunnel
sults of the tests is not yet permitted. South - "Publikationstext Los A", SHAB,
First feed-back from the tests confirm the correct January 10th 2005.
decision of the AlpTransit Gotthard Ltd. and of the [4] D. Fabbri, S. Pedrazzini - "The importance
engineers for a selective bidding procedure, with of the safety ASPECTS during the construc-
separate procurement of an independent certified tion works for the new major Alpine tunnels
contractor for the design and assembling of the test- related to the safety during the regular service
ing equipment as well as for test processing. The ex- phase. Parallelisms and differences", AFTES
treme loading in the Gotthard Base Tunnel, endur- 2005 Conference, Chambery (France), October
ance test and the verification of the air-leakage rate 10th – 12th 2005.
through the door sealing represent a real challenge [5] AlpTransit Ltd./JV- Gotthard Base Tunnel
for each bidder. After the completion of the tests, the South - "Publikationstext Los A", SHAB, Oc-
following revision of the submission documents and tober 11th 2005.
technical / financial revision of the offers, based on [6] D. Fabbri, Ch. Strassl - "Rough work
the very interesting and significant results of the Equipment Part-Section", Tunnel 4/2006.
tests, will represent the next important challenge for [7] Pictures provided by AlpTransit Gotthard
the choice of a central element of the fire/live safety Ltd., client.
system of the Gotthard Base Tunnel. [8] Pictures provided by the Joint-Venture PQ
(VSH Sargans & Berner Fachhochschule Biel,
contractor of Lot P.
7 CONCLUSIONS