You are on page 1of 106

GOVERNMENT OF PAKISTAN

MINISTRY OF ENERGY (POWER DIVISION)

NATIONAL TRANSMISSION & DESPATCH COMPANY (NTDC)

National Transmission Modernization Project (NTMP) - I

ISLAMABAD WEST GRID STATION


RESETTLEMENT ACTION PLAN (REVISED)

February 2022
National Transmission and Despatch Company

TABLE OF CONTENTS

1 INTRODUCTION ....................................................................................................................................... 1
1.1 BACKGROUND ........................................................................................................................................... 1
1.2 DESCRIPTION OF ISLAMABAD WEST GRID STATION ........................................................................................... 1
1.2.1 Project location ................................................................................................................................. 1
1.2.2 Project components .......................................................................................................................... 3
1.2.3 Bay and other Substation Equipment ............................................................................................... 7
1.2.4 Control Building ................................................................................................................................ 8
1.2.5 Rest house / Residential Colony ........................................................................................................ 8
1.2.6 Fencing and Landscaping .................................................................................................................. 9
1.2.7 Access Road ...................................................................................................................................... 9
1.2.8 Construction activities....................................................................................................................... 9
1.2.9 Operation ........................................................................................................................................ 10
1.2.10 Implementation schedule ........................................................................................................... 10
1.2.11 Current stage of implementation ............................................................................................... 10
1.3 ANALYSIS OF ALTERNATIVES ....................................................................................................................... 10
1.4 THE PROJECT AREA .................................................................................................................................. 12
1.5 PROJECT BENEFITS AND IMPACTS ................................................................................................................ 12
1.5.1 Socioeconomic benefits................................................................................................................... 12
1.5.2 Impacts ........................................................................................................................................... 13
1.6 OBJECTIVES OF THE RAP ........................................................................................................................... 13
1.7 OUTLINE OF THE RAP ............................................................................................................................... 13
2 PROJECT LAND REQUIREMENTS AND IMPACTS ..................................................................................... 15
2.1 DESCRIPTION OF THE LAND AREA REQUIRED.................................................................................................. 15
2.2 TYPES OF IMPACTS ................................................................................................................................... 15
2.2.1 Impact on Land ............................................................................................................................... 15
2.2.2 Impact on Crops .............................................................................................................................. 15
2.2.3 Impact on Trees .............................................................................................................................. 16
2.2.4 Impact on Structures ....................................................................................................................... 16
2.3 IMPACTS ON LIVELIHOODS ......................................................................................................................... 17
2.4 VULNERABILITY IMPACT ............................................................................................................................. 17
2.5 PUBLIC INFRASTRUCTURE ........................................................................................................................... 17
2.6 SUMMARY OF IMPACTS ............................................................................................................................. 18
3 SOCIOECONOMIC INFORMATION AND PROFILE .................................................................................... 19
3.1 GENERAL ................................................................................................................................................ 19
3.2 METHODOLOGY ....................................................................................................................................... 19
3.3 IDENTIFICATION OF AHS ............................................................................................................................ 19
3.4 PROFILE OF THE RESPONDENTS ................................................................................................................... 20
3.5 DEMOGRAPHIC DATA................................................................................................................................ 21
3.6 EDUCATION AND LITERACY ......................................................................................................................... 21
3.7 ETHNICITY, TRIBES, LANGUAGE AND RELIGION ............................................................................................... 21
3.8 LIVELIHOOD SOURCES ............................................................................................................................... 22
3.9 HOUSEHOLD INCOME................................................................................................................................ 22
3.10 HOUSEHOLD POSSESSIONS ......................................................................................................................... 23
3.11 LAND HOLDING........................................................................................................................................ 23
3.12 CROPS, FRUITS AND VEGETABLES ................................................................................................................ 24
3.13 LIVESTOCK .............................................................................................................................................. 24
3.14 ACCESS TO INFRASTRUCTURE ...................................................................................................................... 24
3.15 HOUSING................................................................................................................................................ 25
3.16 GENDER ANALYSIS.................................................................................................................................... 26
3.16.1 Female participation in economic activities ............................................................................... 26
3.16.2 Concerns of Women related to the Project ................................................................................ 27

i
National Transmission and Despatch Company

4 LEGAL AND POLICY FRAMEWORK .......................................................................................................... 28


4.1 GENERAL ................................................................................................................................................ 28
4.2 NATIONAL LEGAL INSTRUMENTS ................................................................................................................. 28
4.2.1 Constitution of the Islamic Republic of Pakistan ............................................................................. 28
4.2.2 The LA Act (1894) and Limitations .................................................................................................. 28
4.3 GAP ANALYSIS BETWEEN LAND ACQUISITION ACT AND WORLD BANK POLICIES .................................................... 28
4.4 NTDC PRACTICES, FRAMEWORK FOR LA AND VALUATION ............................................................................... 31
4.5 COMPLIANCE OF WB OP 4.12 IR POLICY..................................................................................................... 32
4.6 REFLECTIONS AND LESSON LEARNED ............................................................................................................ 33
4.7 ENTITLEMENTS ........................................................................................................................................ 33
4.8 ENTITLEMENT MATRIX .............................................................................................................................. 34
4.9 CUT-OFF DATE ........................................................................................................................................ 36
5 LIVELIHOOD RESTORATION ................................................................................................................... 37
5.1 LIVELIHOOD DISTURBANCE ALLOWANCE ....................................................................................................... 37
5.2 VULNERABILITY ALLOWANCE ...................................................................................................................... 37
5.3 TRAINING AND EMPLOYMENT ..................................................................................................................... 37
6 STAKEHOLDERS CONSULTATION AND RESPONSES ................................................................................ 38
6.1 GENERAL ................................................................................................................................................ 38
6.2 MAPPING OF STAKEHOLDERS...................................................................................................................... 38
6.3 CONSULTATION WITH STAKEHOLDERS .......................................................................................................... 38
6.4 CONSULTATION APPROACH AND FRAMEWORK............................................................................................... 39
6.5 CONSULTATIONS CONDUCTED .................................................................................................................... 40
6.6 AP’S CONCERNS AND PROJECT RESPONSE..................................................................................................... 41
6.7 LOCAL RESPONSES TO THE PROJECT ............................................................................................................. 43
6.8 WOMEN INVOLVEMENT IN THE CONSULTATION PROCESS ................................................................................ 44
6.8.1 Overview of the Process .................................................................................................................. 44
6.8.2 Women views and concerns about the Project ............................................................................... 44
6.9 DISCLOSURE OF RAP ................................................................................................................................ 45
6.10 CONSULTATION PLAN DURING PROJECT IMPLEMENTATION............................................................................... 45
7 GRIEVANCE REDRESS MECHANISM........................................................................................................ 48
7.1 INTRODUCTION ........................................................................................................................................ 48
7.2 STRUCTURE OF THE GRIEVANCE REDRESS MECHANISM .................................................................................... 48
7.3 GRIEVANCE REDRESS MECHANISM .............................................................................................................. 50
7.3.1 Grievance Redress Procedure.......................................................................................................... 50
7.3.2 Follow Up and Close Out ................................................................................................................. 50
7.4 DOCUMENTATION OF GRC CASES ............................................................................................................... 51
7.5 CURRENT OPERATING STATUS OF GRM ....................................................................................................... 51
8 INSTITUTIONAL SETUP FOR RAP IMPLEMENTATION .............................................................................. 52
8.1 GENERAL ................................................................................................................................................ 52
8.2 INSTITUTIONAL SETUP ............................................................................................................................... 52
8.2.1 The PMU ......................................................................................................................................... 52
8.2.2 The ESIC........................................................................................................................................... 52
8.2.3 Field-Level Construction Camp Office ............................................................................................. 53
8.2.4 Project Implementation Consultants (PIC) ...................................................................................... 53
8.2.5 Coordination with Government Departments ................................................................................ 54
8.2.6 Project Affected Persons’ Committee ............................................................................................. 55
8.2.7 Independent Monitoring Consultant (IMC) ..................................................................................... 55
8.2.8 Grievance Redress Committees (GRC)............................................................................................. 55
8.2.9 District Governments ...................................................................................................................... 55
8.3 ORGANOGRAM ........................................................................................................................................ 56
8.4 CAPACITY BUILDING AND SAFEGUARD TRAINING ............................................................................................ 56
8.5 IMPLEMENTATION SCHEDULE ..................................................................................................................... 56

ii
National Transmission and Despatch Company

9 COST AND BUDGET ................................................................................................................................ 59


9.1 GENERAL ................................................................................................................................................ 59
9.2 PROVISIONS FOR RESETTLEMENT BUDGET ..................................................................................................... 59
9.3 ITEMIZED COST SUMMARY ......................................................................................................................... 60
9.3.1 Land ................................................................................................................................................ 60
9.3.2 Crops ............................................................................................................................................... 60
9.3.3 Trees................................................................................................................................................ 60
9.3.4 Structures ........................................................................................................................................ 60
9.3.5 Vulnerability Allowance .................................................................................................................. 61
9.3.6 Livelihood Disturbance Allowance .................................................................................................. 61
9.3.7 Relocation Allowance...................................................................................................................... 61
9.4 SUMMARY OF BUDGET .............................................................................................................................. 61
10 MONITORING AND EVALUATION .......................................................................................................... 63
10.1 RAP MONITORING ARRANGEMENTS ........................................................................................................... 63
10.2 MONITORING INDICATORS ......................................................................................................................... 63
10.3 INTERNAL MONITORING ............................................................................................................................ 63
10.4 EXTERNAL MONITORING AND EVALUATION ................................................................................................... 64
10.5 MONITORING DATABASE MANAGEMENT ...................................................................................................... 65
10.6 REPORTING AND DISCLOSURE ..................................................................................................................... 65
10.7 POST-PROJECT EVALUATION ...................................................................................................................... 66
ANNEX A: QUESTIONNAIRES FOR SOCIOECONOMIC AND CENSUS SURVEYS ................................................. 68
1.1..................................................................................................................................................................... 80
ANNEX B: LIST OF AFFECTED PERSONS CONSULTED ....................................................................................... 83
ANNEX C - TOR FOR MONITORING AND EVALUATION SPECIALIST ................................................................. 87
ANNEX D – EVIDENCE OF SURVEYS AND CONSULTATIONS............................................................................. 90

iii
National Transmission and Despatch Company

LIST OF TABLES
TABLE 1-1: SITE COORDINATES 3
TABLE 1-2: TYPICAL SUBSTATION COMPONENTS AND THEIR FUNCTIONS 7
TABLE 1-3: COMPARISON OF ALTERNATIVES FOR ISLAMABAD WEST GRID STATION 11
TABLE 2-1: DETAILS ON LAND TO BE ACQUIRED 15
TABLE 2-2: CROPS IN THE AFFECTED AREA 16
TABLE 2-3: SUMMARY OF RESETTLEMENT IMPACTS 18
TABLE 3-1: SETTLEMENT TYPES BY LOCATION 20
TABLE 3-2: DETAILS OF THE RESPONDENTS 20
TABLE 3-3: AGE DISTRIBUTION OF AFFECTED PERSONS 21
TABLE 3-4: LITERACY OF AFFECTED HOUSEHOLDS 21
TABLE 3-5: DISTRIBUTION OF RESPONDENTS REGARDING MAIN OCCUPATION 22
TABLE 3-6: MONTHLY INCOME OF SURVEYED HOUSEHOLDS 23
TABLE 3-7: LAND HOLDING SIZE 23
TABLE 3-8: DETAILS OF CROPS GROWN AND INCOME 24
TABLE 3-9: LIVESTOCK IN THE PROJECT AREA 24
TABLE 3-10: ACCESS TO SOCIAL AMENITIES IN THE PROJECT AREA 25
TABLE 3-11: WOMEN PARTICIPATION IN VARIOUS ACTIVITIES 26
TABLE 3-12: PARTICIPATION OF WOMEN IN ECONOMIC ACTIVITIES 26
TABLE 4-1: WB OP 4.12 INVOLUNTARY RESETTLEMENT & PAKISTAN LAND ACQUISITION ACT 29
TABLE 4-2: ENTITLEMENT MATRIX 35
TABLE 6-1: PRIMARY AND SECONDARY STAKEHOLDERS 38
TABLE 6-2: FRAMEWORK FOR CONSULTATION 39
TABLE 6-3: SUMMARY OF KEY CONCERNS AND RESPONSES 41
TABLE 6-4: CONSULTATION AND PARTICIPATION FRAMEWORK 45
TABLE 9-1: VULNERABILITY ASSISTANCE TO THE APS 61
TABLE 9-2: SUMMARY OF COST 62

LIST OF FIGURES
FIGURE 1-1: LOCATION MAP OF THE ISLAMABAD WEST GRID STATION .............................................................. 2
FIGURE 1-2: LOCATION OF THE PROPOSED GRID STATION SITE (SATELLITE IMAGERY) ........................................ 2
FIGURE 1-3: TYPICAL GRID STATION CONFIGURATION ......................................................................................... 7
FIGURE 2-1: AFFECTED TREES IN THE PROJECT AREA .................................................................................... 16
FIGURE 2-2 BUILT STRUCTURES IN THE PROJECT AREA ................................................................................ 17
FIGURE 8-1: INSTITUTIONAL SET-UP FOR THE IMPLEMENTATION OF RAP ......................................................... 57
FIGURE 8-2: RAP IMPLEMENTATION SCHEDULE ................................................................................................. 58

iv
National Transmission and Despatch Company

ABBREVIATIONS

APs Affected Persons


APCs Affected Persons Committees
BP Bank Procedure
CAP Corrective Action Plan
CCR Community Complaint Register
DCO District Coordination Officer
DHP Dasu Hydropower Project
Ft Foot or Feet
FGD Focus Group Discussion
GoP Government of Pakistan
GRM Grievance Redress Mechanism
GRC Grievance Redress Committee
IMC Independent Monitoring and Consultant
IP Indigenous People
Km Kilometers
LAA Land Acquisition Act, 1894
LAC Land Acquisition Collector
LAR Land Acquisition and Resettlement
LARF Land Acquisition and Resettlement Framework
M&E Monitoring and Evaluation
NTDC National Transmission and Dispatch Company
OP Operational Policy
OPL Official Poverty Line
PKR Pakistan Rupees
PMU Project Management Unit
RAP Resettlement Action Plan
RU Resettlement Unit
sft Square Feet
T5HP Tarbela Fifth Extension Hydropower Project
TOR Terms of Reference
USD US Dollar
WAPDA Water and Power Development Authority
WB World Bank
Currency unit: Pak Rupees
Currency exchange rate: PKR 167 equals 1 US$ (Sep 2021)

v
National Transmission and Despatch Company

Definition of Key Terms

Asset Inventory A complete count and measurements and details of all property that will
be acquired.
Resettlement Cash paid to cover resettlement-related expenses other than losses of
Allowance immoveable assets paid as compensation. A moving allowance can be
paid to people who have to relocate as a result of the project impact. An
allowance is distinguished from compensation, which compensates for
the loss of an immoveable asset due to acquisition.
Baseline A set of pre-project conditions used as a basis for the project.
Compensation Payment in cash or in-kind for an asset or resource acquired by the
project.
Customary Law A law passed down through oral tradition, which has now been adopted
by the community as riwaj to use rights and management of natural
resources.
Cut-off-Date The cut-off date is the date the census begins. The cut-off date
determines the eligibility for compensation and entitlements.
Economic Loss of income streams or means of livelihood resulting from loss of land
Displacement and/or restricted access to land and other resources resulting from
project intervention.
Grievance Mechanism This is an extra-judicial mechanism by which project-affected persons
or the general public can raise their concerns to project authority.
Involuntary Involuntary or forced resettlement in project context without any
Resettlement recourse or power to refuse resettlement.
Jirga Jirga, a traditional dispute resolution mechanism, refers to the assembly
of local elders/maliks to resolve the community concerns.
Kharif Summer cropping season of the year (15th April – 15th September)
Katcha House or building made of un-burnt bricks and/or mud with
wooden/thatched roof.
Rabi Winter cropping season of the year (15 September – 15th April)
Mouza/Village A demarcated territory, for which a separate revenue record (Cadastral
map) is maintained by the Revenue Department.
Pacca A house/ structure is considered pacca, if both the walls and roof of the
house are made of material that includes bricks, cement, sheets, slates,
corrugated iron, zinc or other metal sheets, bricks, lime, and stone or
RBC/RCC concrete.
Patwari Revenue record keeper/clerk at village level.
Project Affected Person Persons (or households) affected by project-related changes in use
or Household of land, water, or other natural resources either in full or in part,
permanently or temporarily.
Physical displacement Loss of shelter and assets resulting from the acquisition of land
associated with a project that requires the affected person(s) to move to
another location.

Rehabilitation Re-establishing incomes, livelihoods, living, and social systems at least


to the pre-project levels
Resettlement Strategy The approaches used to assist people in their efforts to improve (or at
least to restore) their incomes, livelihoods, and standards of living in real
terms after resettlement.

vi
National Transmission and Despatch Company

Resettlement Action A time-bound action plan with a budget setting out resettlement
Plan strategy, objectives, entitlement, actions, responsibilities, monitoring
and evaluation
Resettlement Resettlement entitlements with respect to a particular eligibility
Entitlements category are the sum total of compensation and other forms of
assistance provided to displaced persons in the respective eligibility
category.
Replacement value Cost of replacing lost assets and incomes without depreciation,
including cost of transactions (taxes, duties and any other allied
expenses)
Semi Pacca A house/structure is considered Semi Pacca, if both the walls and roof
of the house are made of material that includes wood, planks, grass,
leaves and wall are made of bricks walls with mud masonry or un-burnt
brick.
Stakeholders Any and all individuals, groups, organizations, and institutions
interested in and potentially affected by a project or having the ability to
influence a project.
Socioeconomic A complete and accurate survey, (i.e., census) of the project-affected
Census/Survey population. The survey focuses on income-earning activities and other
socioeconomic indicators.
Shamelat Communal land
Tehsil Tehsil is a sub-district, (i.e., the layer of administration below a district).
Vulnerable groups Persons below poverty-line, physically challenged, infirm, and women-
headed households who might suffer disproportionately from
resettlement effects.

vii
National Transmission and Despatch Company

EXECUTIVE SUMMARY

The project

The National Transmission Modernization 1 Project by the Government of Pakistan (GOP)


aims at increasing the availability, reliability and efficiency of selected segments of the
national transmission system in Pakistan. One of the components of the Project includes
investments to develop key power grid stations essential for delivery of power to load
centers in Pakistan. These include the development of a new grid station, known as
‘Islamabad West’ at 30 km west of Islamabad. National Transmission and Dispatch
Company (NTDC) is the executing agency of the Project.

The proposed project (a 765/500/220 kV grid station) will be constructed in village Kamalpur
Miyan Tehsil Fateh Jang, District Attock in Punjab to receive power from Tarbela Fifth
Extension Hydropower Project (T5HP) and Dasu Hydropower Project (DHP). The proposed
site located in Kamalpur Miyan has been selected after an evaluation of three alternative
sites in Kamalpur Miyan, Behlol Pathar Garh and Mouza Chaharat on the basis of
minimizing land acquisition, socioeconomic impacts, technical requirements and ensuring
ease of access. In addition to these three sites another piece of land in Lundi Dhoke Gondal
near village Kot was assessed by the NTDC but later on it was rejected due to the technical
reasons and narrow access.

The Resettlement Action Plan (RAP)

The present RAP has been prepared based on 100% census of Affected Persons (APs) in
terms of loss of land, crops, trees, structures and livelihoods. In addition, socio-economic
surveys of affected households were carried out in July 2019 and November-December
2020 to obtain a detailed understanding of the socio-economic conditions of the APs and
to provide baseline data for the monitoring of the implementation of the RAP and the
impacts of the project. The surveys were supported by Focus Group Discussions (FGDs)
with men and women conducted in the project area and consultation with stakeholders.

Project Impact

The project involves the acquisition of 202 acres of agricultural land (mostly wheat and
maize), felling of 83 trees (11 of which are fruit trees) and resettlement of 16 households.
The affected households are 274 and the total number of APs is 1,288. A total sixty (60)
households among the 274 affected ones are considered vulnerable, as their income is
below the official poverty line or are headed by a female. A summary of the impacts is
provided below.

Resettlement Impacts Quantity Nature of Impact


A. Land to be acquired
Agricultural land 202 acres Loss of land

i
National Transmission and Despatch Company

Resettlement Impacts Quantity Nature of Impact


Total 202 acres
B. Affected Structures
Total Number of Residential 37 Loss of structure
Structures
Total affected structures 37
C. Affected crops
Total area of agriculture land to be 202 acres Loss of crops and crop
impacted by Grid Station income
construction
Total 202 acres
D. Public Infrastructure (road) 2 Km Upgrade of access road
Agricultural land 2 acres
E. Affected trees
1 Privately owned Wood/ Timber 72 Loss of trees
Trees
2 Privately owned Fruit Trees 11 Loss of trees
Total affected trees 83
F. Project Affected Households 274
Number of affected persons 1288
1 Households losing crops 274
2 Households losing trees 54
3 Households losing structures 16
4 Vulnerable households 60 HHs below the OPL and
women-headed HHs
5 APs with impacts on livelihoods 647 APs losing their land while
due to loss of land their livelihood is based on
agriculture

Cut-off date

March 5, 2016 has been established as the cut–off-date for the census survey in the project
area. An additional cut-off date will be set for affected people losing land and assets as a
result of the extension of the road connecting the Grid Station with the Brahma – Bahlol
road. The design of the road extension will be carried out by the Contractor.

Anyone moving to the project site after that date will not be eligible for assistance and/or
compensation. This was communicated to the APs during the consultation meetings.
Section 4 was also issued on March 5, 2016. The invoking of section 4 was also shared
with the APs.

ii
National Transmission and Despatch Company

Consultation

The first round of consultation began in October 2015, followed by a second-round during
November 2015 till March 2016. The third round of consultation was carried out in August
2019 for the needs of the revision of the RAP. These consultations were held in a
participatory manner through key informants’ interviews, structured surveys, informal group
meetings and consultative workshops. The main topic discussed included a description of
project components, project activities and their impact assessment; land acquisition and
resettlement process, eligibility criteria, compensation package, entitlement matrix;
grievances redress procedures and general concerns of the APs. In total 275 individuals
attended the consultation meetings, among which 126 women.

A final consultation round was undertaken at the end of November – beginning of


December 2020, in the form of a Workshop where affected people had the chance to
receive up to date information on the progress of the project, voice a number of concerns
and assist the project team to update the socioeconomic profile of the local population.

The general concerns of the APs were focused on the payment of compensation (which
rates will be used), forms of payment, employment in the construction activities, shifting of
grid station site and adequate mechanism for grievance redress. APs were informed that
NTDC is working with the local government to finalize and come up with the replacement
cost of the lost assets and compensation disbursement will commence once the
compensation package is finalized. Similarly, the jobs will be provided preferably to local
people in the construction activities. NTDC has also established a Grievance Redress
Mechanism (GRM) to receive and address the grievances from the APs. APs were also
informed that the land selected for the grid station cannot be changed in this advance stage
as a lot of technical, environmental and social studies has been conducted for this site and
some land has also been purchased through private negotiation. The RAP will be disclosed
to the APs and key stakeholders and posted on the NTDC website and other prominent
places. NGOs (The Citizen Foundation and Al-Khidmat Foundation) were also consulted.
The feedback received from these NGOs includes the preference given to locals for project
hiring and timely payment of compensation to the APs.

Policy Framework

NTDC will follow a mixed method combining the use of eminent domain under the 1894 LA
Act and private negotiations for land acquisition. It is expected that this will help to put the
acquisition process on a fast track for the construction of the grid station. The LA Act has
been used to issue Section 4 to “freeze” the land area from any future transitions. The
NTDC ‘negotiation committee” will take the responsibility for negotiation and agreement
with the land owners on rates. Once the agreement is reached, the agreed compensation
will be disbursed through the NTDC. Should the negotiations fail, NTDC will resort to
applying eminent domain and secure acquisition of the land through the District Collector
by applying Section 4 of the LA Act of 1894. Discussion and negotiations have already

iii
National Transmission and Despatch Company

started by NTDC with the committee of the APs to develop a base price for RAP planning
purposes, which is used in the matrix and the budget.

Entitlements

Compensation and various forms of assistance are proposed for the APs in a way that will
ensure their standards of living to at least their pre-project levels. The Entitlement matrix
developed for the APs is given below.

Entitlement Matrix

Type of Loss Specification Eligibility Entitlements

1. LAND, TREES, CROPS AND ASSETS

Owners Cash compensation based on negotiation


(titleholder, or ensuring replacement cost above the market
Impact on
Land loss holder of value, plus all transaction costs, applicable
Land
traditional fees and taxes and any other payment
rights) applicable.
Negotiated cash compensation for timber trees
at current market rate or above for timber value
Trees Affected trees Owners
of species at current volume, and required
inputs to replace trees.
Cash compensation at current market rate
proportionate to size of lost plot, based on crop
type and highest average yield in the project
Crops Affected crops Owners
area to be determined by NTDC Team with
assistance from relevant departments /
agencies.
Cash compensation at replacement rates for
Houses/ All relevant affected structure and other fixed assets free of
Structures APs salvageable materials, depreciation and
transaction costs.

2. RELOCATION ALLOWANCE

Transport and Provision of allowance to cover transport


All APs
transitional expenses (PKR 5,000) and livelihood
Relocation affected by
livelihood expenses for three months (PKR 78,000 per
relocation
costs household).
3. LIVELIHOOD DISTURBANCE ALLOWANCE

Loss of viable Provision of livelihood disturbance allowance


Loss of agricultural amounting to PKR 92160/Acre of land equal to
Owners of
agriculture- land without the market value of gross harvest of the
agricultural
based availability of affected land for 1 year (inclusive of winter and
land
livelihood alternative summer crops) to all APs who lose their land
land and agriculture is their primary occupation
4. VULNERABILITY ALLOWANCE

Provision of one time subsistence allowance


Livelihood
Vulnerable All vulnerable amounting to PKR 78,000 (equal to 3 months
improvement
Aps APs of PKR 26,000 as per Official Poverty Line
and removal
(OPL)) to all APs whose income is below the

iv
National Transmission and Despatch Company

of OPL or are women-headed HHs, disabled or


disadvantages child headed households. Preferential
selection for project related employment.

Institutional arrangements

A Project Management Unit (PMU) has been established within NTDC and has been
mandated to manage the design, procurement, and construction activities of the project.
The PMU is headed by the Chief Engineer/Project Director. For the implementation of RAP,
several entities will be involved including the PMU itself, Environment and Social Impact
Cell (ESIC) established within PMU, Project Consultants responsible for design and
construction supervision of the project, relevant government departments, APs, and others.

PMU is responsible for the implementation of RAP in a satisfactory manner and in


compliance with project safeguard policy framework. NTDC will manage all safeguard
related matters through its Camp Office (CO) in coordination with local government. At
PMU level, the ESIC Team will liaise with CO with close coordination of relevant
dept./agencies and affected communities. ESIC will review and prepare safeguard
documents (internal monitoring reports and any Corrective Action Plan (CAP)) according
to approved RAP. For this reason, the ESIC will provide the necessary training and capacity
building to field staff including contractor, consultant, Grievance Redress Committee (GRC)
and APs. An independent monitoring consultant will also be engaged for the monitoring
and evaluation of RAP implementation.

Grievance Redress Mechanism

A Grievance Redress Mechanism (GRM) has been designed and established to ensure
that the complaints and grievances of affected households are addressed and resolved in
a timely and satisfactory manner. A two-tier grievance redress mechanism (GRM) (Project
Level, and NTDC - Head Quarters level) will be established. The APs will first approach
NTDC’s ESIC Team for the redress of grievances. In case the grievances are not resolved
at local level, the case will be forwarded to NTDC HQ level for resolution. If not, aggrieved
persons or disputants can subsequently move to court of law. GRM will ensure the access
of APs to register their complaint and further its resolution that are consistent with local
laws and WB involuntary resettlement policy.

RAP implementation schedule and budget

The RAP implementation schedule for the proposed project includes RAP preparation,
disclosure, disbursement of compensation with its internal and external monitoring,
evaluation and reporting. The construction of Islamabad West Grid Station will be
completed by the end of 2025. Payment of compensation and allowances will be completed
by June 2022 to ensure that compensation is paid prior to commencement of civil works.
Public consultation, internal monitoring and grievance redress will be undertaken

v
National Transmission and Despatch Company

throughout the project duration. However, the schedule is subject to modification depending
on the progress of the project activities.

The total RAP budget amounts to PKR 1,260.62 Million (7.5 million USD). The budget
includes land cost of PKR 887.7 Million, crop compensation PKR 18.8 Million, trees
compensation PKR 0.9 Million, compensation for structures PKR 12.3 Million, Allowances
and training cost PKR 34.7 Million, monitoring and evaluation cost PKR 47.8 Million and
contingencies cost PKR 238.8 Million.

RAP monitoring and evaluation

RAP activities under the Project will be subjected to monitoring and evaluation. NTDC will
be responsible for internal monitoring of resettlement activities ensuring that the draft RAP
is finalized and implemented according to approved project policy. The result of internal
monitoring will be included in the monthly progress reports to be submitted to the WB.
NTDC will engage the services of an independent monitor for monitoring of the RAP.
External monitoring and evaluation reports will be prepared quarterly and semi-annually
during the implementation of the project. Based on the external monitoring and evaluation
report, if significant issues are identified, a Corrective Action Plan (CAP) will be prepared.
A post-project audit and evaluation will also be conducted by NTDC once the project
construction work is complete.

vi
National Transmission and Despatch Company

1 INTRODUCTION

1.1 Background

The National Transmission Modernization 1 Project (the Project) is the proposed Project
by the Government of Pakistan (GoP) to increase the availability, reliability and efficiency
of selected segments of the national transmission system in Pakistan. One of the
components of the Project includes investments to develop key power grid stations
essential for delivery of power to load centers in Pakistan. These, among other transmission
lines and grid stations, include development of a new grid station, known as ‘Islamabad
West’ located at 30 km west of Islamabad to receive power from the proposed Tarbela 5th
Extension Hydropower Project (T5HP) and Dasu Hydropower Project (DHP). The power
from both of these projects will be evacuated through a new 500 kV transmission line from
T5HP and 765kV transmission line from DHP to the new Islamabad West Grid Station. The
project will be constructed on private land of Village Kamalpur Miyan, District Attock, (as
shown in Figure 1-1).

A Resettlement Action Plan (RAP) was prepared for the project in 2017, describing the
legal framework for land acquisition and compensation, resettlement and social impact of
the project, socioeconomic baselines of the project affected persons, eligibility and
entitlement, compensation and rehabilitation plan and payment procedure, details of
consultations, institutional arrangements, Grievance Redress Mechanism (GRM),
monitoring and evaluation framework and a time bound action plan. The present revision
of the RAP is based on additional surveys carried out in 2019 and 2020 and
addresses technical changes to the project as well as potential changes in the
socioeconomic characteristics of the project area.

1.2 Description of Islamabad West Grid Station

1.2.1 Project location

The 765/500/220 kV Grid Station is proposed to be established on private land of village


Kamalpur Miyan, Tehsil Fateh Jang and district Attock, Punjab. The location of the
proposed grid station is shown in Figure 1-1 and a satellite imagery of the proposed site is
given in Figure 1-2.

1
National Transmission and Despatch Company

Figure 1-1: Location Map of the Islamabad West Grid Station

Figure 1-2: Location of the Proposed Grid Station Site (Satellite Imagery)

2
National Transmission and Despatch Company

The 765/500/220kV Grid Station will be constructed in an area of approx. 1000m x 800m.
The site coordinates are given below.

Table 1-1: Site coordinates


Latitude Longitude
IW-A 33°41'39.30"N 72°39'56.02"E
IW-B 33°41'52.31"N 72°40'7.00"E
IW-C 33°42'3.02"N 72°40'26.99"E
IW-D 33°41'36.99"N 72°40'43.31"E
IW-E 33°41'29.17"N 72°40'23.58"E
IW-F 33°41'19.20"N 72°40'11.05"E
Source: NTDC, 2019

1.2.2 Project components

The proposed 765/500/220 kV Islamabad West Grid Station (IWGS) will be constructed in
202 acres of agricultural land and will be connected to the following Grid Stations:

• Mansehra - by two (2) new 765 kV transmission lines (approximate length 108 km)

Furthermore, the new 765/500/220/132 kV Islamabad West Grid Station will be connected
by eight (8) new 500 kV transmission lines with the following substations:

• Tarbela - by one (1) new 500 kV transmission line (LILO Tarbela-Rewat New)
• Rewat New - by one (1) new 500 kV transmission line
• Ghazi Brotha - by one (1) new 500 kV transmission line (LILO Ghazi Brotha-Rewat
New)
• Rewat New - by one (1) new 500 kV transmission line
• Maira - by two (2) new 500 kV transmission lines
• Tarbela 5th Extension - by two (2) new 500 kV transmission lines.

In addition, the new 765/500/220/132 kV Islamabad West Grid Station will be connected by
four (4) new 220 kV transmission lines with the following substations:

• ISPR - by one (1) 220 kV transmission line (LILO ISPR-Mansehra-Haripur)


• Mansahra - by one (1) 220 kV transmission line
• ISPR - by one (1) 220 kV transmission line (LILO Tarbela-Kamra)
• Tarbela - by one (1) 220 kV transmission line

Finally, the new 765/500/220/132 kV Islamabad West Grid Station will be connected by six
(6) new 132 kV transmission lines. The corresponding substations will be defined at a
later stage.
The Air Insulated Substation (AIS) configuration will be as follows:

• a 765 kV AIS switchgear with five (5) bays and space for future extension by seven (7)
bays, with:

3
National Transmission and Despatch Company

– 765 kV one and half breaker busbar system (six (6) diameters)
– Five (5) Diameters shall be built in this phase and space for one (1) Diameter
shall be reserved for further extension
– two (2) 765 kV transmission line bays
– two (2) 765 kV reactor bays incorporated in transmission line bays
– three (3) 765 kV transformer bays
• three (3) autotransformer banks of three single-phase units 765/500/33 kV, 3 x 400
MVA.
– two (2) spare single-phase autotransformer unit 765/500/33 kV, 400 MVA
• two (2) reactor banks of three single-phase 765 kV, 3 x 80 MVAr
– one (1) spare single-phase reactor units 765 kV, 80 MVAr
• space for future extension by seven (7) 765 kV transmission line or transformer bays

• a 500 kV AIS switchgear with fourteen (14) bays and space for future extension by four
(4) bays, with:
– 500 kV one and half breaker busbar system (nine (9) diameters)
– Eight (8) Diameters shall be built in this phase and space for one (1) Diameter
shall be reserved for further extension
– eight (8) 500 kV transmission line bays
– six (6) 500 kV transformer bays
• three (3) autotransformer banks of three single-phase units 500/220/22 kV, 3 x 250
MVA.
– two (2) spare single-phase autotransformer units 500/220/22 kV, 250 MVA
• space for future extension by four (4) 500 kV transmission line or transformer bays

• 220 kV AIS switchgear with ten (10) bays and space for future extension by ten (10)
bays, with:
– 220 kV one and half breaker busbar system (10 diameters)
– four (4) 220 kV transmission line bays
– six (6) 220 kV transformer bays
• three (3) three-phase autotransformers 220/132/11 kV, 250 MVA.
• space for future extension by ten (10) 220 kV transmission line bays or transformer bays

• 132 kV AIS switchgear with twelve (12) bays and space for future extension by five (5)
bays, with:
– 132 kV double busbar system
– six (6) 132 kV transmission line bays
– five (5) 132 kV transformer bays
– one (1) 132 kV bus coupler bays
• two (2) three-phase power transformers 132/11 kV, 13 MVA.
• space for future extension by five (5) 132 kV transmission line bays or transformer bays

• 11 kV GIS switchgear with seven (7) bays:


– 11 kV single busbar system
– two (2) 11 kV transformer bays
– two (2) 11 kV auxiliary transformer bays
– two (2) 11 kV cable/transmission line bays
– one (1) 11 kV bus section bay
• two (2) three-phase, 11/0.4 kV, 1.000 kVA, auxiliary power transformers

4
National Transmission and Despatch Company

• metering, for each transmission line and each transformer


• associated substation control and monitoring system and relay protection,
including:
– protection panels
♦ protection panels I & II for each transmission line
♦ protection panels I & II for each transformer
♦ protection panels, including synchronisation, for each reactor
♦ breaker failure panel for each diameter
♦ trip circuit supervising panel for each diameter
♦ busbar protection panel
– control panels
♦ control panels for each diameter
♦ common control panel for each voltage level
♦ station level synchronizing panel
♦ station level fault recorder panel
♦ working station
♦ redundant working station
– local control cubicles for each:
♦ busbar
♦ line breaker
♦ middle breaker
♦ transformer breaker
♦ reactor

• AC & DC auxiliary power supply, including:


– AC switchgears
– DC switchgears, for each voltage level
– Two 220 V DC ACU batteries, minimum 800 Ah, for 765 kV voltage level
– Two 220 V DC ACU batteries, minimum 600 Ah, for each 500 kV and 220 kV
voltage level
– Two 110 V DC ACU batteries, minimum 600 Ah, for 132 kV voltage level
– Two 220 V AC/DC battery chargers, minimum 100 A, for each voltage level
– Two 220 V DC/AC inverter, minimum 5 kVA
♦ 220 V DC as control & motor supply voltage for 750 kV, 500 kV and 220 kV voltage
level
♦ 110 V DC as control & motor supply voltage for 132 kV voltage level
♦ DC supply for each voltage level separately
– Two (2) diesel generator sets for complete substation, 0.4 kV, 625 kVA
• telecommunication, including digital PLC for each transmission line
• cables,
• metal structure,
• earthing,
• lightning protection,
• outdoor lighting
• complete outdoor and indoor civil works
• Land development of the complete switchyard area by cutting, land filling, compacting
up to a suitable level including slope protection. The approximate total area of the

5
National Transmission and Despatch Company

substation is 800 x 1000 meters.


• 765 kV, 500 kV, 220 kV, 132 kV, 33 kV, 22 kV and 11 kV gantry foundations,
• 765 kV, 500 kV, 220 kV, 132 kV, 33 kV, 22 kV and 11 kV equipment foundations,
• autotransformer, reactor, power transformer and auxiliary transformer foundations,
• blast walls,
• oil pit
• access road,
• substation main gates and guard houses,
• security boundary wall,
• internal fencing,
• internal roads and parking,
• surface and switchyard drainage system including outfall,
• cable trench including soak pit, PVC pipes, etc.,
• switchyard surface finishing and gravel surfacing
• complete civil, electrical and mechanical works and facilities for:
– one new control building,
– new relay houses,
– one new metering room,
– one new guard house,
– one new service building
– one new Rest house, (12-unit bed Officer rest House)

including foundation works, super structure works, electrical and telecommunication


system, lighting, cooling, heating, ventilation, air-conditioning, finishing works like
rendering, painting, water supply, sanitary, floor finishing, rain water drainage system,
lightning protection, furniture, etc.
• Water supply system including pump house, pump, water reservoir, water pipe lines, etc.,
sewage facilities including septic tank, etc.

A schematic drawing of the proposed facilities are shown in Figure 1-3.

6
National Transmission and Despatch Company

Figure 1-3: Typical Grid Station configuration

1.2.3 Bay and other Substation Equipment

A substation “bay” is the physical location within a substation fenced area where the high
voltage circuit breakers and associated steel transmission line termination structures, high-
voltage switches bus supports, controls, and other equipment are installed. Typical component
of substation and their functions are given in Table 1.2.

Table 1-2: Typical Substation Components and their Functions


Equipment Functions
Transformers To step-down or step-up voltage and transfer power from one current to
another. The windings of such large transformers are immersed in
transformer oil, which is a highly refined mineral oil that is stable at high
temperatures and has excellent electrical insulating properties. Its
functions are to insulate, suppress corona and arcing, and to serve as a
coolant for transformers.
Circuit Breakers Automatic switching during normal or abnormal conditions.
Feeder Bay Steel work housing for circuits.
Reactors Equipment for the efficient operation of long transmission power lines as
they compensate the voltage on power lines to avoid uncontrolled voltage
rise, especially on lightly loaded lines.
Isolators Equipment for de-energising a circuit for maintenance and repair.

7
National Transmission and Despatch Company

Equipment Functions
Bus bars Incoming and outgoing circuits of the same voltage tie into a common
node called a busbar, which consists of a number of tubular conductors
made of aluminum.
Wave trapper Equipment for trapping communication signals sent via the transmission
lines rather than the telephone network.
Loop-in lines Incoming power lines (connected to bus bars).
Loop- out lines Outgoing power lines (connected to bus bars).
Telecommunication Equipment used for remote communication with the sub-station.
mast

1.2.4 Control Building

One control building is required for the substation to house protective relays, control devices,
battery banks for primary control power, and remote monitoring equipment.

The control building will be a two-store building having approximate minimum dimensions
45mx21m, comprising structural, architectural, electrification, fire protection & detection,
lighting protection, fittings and fixtures, HVAC system (including AC units as per calculation &
requirements of room size), water supply arrangements, sewerage systems, fair face bricks,
wood-work, steel/aluminum work, painting / polishing/ whitewashing, complete in all respects
as per Drawings and Specifications and as per NTDC specification P-draft for civil works.

1.2.5 Rest house / Residential Colony

A Rest house (officer rest house) will be built on one side of the grid station. Common drinking
water supply (through groundwater wells) and sewerage facilities (with septic tanks) will be
established to provide water and sanitation facilities to the rest house. Storm water drainage
facilities will be established both in the grid station site and in the rest house. WHO endorsed
standards on EMF (http://www.who.int/peh-emf/standards/en/ - developed by International
Commission on Non-Ionizing Radiation Protection, ICNIRP) will be complied through design
considerations by providing adequate distance from the grid station equipment and the rest
house. Exposure to noise from the grid station equipment will also be evaluated, to comply
with national standards, to provide adequate distance from the grid station and the rest house.

In the future, the rest house may be expanded to a Residential Colony able to house approx.
100 families. The decision on this has not been made yet.

A construction camp to accommodate about 40 to 50 outstation workers will be built within the
proposed grid station area. The camp will include residential quarters, washing areas, kitchen,
toilets, fuel storage, water storage, sewage disposal arrangements, firefighting arrangements,
electric generators, and others.

8
National Transmission and Despatch Company

1.2.6 Fencing and Landscaping

A security fencing (a fencing wall) will be constructed around the entire perimeter of the grid
station to protect sensitive equipment and prevent accidental contact with energized
conductors by third parties.

A 3 m buffer zone with plantation will be developed within the acquired area and around the
fence, and landscaping will be carried out wherever allowed.

1.2.7 Access Road

Access to the Grid Station is provided by an existing asphalt road at the south-southeast
boundary of the site, connecting the Grid Station with the Brahma – Bahlol road, approx. 2 km
to the east. This road will need to be permanently upgraded to provide access for personnel,
material deliveries, vehicles, trucks, heavy equipment, low-boy tractor trailer rigs (used for
moving large transformers), and ongoing maintenance activities. Upgrade will involve the
extension of the road for approx. 4m along its length and the improvement of the asphalt layer.
The design of the road upgrade is not available. It will be carried out by the Contractor.

1.2.8 Construction activities

The process for constructing the new grid station will follow standard NTDC practices. The
key activities in the construction process include the following:

• The major civil works in the grid station area will include construction of foundations
and buildings. The raw material required for these constructions are aggregates, sand,
cement and steel. The exact quantities of these materials required for construction will
only be known at the time of design. However, all these materials will be procured from
the market and no quarry site will be developed under this project.

• The steelwork will then be erected. The transformers, circuit breakers, reactors and
other high voltage equipment will be delivered to site, erected and then commissioned.
During construction when the civil works are being carried out (foundations, buildings,
etc.), there would be approximately 100 to 150 people present on the site at any one
time. Depending on the level and nature of construction activity taking place, there will
be varying numbers of people housed on site within a construction camp. This will be
constructed within the proposed grid station facility. Overall, it is estimated that 200 –
250 staff will be employed in various works (civil, installation, electrical, other) during
project construction.

• Construction will commence with the clearing of vegetation and the levelling and
terracing of the ground surface in those areas where heavy electrical transformers and
other switchgear will stand. Once levelled and terraced, the concrete works and
construction of foundations for the supporting steelwork, transformers and other
switchgear will commence. This will also include the construction of storm water
drainage pipes, slabs, bund walls, a control room, small buildings and storage areas

9
National Transmission and Despatch Company

that are needed.

• All open areas between the transformer plinths and other switchgear foundations will
be covered with about a 100 mm layer of 25 – 38 mm crushed stone.

• Waste generation from the construction works is estimated to be about 140 kg/day
(considering an average per capita waste generation in Pakistan, which ranges from
0.286 to 0.612 kg/capita/day). These wastes will be disposed at the local municipal
waste disposal sites. Since the project site is located in the wider Islamabad area, the
municipal waste disposal site is already available. No new waste disposal sites will be
developed for the project.

1.2.9 Operation

Grid stations in grid system of NTDC are designed and constructed for operation, supervision
and control by the staff around the clock, unlike the grid system of many developed countries
where the grid stations are remote operated, supervised and controlled at central control
centers.

The operation staff at control rooms of grid stations comprises shift engineers, operators,
attendants, etc. and perform duty in three shifts, i.e., morning shift, evening shift and night
shift. The operation staff supervises and controls the grid station in accordance with the
provisions made in the design and construction of the equipment and transmission lines and
in compliance of the instructions of the system operator.

1.2.10 Implementation schedule

The construction period for the Islamabad West Grid Station is expected to take 36 months.
Construction is expected to start in June 2022 and the station will be ready for commissioning
before the end of 2025.

1.2.11 Current stage of implementation

The detailed design for the substation has been completed and the procurement stage is
currently on-going. The submission of technical bids is expected at the end of September /
beginning of October 2021. The opening of financial bids is anticipated at the beginning of
December 2021. The notification of awards to the successful bidder is planned for the end of
January 2022.

1.3 Analysis of Alternatives

A total of three sites were assessed for the selection of the location of the proposed Islamabad
West Grid Station. All these sites are located in Fateh Jang Tehsil of Attock District. These
are:

• Option 1: Kamalpur Miyan

10
National Transmission and Despatch Company

• Option 2: Brahma Pathergarh


• Option 3: Mouza Chaharat

The key criteria for site selection included technical suitability and minimisation of
environmental and social issues, as described below:

• Suitable and relatively flat land availability


• Type of terrain
• Easy access to Site
• Environmental issues, including likely sensitive/protected areas or species
• Social Issues, including needs for land acquisition, physical resettlement
The evaluation of the location alternatives on the basis of the above-mentioned criteria is
presented in Table 1-3.

Table 1-3: Comparison of alternatives for Islamabad West Grid Station

Criteria Option 1: Option 2: Option 3:


Kamalpur Miyan Brahma Mouza Chaharat
Pathergarh
(recommended)
Suitability of the site Flat and easily Undulating terrain Land form similar to
for grid station. accessible land with sudden Option 2 but with
depressions (of 6 to lesser depressions.
10 m).

Land use The land and Most of the land is Similar to Option 2
surrounding areas being used for
are being used for agricultural purpose,
agricultural purpose while some parts
are left barren. The
surrounding areas
also under
agricultural use
Environmental Environmentally all sites are located in a rural setting and are in
sensitivity agricultural use. No environmental sensitivity or sensitive
receptors are identified in and around the proposed sites
Access roads Access road is A 2 km of access A 1 km of access
available but roads needs to be road needs to be
requires upgrade built built
Land acquisition and Land acquisition is Land acquisition will Land acquisition will
resettlement required for grid be required for both be required for both
station and access grid station and grid station and
road upgrade. access road access road
construction. construction.
Limited need for
physical Limited need for Limited need for
resettlement (10 physical physical
houses). resettlement resettlement
(scattered houses (scattered houses
and warehouses). and warehouses).

11
National Transmission and Despatch Company

In view of the above-mentioned comparison, the site at Kamalpur Miyan was selected as the
preferred option.

In addition to these sites, another site located at Lundi Dhoke Gondal near village Kot in Tehsil
Fateh Jang District Attock was assessed and conditionally approved for construction of this
grid station by the NTDC. Later on, this site was rejected due to the technical reasons and
also due to the narrow access as the existing road needs widening for the transportation of
heavy trailers for auto transformers and other equipment, hence management decided to go
back to the previously recommended site Option 1 (Kamalpur Miyan).

1.4 The Project Area

For the needs of the RAP, the project area is the footprint of the Islamabad West Grid Station
as well as the area for the widening of the access road that will need to be upgraded. There
are a few residencies living with the project footprint, which consists largely of agricultural land.
The loss of land has impacts on income and livelihood of the affected families who live in the
village of Kamalpur Miyan. Therefore, for the purpose of census and other social data, the
project area has been extended to include the adjacent village of Kamalpur Miyan where APs
are located and reside. Potential socioeconomic impacts to the communities or other
environmental impacts are examined in the project ESIA.

1.5 Project Benefits and Impacts

1.5.1 Socioeconomic benefits

Islamabad West Grid Station is one of the key power grid stations to be developed under the
National Transmission Modernization 1 Project with the aim to increase the availability,
reliability and efficiency of selected segments of the national transmission system in Pakistan.
The construction and operation of the Grid Station is expected to:

• Contribute to further electrification of currently non-electrified areas, strengthening of


the grid and improvement of the quality of electricity supply. These benefits will be felt
at regional and local level, in the form of better quality of electricity supply, voltage
improvement and reduction of outages.

• Generate temporary employment opportunities for local contractors and local labor will
be generated during construction. It is estimated that the project construction will utilize
150-200 staff. Although many of these positions will require specialized skills, there
will be employment opportunities for non-skilled staff. The project will seek to maximize
such opportunities for local labor through special conditions in the bidding documents.

• Create business opportunities for small businesses or people providing goods and
services to project construction or its staff (i.e., machinery, trucks, vehicles, catering,
cleaning and entertainment, etc.) during construction.

12
National Transmission and Despatch Company

The project will have positive gender impacts through improved access to electricity or better
electricity supply as improved access to electricity and power will facilitate tasks carried out
by women and girls and thus promote gender equality, women’s empowerment, and girls’
access to education, health care and employment.

1.5.2 Impacts

Adverse project impacts are related to involuntary physical and economic displacement due
to project construction. In specific:

• Loss of land in the footprint of the Grid Station (202 acres). A total of 274 households
(1288 people) are affected;

• Loss of structures in the footprint of the Grid Station. A total of 16 households are
affected;

• Permanent loss of income due to crop and tree loss for Grid Station construction. A
total of 274 households are affected by crop loss and 54 households by tree loss.

• An additional area of approx. 2 acres of agricultural land will be needed for the upgrade
of the access road, the actual figure depending on the road design. No assets /
structures are affected by land acquisition due to road upgrade.

The project addresses these impacts through compensations and livelihood restoration
allowances as explained in subsequent sections of this report.

1.6 Objectives of the RAP

The primary objective of the RAP is, thus, to provide necessary details for compensation by
identifying (i) the extent of losses; (ii) the policy framework for compensation payments,
income restoration, (iii) eligibility and entitlement (iv) mechanisms for timely disclosure of
information to the APs and other stakeholders (v) institutional arrangements for participation
and implementation; (vi) grievance redress mechanism; (vii) responsibilities for monitoring the
implementation process and (vii) resettlement budget and implementation schedule, and
monitoring and evaluation. The RAP thus complies with WB OP 4.12 Involuntary Resettlement
Policy and address largely physical and economic displacement aspects in the context of the
project.

1.7 Outline of the RAP

The RAP is structured as follows:

• The present chapter presents an overview of the project, its location, the benefits and
impacts associated with it as well as the objectives of the RAP

13
National Transmission and Despatch Company

• Chapter 2 focuses on the project impacts in terms of land acquisition and loss of
structures, crops and trees and livelihood related impacts. It also discusses the
significance of these impacts to APs.

• Chapter 3 discusses the socioeconomic profile of the affected population as it was


derived by the census and socioeconomic survey carried out by the social/census
teams. It addresses issues related to demography, income, sources of income, land
holding, assets, etc.

• Chapter 4 analyses the applicable national legal and institutional framework related to
land acquisition and compensation for lost assets, as well as its compliance with WB
OP 4.12 on Involuntary Resettlement. It goes on to discuss the negotiations of land
purchases and how the legal framework applies to this particular case, compulsory
acquisition needed under eminent domain and what is the process of compensation to
be employed.

• Chapter 5 discusses the approach to stakeholder consultation and the main outcomes
of it, in particular with regard to stakeholder concerns and how the project addresses
them.

• Chapter 6 describes the livelihoods restoration adopted by the project in order to


improve or at least restore the livelihoods of affected persons.

• Chapter 7 discusses the institutional setup for RAP implementation

• Chapter 8 presents the grievance redress mechanism setup by NTDC to collect and
address grievances by the project stakeholders

• Chapter 9 outlines the cost of RAP implementation

• Chapter 10 presents the provisions for monitoring and evaluation for RAP
implementation

14
National Transmission and Despatch Company

2 PROJECT LAND REQUIREMENTS AND IMPACTS

Land acquisition and the related impacts were assessed based on the census of affected
population, identification of affected assets, consultations with APs and general public at
village Kamalpur Miyan. The first census of IW Grid Station was carried out in 2016. The
census was revised in July 2019 and was further confirmed in November-December 2020
based on the revenue records and field surveys. Details on land acquisition and impacts are
illustrated below.

2.1 Description of the Land Area Required

Project construction and operation will require the acquisition of 202 acres of land close to the
village Kamalpur Miyan, approx. 30 km west of Islamabad, in the District of Attock. Almost all
the affected land is used for agriculture.

2.2 Types of Impacts

2.2.1 Impact on Land

The project requires the acquisition of 202 acres of (private) land owned by 647 individuals
(as per the Revenue Land Records) belonging to 274 affected households (1288 affected
persons), located in Kamalpur Miyan of district Attock. Almost all the affected land is used for
agriculture. The average land loss per owner is shown in Table 2-1, where it is shown that
92% of the APs are losing less than 1.0 acre of land.

Table 2-1: Details on land to be acquired


No Land to be Number of owners %
acquired (acres)
1 Up to 1.0 598 92
2 1.0 – 3.0 38 6
3 3.0 and above 11 2
Total 647 100
Source: Field Survey (2019, 2020)

The 2020 survey showed that 21 out 41 households, (i.e., 51%) lose more than 10% of their
land holding while agriculture is their main source of income. The impact for these households
is severe.

2.2.2 Impact on Crops

Almost all the proposed area for acquisition is under cultivation. Major crop is reported to be
wheat in Rabi season; the average (per acre) yield of wheat crop is 1024 kg. The estimated
production is given in Table 2-2.

15
National Transmission and Despatch Company

Table 2-2: Crops in the affected area


Crop Area (acre) Product (Kgs)
Wheat 193 197,632
Maize 4 3,712
Vegetables 5 22,175
Total 202
Source: Field Survey (2019, 2020)

2.2.3 Impact on Trees

The inventory survey results indicate that the project will have impact on 83 trees. These are
mostly Acacia trees and Guava. All trees are having 1 to 2 feet girth. Their location in the Grid
Station area is shown in the figure below.

Figure 2-1: Affected trees in the project area

Location of trees

Source: Field Survey (2020)

2.2.4 Impact on Structures

The project will have impact on 16 built structures located in the project area. A total of 37
rooms and cattle sheds are included in these structures. Out of them, 30 are Pacca and 7 are
Kacha structures. The structures are constructed on an area of 0.8 acre. The location of the
built structures in the project area is shown in the figure below.

16
National Transmission and Despatch Company

Figure 2-2 Built structures in the project area

Source: Field Survey (2020)

The project will also require the dislocation of 8 tube wells used for irrigation purposes. These
tube wells are owned by 8 different owners.

2.3 Impacts on Livelihoods

Given that the project area comprises fertile land, subject to intensive cultivation, the project
will have significant impact on the livelihood of affected people losing their productive land,
provided that agriculture is their primary source of income. The census showed that almost
647 APs (land owners) are losing their land holding while agriculture is their main source of
income. The impact to these persons is severe.

2.4 Vulnerability Impact

Field investigation has shown that the project has impact on a number of low- income families,
calculated at 10% of affected households. These families are earning less than the official
poverty line of PKR 26,000/month. These families/households are considered vulnerable for
the purposes of this RAP. In addition, women-headed households comprise 12% of affected
households; they are also considered vulnerable for the purposes of this RAP.

2.5 Public Infrastructure

The project will need to upgrade the existing access road (approx. 2 km) connecting the grid
station site to the Brahma – Bahlol road. Upgrade will involve extent of the road (by an
estimated 4 m) and improvement of asphalt layer. The design of the road is not currently in

17
National Transmission and Despatch Company

place, so it is not known if the road will be extended on one side or both. And although there
are a few residential structures along the road, the extension can still take place without
affecting them. It is therefore assumed that road extension will affect only agricultural land.

2.6 Summary of Impacts

The resettlement impacts discussed in the earlier sections are summarized below.

Table 2-3: Summary of Resettlement Impacts


Resettlement Impacts Quantity Nature of Impact
A. Land to be acquired
Agricultural land 202 acres Loss of land

Total 202 acres


B. Affected Structures
Total Number of Residential 37 Loss of structure
Structures
Total affected structures 37
C. Affected crops
Total area of agriculture land to be 202 acres Loss of crops and crop
impacted by Grid Station income
construction
Total 202 acres
D. Public Infrastructure (road) 2 Km Upgrade of access road
Agricultural land 2 acres
E. Affected trees
1 Privately owned Wood/ Timber 72 Loss of trees
Trees
2 Privately owned Fruit Trees 11 Loss of trees
Total affected trees 83
F. Project Affected Households 274
Number of affected persons 1288
1 Households losing crops 274
2 Households losing trees 54
3 Households losing structures 16
4 Vulnerable households 60 HHs below the OPL and
women-headed HHs
5 APs with impacts on livelihoods 647 APs losing their land while
due to loss of land their livelihood is based on
agriculture

18
National Transmission and Despatch Company

3 SOCIOECONOMIC INFORMATION AND PROFILE

3.1 General

A socioeconomic survey was carried out in July 2019 in the project area, village Kamalpur
Miyan, to obtain a detailed understanding of the social and economic conditions of the APs
and to provide baseline data for monitoring of RAP implementation and the impacts of the
project. The main objective was to analyze socioeconomic and cultural characteristics of the
population in the project area in order to understand their interrelationships, social dynamics,
and inequalities and to identify opportunities and constraints in accessing project benefits.
This also included those with special characteristics (based on gender, ethnicity, level of
income, geographical remoteness etc.).

A second survey was carried out in November – December 2020, in order to verify existing
information from the first survey and update the findings.

3.2 Methodology

The methodology adopted for the 2019 socioeconomic survey included: a review of secondary
information including official records and statistics, such as the Population Census Report
(2017) of district Attock; complete survey of the households affected by land acquisition. The
survey used a pre-structured questionnaire (see Annex A) aimed at registering and
documenting the number and status of affected persons likely to be physically or economically
displaced as a result of the project and, therefore, entitled to compensation.

Primary sources of information included Focus Group Discussions (FGDs) with selected
households in village Kamalpur Miyan, individual interviews with APs and key informants and
transect walk in the area, which helped the survey team to physically observe the socio-
economic conditions in the project area. The key variables covered in the surveys and
qualitative interviews included (i) identification of the affected population; (ii) demography, (iii)
social organization (iv) literacy level, (iv) occupational structures, (v) income and expenses
levels, (vi) access to public services, (vi) personal property, (vii) project’s impacts on the poor,
indigenous and/or ethnic minorities, and other vulnerable groups, (viii) identification of gender
and resettlement impact and (ix) impacts, priorities and needs of the women.

The 2020 survey was based on a sample of the total population comprising 65 individuals from
41 affected households (192 affected persons in total). These people attended two workshops
carried out in Wah Cantt at the end of November and beginning of December. The aim of the
2020 survey was to verify existing information and record likely changes.

3.3 Identification of AHs

Any household (and/or person), whose land, asset/infrastructure, source of income or access
to resources/workplace is likely to be affected by the project’s operations, is an AP. These
include mainly the residents, owners and users of land or assets/structures within the

19
National Transmission and Despatch Company

substation footprint or the associated infrastructure. The total number of such affected
households is 274 (1288 affected persons 1).

During the 2020 survey, 41 HHs were surveyed totaling 192 affected persons. NTDC decided
to undertake the 2020 survey in order to capture a more accurate snapshot of the
socioeconomic conditions of the AHs, especially with regard to parameters such as
employment or income (and thus vulnerability) which present very dynamic characteristics in
an area close to the capital. In general, data from 2020 survey corroborate data from the
previous (2016/2019) surveys. In any case, the rest of the analysis in this section will be based
on data from 2020 survey as this data is very recent and therefore more accurate.

3.4 Profile of the Respondents

Table 3-1 shows that all surveyed HHs belong to rural area, Village Kamalpur Miyan.

Table 3-1: Settlement Types by location


Settlement Surveyed Surveyed
No.
Type Households (No) Households (%)
1 Rural 41 100
2 Simi Urban 0 0
3 Urban 0 0
Total 41 100
Source: Field Survey (2020)

Table 3-2 reveals that almost all of the respondents (with one exception) are resident-owners.
None of the respondents was a resident tenant, resident owner cum tenant or resident
absentee.

Table 3-2: Details of the Respondents


Household
No. Respondent Type Household (No)
(%)
1 Resident Owner 40 97.6
2 Resident Tenant 0 0
3 Resident Owner cum Tenant 0 0
4 Resident Absentee 0 0
5 Business owner 1 2.4
Total Surveyed households 41 100
Source: Field Survey (2020)

1 The number of affected persons is calculated by the number of affected households multiplied by the average size of household
(4.7 individuals per HH) which resulted from the 2020 survey.

20
National Transmission and Despatch Company

3.5 Demographic Data

Household surveys were carried to understand the demographic and socio-economic


characteristics of the population in the project area. According to the household census data
(274 affected households), the female population is slightly higher (52%) compared to male
population (48%) in the project area. These findings are corroborated by the results of the
2020 survey where the female population was 100 out of 192 total population or 52%. The
data regarding the distribution of affected people by age is presented in Table 3-3.

Table 3-3: Age Distribution of Affected Persons

Age range No %
Below 18 41 21
18 - 30 Years 58 30
31 - 40 Years 15 8
41 and 50 Years 37 19
Above 50 41 22
Total 192 100
Source: Field Survey (2020)

3.6 Education and Literacy

In term of education distribution, only approx. 1% of the respondents were reported illiterate
(respondents have had Deeni (religious) education). The majority had some degree of
education, with a notable 8% having a post-graduate degree. The results are shown in
Table 3-4.

Table 3-4: Literacy of Affected Households


Respondents
Education
No. %
Preschool age 6 3
Illiterate (respondents have had Deeni 2 1
(religious) education)
Primary 35 18
Middle 43 22
Matriculation 47 24
Intermediate 22 11
Graduate 25 13
Master and other professional degrees 12 8
Total 192 100
Source: Field survey (2020)

3.7 Ethnicity, Tribes, Language and Religion

In the project area, in village Kamalpur Miyan, Awan are dominant (60%), followed by the
Khattar (26%), Khan (10%) and the Kashmiri (4%). All of the surveyed households are Muslim
by religion and they communicate in the same language.

21
National Transmission and Despatch Company

3.8 Livelihood Sources

From the 192 affected persons (belonging to the 41 surveyed households), 64 have some
form of occupation (33%). From those, 37 (58%) have one source of income, 25 (39%) have
a second job and 2 (3%) have a third job.

The main occupation reported comprises agriculture, employment in government services,


operating own private business such as running a grocery, livestock rearing, tailor, etc., driver,
lawyer, and pensioners. Details are presented in Table 3-5.

Agriculture is the most dominant occupation in the area with 40% of the affected people
depending on farming as the primary source of income. In most of the cases though,
agriculture is complemented by a secondary source of income, such as live stock or pension
(ex-army or ex-government employee).

Table 3-5: Distribution of Respondents Regarding Main Occupation


Occupation No. of Respondents Percentage (%)
Employee in Government 5 8
Employee in private sector 8 12
Laborers 1 2
Pensioners 4 6
Agriculture 26 40
Teacher 5 8
Driver 3 5
Army staff 2 3
Other 10 16
Total 64 100
Source: Field Survey (2020)

3.9 Household Income

Table 3-6 shows that 10% of the surveyed households fall in the income category of less than
PKR 25,000 which is below the OPL level which is PKR 26,000 2. This is below but relatively
close to the average Punjab figures for poverty (approx. 14%).

2 According to the National Poverty Report 2015-16, issued by the Ministry of Planning, Development and Reform, using Cost of
Basic Needs (CBN), the poverty line is 3,250.28 (Rs. per adult equivalent per month). Taking the average (for Pakistan) household
size of 6, the poverty line of a household is calculated as 3250.28 x 6 = PKR 19,502/- per household. When inflation is taken into
account (4.09% for 2017, 5.08% for 2018, 10.58% for 2019 and 9.74% for 2020) the OPL is calculated as (approx.) PKR 26,000/-
per month per HH.
(Inflation Rates Source: https://www.macrotrends.net/countries/PAK/pakistan/inflation-rate-cpi)

22
National Transmission and Despatch Company

Table 3-6: Monthly Income of Surveyed Households


Income Level Number of Percentage (%)
(PKR/Month) Households of households
Less than 25000 4 10
26000 - 40000 6 14
41000 - 60000 5 12
61000 - 100000 11 27
101000 - 150000 8 20
Above 150000 7 17
41 100
Source: Field Survey (2020)

3.10 Household Possessions

The possession and use of household durable goods have multiple effects and implications.
For instance, access to satellite dish or television helps household members to remain
updated about daily events, information, and educational materials. Similarly, a refrigerator
prolongs food storage and keeps food fresh and healthy. Ownership of transportation allows
greater access to services away from the local area and enhances social and economic
activities.

The survey results corroborate the findings of the household income and suggest a population
of average or above average buying potential. The majority of the households surveyed
possess domestic household appliances such as refrigerators, washing machines, electric
irons, etc. Almost all households possess LCD TV sets, while few have more than one. Mobile
phones are widespread, with 2.8 phones per household on average. Vehicles are less
widespread, with 17% of the households owning one.

3.11 Land Holding

Land is the major determinant of agricultural income and big holding size is the symbol of
dignity and honor in the rural set up. All surveyed households are land owners.

Generally, the affected people have small land holdings, as approx. 83% have less than 5
acres (in fact 44% have less or close to 1 acre). None had more than 15 acres. In addition,
the land holding size is decreasing with time due to inheritance fragmentation in the rural area.

Table 3-7: Land Holding Size


Land Holding Size (Acre) No. of Households %
0.1 – 5 34 83
6 – 10 5 12
11 – 15 2 5
More than 15 0 0
41 100
Source: Field Survey (2020)

23
National Transmission and Despatch Company

3.12 Crops, Fruits and Vegetables

As per Table 3-8, the major crop of the area is wheat, with maize and vegetables, especially
peas and cabbage, contributing to a smaller extent. Others crops like fodder gram, ground
nuts, oil seeds, lentil are also grown. Fruits are generally not grown in the project area. The
dominance of wheat is explained by the fact that the area is rainfed. Some tube-wells have
been installed to irrigate vegetables and fodder crop.

Table 3-8: Details of Crops Grown and Income


Average Total Total cost
Type of Cultivated Net income
Yield per income incurred
Crop Area (Acre) (PKR)
Acre (Kgs) (PKR) (PKR)
Wheat 193 1,024 6,144,000 4,204,017 1,939,983
Maize 4 928 92,800 26,200 66,600
Vegetables 5 4,435 399,150 228,000 171,150
Source: Field Survey (2019)

3.13 Livestock

According to the field survey, Buffalos and cows (mostly), goats, sheep and donkey are the
common livestock in the area. Table 3-9 shows the number of animals and their market value.

Table 3-9: Livestock in the project area


Livestock HH Number Average market Value
per animal (KPR)
Buffalos 21 105 120,000 - 220,000
Cows 25 90 100,000 - 175,000
Sheep / goats 8 40 40,000 - 75,000
Donkeys / horses 7 18 20,000 - 100,000
Source: Field Survey (2020)

The fact that more than 50% of the surveyed households are involved in livestock breeding
shows that this is a common income source. However, in very few cases livestock is the main
or the primary income source. It is usually a secondary income source for those having
agriculture as primary occupation.

3.14 Access to Infrastructure

Access to safe drinking water and sanitation is essential for health, security, livelihood, and
quality of life, and is especially critical for women and children. Improved water supply and
sanitation interventions could thus provide a wide range of benefits like longer lifespan,
reduced morbidity and mortality from various diseases, and low health costs.

Table 3-10 lists the available social amenities in the project area.

24
National Transmission and Despatch Company

Table 3-10: Access to Social Amenities in the Project Area


Accessible to Level of Satisfaction
Description the Household (Excellent=1), (Good=2),
Yes No (Poor=3)
1 Water Supply Connections  1
2 Access Road  3
3 Washing / Bathing Points  2
4 Primary School (Boys / Girls)  2
Secondary / Higher Secondary In Bahtar (about 20 km
5 
School (Boys / Girls) away)
In Bahtar (about 20 km
6 Dispensary / Basic Health Unit 
away)
In Bahtar (about 20 km
7 Hospital 
away)
8 Mosque  02 Nos.
In Bahtar (about 20 km
9 Market 
away)
10 Cemetery (Graveyard)  03 Nos.
Mobile / Telephone
11  1
Connections
12 Electricity Connection  1
13 Disposal of Solid Waste  Partial
14 Disposal of Waste Water  Partial
In Brahma (10 km away) &
15 Bridge Crossings
Neeka (5 km away)
16 Water Mill None
Irrigation Scheme / Water
17 Tube Wells / Rain Water
Channels
Source: Field Survey (2020)

Table 3-10 indicates that all surveyed households enjoy basic amenities such as the
connection to potable water, electricity and gas. Some of these amenities are not at the
desired level of quality, such as road connection, access to education (primary and
secondary), access to waste and wastewater management services.

Health facilities in the project area are not adequate as people have to travel to Bahtar to
access basic health and hospital facilities.

3.15 Housing

The typical residential structures comprise pucca or semi-pucca houses. Pucca houses are
constructed with bricks, cement and concrete, with wooden and steel doors and windows.
Semi pucca houses are made of bricks (joint with mud) and their roofs are mostly of wood,
and partially bricks. All surveyed households live in pacca houses.

25
National Transmission and Despatch Company

3.16 Gender Analysis

3.16.1 Female participation in economic activities

The participation of women in different activities was assessed as part of the survey. Given
that the surveyed individuals (2020 survey) were predominantly male, the results of the survey
also reflect the anticipated position of women in the household and society.

As shown in Table 3-11 women are mostly (and expected to be) active in housekeeping and
child caring where they undertake all decision-making. Women are also active in social events
of everyday life, like marriages, where their view is considered equally weighted as that of
men. In economic life, women are expected to contribute to livestock management at
household scale.

Table 3-11: Women Participation in Various Activities


Activities Participation Decision
making
Housekeeping 100% 100%
Child caring 100% 100%
Farming 0% 0%
Livestock 25% 0%
Sale / Purchase of property 0% 0%
Social obligations (marriage, birthday & other functions) 50% 50%
Local Representation (councilor /political gathering) 0% 0%
Source: Field Survey (2020)

The above survey analysis is further supported by the results of focus group discussions. As
reported, the daily work of a female is housekeeping, child rearing, and fetching water, laundry,
cooking and taking care of livestock and other social obligations like marriage, birthday & other
functions. Females are expected to meticulously follow the cultural tradition of modesty, which
is the main factor constraining participation of women in the social activities.

In reality, the situation with regard the position of women in society is changing, although at
slow pace. The analysis of occupation of women in the 41 surveyed households has shown
that a 10% (i.e., 10 women out of 100) are working in the services sector.

Table 3-12: Participation of women in economic activities


Position in household Number Occupation
Head of HH 9
Aunt 2
Cousin 1
Daughter 39 2 teachers, 1 doctor, 1 Govt. employee, 1 lawyer
Daughter-in-law 5
Grand daughter 5
Mother 4 1 teacher
Niece 1
Sister 4
Step mother 1

26
National Transmission and Despatch Company

Position in household Number Occupation


Wife 29 2 teachers, 1 lawyer, 1 Lady Health Worker
100 10
Source: Field Survey (2020)

3.16.2 Concerns of Women related to the Project

Due to the nature of the project, it was not considered to offer any benefits to women at a
professional level. Instead, their concerns were mostly related to likely restrictions during
construction or to opportunities that NTDC could materialize in the form of community
assistance. In specific, during the socioeconomic survey, women of the project area pointed
out the following major issues relating to project activities:

• Care should be taken to ensure that, despite the potential presence of foreign workers,
the local population, especially women and children, will be able to be engaged in their
routine activities (i.e., school, shopping) during construction activities;

• Fair compensation should be provided for the acquired land. In addition, as


compensatory measures, employment to the men of the affected households should
be provided.

• The current rate of women involved in commercial activities is still low. Women have
requested that training should be provided to improve their skills in handcrafts or other
work that can be done in house, for domestic or commercial use.

27
National Transmission and Despatch Company

4 LEGAL AND POLICY FRAMEWORK

4.1 General

This chapter outlines and reviews the existing legislations, policies and presents the legal and
policy framework to be used in the land acquisition for the Islamabad West Grid Station. The
dual approach to acquisition using the LA Act of 1894 and negotiation for land purchases and
the mode of payments directly from NTDC is clearly explained. This is done to expedite the
process and to fast track the acquisition with full compliance of the WB OP4.12 Involuntary
Resettlement Policy in terms of rates and negotiated packages for acquisition of land for the
project.

4.2 National Legal Instruments

4.2.1 Constitution of the Islamic Republic of Pakistan

The Constitution of Pakistan (1973) clearly addresses the protection of property rights (Article
24) that it includes “no person shall be compulsorily deprived of his property in accordance
with law” and “no property shall be compulsorily acquired or taken possession for a public
purpose, and by the authority of law which provides for compensation” therefore and either
fixes the amount of compensation or specifies the principles on and the manner in which
compensation is to be determined and given. Further, Article 4 (sub-clause/a of 1) reiterates
the legislative right of the people by stating that: “No action detrimental to the life, liberty, body,
reputation or property of any person shall be taken except in accordance with law.

4.2.2 The LA Act (1894) and Limitations

The LA Act of 1894 is the principal legal instrument for land acquisition for public purpose
project in Pakistan. The Act lays down detailed procedures for acquisition of land and
payments of compensation, but falls short of the standards required in terms of replacement
costs and other support such as resettlement and livelihood aspects associated with
displacement. The Act has 55 sections with a long-drawn process that requires, as
experiences suggest, two or more years for land acquisition. Further, the Act does not provide
for equal or enhanced living standards to the project affected persons. Due to the challenges
encountered during the application of the Law, NTDC authorities are becoming also more
cognizant of the limitations of the law and its coherence with other international standards and
the need to ensure its consistency with the provisions of the World Bank policies.

4.3 Gap Analysis between Land Acquisition Act and World Bank Policies

The LAA of 1894 is the national legislation applicable for land expropriation in the province,
whereas OP 4.12 provides the WB’s policy principles and requirements relating to involuntary
resettlement. A comparison of land acquisition under LAA 1894 and the World Bank OP 4.12
on Involuntary Resettlement shows that major differences exist between the two instruments.

28
National Transmission and Despatch Company

Error! Reference source not found.An attempt has been made to compare the LAA 1894
and OP 4.12, the objective being to identify if and where these sets of procedures are in
conformity with each other and more importantly how to address the differences and gaps
(Table 4.1).

Table 4-1: WB OP 4.12 Involuntary Resettlement & Pakistan Land Acquisition Act
No. WB Involuntary Resettlement Pakistan Land Approaches to
Policy Principles Acquisition Act Address the GAPs
1 Screen the project early on to identify No equivalent Screened and
past, present, and future involuntary Requirements categorized. Scope
resettlement impacts and risks. (though the defined, social
Determine the scope of resettlement Pakistan assessment and
planning through a survey and/or Environmental gender analysis
Census of displaced persons, Protection Act undertaken.
including a gender analysis, (PEPA) 1997 does
specifically related to resettlement require screening
impacts and risks. of social impacts
that also include
resettlement
impacts)
2 Carry out meaningful consultations No equivalent Complaints and
with APs, host communities, and requirements other grievances are
concerned nongovernment than consultations resolved through
organizations. being a key project grievance
Inform all displaced persons of their requirement of redress
entitlements and resettlement PEPA 1997. mechanism.
options. Ensure their participation in
planning, implementation, and
Consultations
monitoring & evaluation of
conducted,
resettlement programs. Pay particular
vulnerable groups
attention to the needs of vulnerable
identified and
groups, especially those below the
supported as
poverty line, the landless, the elderly,
appropriate.
women and children, and Indigenous
Peoples (IP), and those without legal
title to land, and ensure their
participation in consultations.
Establish a grievance redress
mechanism to receive and facilitate
resolution of the APs’ concerns.
Support the Social and cultural
institutions of APs and their host
population. Where involuntary
resettlement impacts and risks are
highly complex and sensitive,
compensation and resettlement
decisions should be preceded by a
social preparation phase.
3 Improve, or at least restore, the No equivalent The present RAP
livelihoods of all APs. through (I) land- requirements addresses these
based resettlement strategies when requirements.
affected livelihoods are land based

29
National Transmission and Despatch Company

No. WB Involuntary Resettlement Pakistan Land Approaches to


Policy Principles Acquisition Act Address the GAPs
where possible or cash compensation
at replacement value for land when the
loss of land does not undermine
livelihoods, (ii) prompt replacement of
assets with access to assets of equal
or higher value, (iii) prompt
compensation at full replacement cost
for assets that cannot be restored, and
(iv) additional revenues and services
through benefit sharing schemes
where possible.
4 Provide physically and economically No equivalent The present RAP
displaced persons with needed requirements addresses these
support requirements.
5 Resettlement assistance and The LAA Resettlement
compensation for the loss of land or recognizes only the assistance will be
assets title holder as paid to the APs
eligible for even without
compensation having legal title of
the land to be
affected.
6 Crop losses compensation provided Crop losses Compensation for
to landowners and share-crop/lease compensation crop losses will be
tenants whether registered or not. provided only to provided to
registered landowners and
landowners and share-crop/lease
share-crop/lease tenants whether
tenants registered or not
7 Disclosure requirements Partially covered. Information related
The decisions to quantification of
regarding land land, structures and
acquisition and other assets,
compensations to entitlements and
be paid are amounts of
published in the compensation and
official Gazette and financial assistance
notified in are to be disclosed
convenient places to the affected
so that the people persons prior to
affected are aware. taking possession
of their assets.

The present RAP


will be disclosed
locally as well as
internationally.

30
National Transmission and Despatch Company

4.4 NTDC Practices, Framework for LA and Valuation

For transmission line projects, NTDC uses the WAPDA Act 1958, Electricity Act 1910 and
Telegraphic Act 1885, and avoids any acquisition of land; instead of permanent acquisition,
land is required temporarily and all kinds of losses are considered for compensation. The Dasu
Transmission Line Project (DTLP) has taken this approach. However, for substations such as
the Islamabad West GS, there is need for permanent land acquisition.

For permanent land acquisition, NTDC practice is to use the eminent domain, (i.e., LA Act of
1894) and in some cases the private negotiation. The experience of NTDC with the private
negotiations and the eminent domain alone is not good as there are many issues related to
the transfer of land which causes lot of delay in the acquisition process and similarly in the
other method, low land rates given by the District administration are also not fascinating.

To cater these issues in Islamabad West GS, NDTC intends to follow a mixed approach. NTDC
has followed the national legal framework, (i.e., LA Act of 1894) to acquire and “freeze” the
land area by Section 4/1894 Act for project development through the use of “eminent domain.”
The application of the Act helps to secure the availability of land without dispute. The rest of
the process – for example, compensation rate etc. - are determined through consultation and
negotiations, taking into consideration the replacement cost including market value and other
associated costs. In such a case, the application of the LA Act (1894) remains limited to
notification by the District Collector for acquisition of land for public purpose project. In case
land acquisition process through private negotiation fails, NTDC will resort to applying eminent
domain and secure acquisition of the land through the District Collector by applying LA Act of
1894.

Under the negotiations concept, and following the notification, NTDC will constitute, as per the
NTDC Guidelines, a five-member committee to purchase private land through negotiation for
the Islamabad West GS. The processes work out as follows.

• First, the NTDC Committee engages with the land owners.

• Second, NDTC has qualified technical and field staff mostly on deputation from the
revenue department to carry out valuation of assets.

• Third, once the land is identified, the value of land is determined by the Committee
through a series of meetings and negotiations with individual owners and community-
level meetings.

• Fourth, if there is any building, crop, fruit bearing trees or any other immovable
structure on the land, then its value assessed is referred to the concerned
departments/agencies.

• Fifth, NTDC/PMU employs patwaris (surveyors) to assist the Committee to determine


boundaries, location, size and area of the land to be purchased. Patwari will prepare

31
National Transmission and Despatch Company

land record including ownership genealogy, rights and interests held in the land, and,
estimated value of improvements to land in consultation with the landowners. This is
typically done over a period of several months.

• Sixth, following the completion of the valuation of assets for negotiation (includes land,
crops, trees, and other assets) as well as compensation package and entitlements, the
compensation payment is disbursed directly by NTDC to the affectees.

In case the negotiations fail, i.e., parties do not agree on rates or parties refuse to take part in
the process, the LA Act (1894) will be used fully to complete the entire acquisition process.
The land which will be acquired under this policy will be registered in the name of NTDC.

In the case of married couples/households, the compensation will be paid to the one who owns
the assets. If these assets are jointly owned by couple, then the amount is paid to both the
parties. However, when assets are owned by single/unmarried/separated women, they will
receive compensation directly. Compensation will be paid through cross cheque to the entitled
individuals. In case of married couples, if assets are jointly owned then the amount is paid to
both the parties. These provisions for payments were also discussed during consultation with
women.

4.5 Compliance of WB OP 4.12 IR Policy

World Bank OP 4.12 3 encourages the purchase of land through negotiation based on pre--
displacement market value of land to be expropriated through full compensation at
replacement cost, independently with advance public notice, negotiation and right of appeal.
The processes undertaken in the Islamabad West GS complies with OP 4.12 IR Policy
guidelines. As explained earlier, the entire processes of land acquisition through private
negotiation, demonstrate both the legitimacy of the processes and ensure transparency from
the part of NTDC. The rights to compensation is extended to owners, tenants, workers, or any
person who can demonstrate any interest lost as a result of expropriation, including provisions
for grievances and disagreement on the agreed price and packages.

In this project, the determination of compensation for land is based on negotiations with the
affectees, based on recent market data (September, 2019) as the basis; and the rates are
eventually above market value. For other land-based assets (trees and crops), consultation
with the relevant government departments (forestry, agriculture) was done. Finally, in case of
delay in RAP implementation, the compensation will be adjusted as per the inflation rate.

3 As of October 1, 2018, the new WB ESF applies to all new World Bank investment projects. Under
the WB ESF 2018, ESS5: Land Acquisition, restrictions on land Use and involuntary resettlement
replaces OP4.12. However, with existing projects continuing to apply the Safeguard Policies, the two
systems will run in parallel for an estimated seven years.

32
National Transmission and Despatch Company

Further, to minimize the gaps and to comply with the OP4.12 requirements, the RAP policy
has taken measures – for example, analysis of gender issues, consultation with women and
other vulnerable groups, grievances/dispute resolution, and livelihood restoration measures
so that affected persons can regain and restore their livelihood in post-project period.

4.6 Reflections and Lesson Learned

In this project, based on past transmission line project implementation experiences, the
following are highlighted as “lesson learned,” for better management and implementation of
the Islamabad West GS.

Timely arrangement of funds for avoiding delays in compensation payment:


Resettlement and land acquisition issues should be dealt with arranging funds for the timely
disbursement of compensation payment to avoid protracted delays. The delay in payment of
compensation can delay the implementation of the whole project and can deteriorate the
community and implementing agency relationship. NTDC has faced this problem in several of
its transmission and distribution projects. Keeping this lesson in view, funds are earmarked for
compensation payment before the commencement of work without any impediment to avoid
APs grievances. This should expedite the project implementation tasks.

Direct purchase of private land through private negotiation for the Islamabad West Grid
Station: For public interest projects, the use of LA Act of 1894 has caused delays due to
difficulties in assessing market or replacing value under the Act. Experiences with past project
have shown this time and again. Private negotiation of land has proven to be more effective
and expeditious in comparison to land acquired through eminent domain. Keeping this in view,
NTDC has planned to use private negotiations for this project. Accordingly, NTDC has
established a high-powered Committee for Land Acquisition for all transmission projects to be
funded by international financial institutions such as the World Bank and the Asian
Development Bank. However, as a last resort in case negotiations fail to arrive at mutually
accepted compensation rates or affected persons refuse to take part in the process, the
application of eminent domain will remain an option.

As the negotiations with the land owners were not successful, now NTDC is moving towards
the eminent domain in a fast track. The rate of land will be increased and dispersed through
the district administration. The district administration has promised to complete the
disbursement of compensation and hand over the land to NTDC by mid-2022.

4.7 Entitlements

Based on the policy review and impacts identified in previous chapters, the following affected
persons would be eligible for compensation and resettlement assistance as per the policy
framework:

Land impacts will be compensated as follows:

33
National Transmission and Despatch Company

(a) Permanent Losses: Compensation will be paid at the negotiated rate after
agreement with the affected community and the households to legal owners as well as
those with customary rights. The negotiated package will be over and above the market
price.

All Other Assets and Incomes:

(a) Crops will be compensated at the full market rate for one year of harvest including
both rabi and kharif seasons.

(b) Trees will be compensated based on the market value of the wood production,
having taken due consideration of the future potential value for three years.

(c) Structures will be compensated in cash at replacement cost. Any transaction costs
will also be paid. Materials that can be salvaged are allowed to be taken by the
owner, even if compensation has been paid for them.

(d) Relocation Allowance will be paid to those affected households physically


relocated as a result of the project. It will cover transport expenses (PKR 5,000)
and livelihood expenses for three months (PKR 78,000 per household)

Impacts to livelihood will be compensated as follows:

(a) Livelihood Disturbance Allowance will be paid to those affected households


losing their land holdings while their livelihood is based on agriculture. This
allowance will be equal to the market value of gross harvest of the affected land
for 1 year (inclusive of winter and summer crops).
Vulnerability will be compensated as follows:

(a) Vulnerability Allowance will be paid to vulnerable APs, i.e., households earning
below the OPL or are women-headed. It will comprise one time subsistence
allowance amounting to PKR 78,000 per eligible household.

4.8 Entitlement Matrix

The entitlement matrix is developed based on the above discussed eligibility criteria, nature of
losses and implementation issues of the proposed project in consultation with the APs.

34
National Transmission and Despatch Company

Table 4-2: Entitlement Matrix

Type of Loss Specification Eligibility Entitlements

1. LAND, TREES, CROPS AND ASSETS

Cash compensation based on negotiation


Owners
ensuring replacement cost above the market
Impact on (titleholder, or
Land loss value, plus all transaction costs, applicable
land holder of
fees and taxes and any other payment
traditional rights)
applicable.

Negotiated cash compensation for timber


trees at current market rate or above for
Trees Affected trees Owners
timber value of species at current volume, and
required inputs to replace trees.

Cash compensation at current market rate


proportionate to size of lost plot, based on
Affected crop type and highest average yield in the
Crops Owners
crops project area to be determined by NTDC Team
with assistance from relevant
departments/agencies.
Cash compensation at replacement rates for
Houses/ affected structure and other fixed assets free
All relevant APs
Structures of salvageable materials, depreciation and
transaction costs.

2. RELOCATION ALLOWANCE

Transport and Provision of allowance to cover transport


transitional All APs affected expenses (PKR 5,000) and livelihood
Relocation
livelihood by relocation expenses for three months (PKR 78,000 per
costs household).
3. LIVELIHOOD DISTURBANCE ALLOWANCE

Provision of livelihood disturbance allowance


Loss of viable
amounting to PKR 92160/Acre of land equal
Loss of agricultural
to the market value of gross harvest of the
agriculture- land without Owners of
affected land for 1 year (inclusive of winter
based availability of agricultural land
and summer crops) to all APs who lose more
livelihood alternative
their land holding and agriculture is their
land
primary occupation
4 VULNERABILITY ALLOWANCE

Provision of one time subsistence allowance


Livelihood
amounting to PKR 78,000 (equal to 3 months
improvement
of PKR 26,000 as per Official Poverty Line
Vulnerable and removal All vulnerable
(OPL)) to all APs whose income is below the
APs of APs
OPL or are women-headed HHs, disabled or
disadvantage
child headed households. Preferential
s
selection for project related employment.

35
National Transmission and Despatch Company

4.9 Cut-Off Date

Eligibility for entitlements is limited by an officially declared and publicized cut-off date. Cut-
off-Date is the date when the Section 4 is published in the provincial gazette as per the LAA.
The cut-off-date was discussed with the implementing agency and the affected people and
announced during the survey as well as consultation meetings. Any one moving to the project
site after the cut-off-date would not be eligible for any compensation and/or assistance under
the project.

The cut–off date in this RAP is March 5, 2016. This was published in the Punjab Gazette
in March 22, 2016.

An additional cut-off date will be set for affected people losing land as a result of the extension
of the road connecting the Grid Station with the Brahma – Bahlol road. This will take place
when the road design is implemented.

36
National Transmission and Despatch Company

5 Livelihood Restoration

The forms and levels of livelihood restoration assistance vary and will be commensurate with
the duration, level and severity of impacts on livelihoods and productive assets as well as
vulnerability of the APs. The APs entitled for livelihood restoration assistance are all APs who
suffer severe impacts (i.e., land loss more than 10% of their income generating land holding)
or are vulnerable.

5.1 Livelihood Disturbance Allowance

All affected persons losing their income generating land holding and have agriculture as their
main occupation will receive livelihood disturbance allowance in addition to the compensation
that they are entitled. This allowance will be equal to the market value of gross harvest of the
affected land for 1 year (inclusive of winter and summer crops).

5.2 Vulnerability Allowance

All vulnerable affected households will be provided vulnerability allowance at the rate of
PKR 78,000 /Household, (i.e., PKR 26,000/month for 3 months). Vulnerable APs will also be
given priority in project–related employment opportunities as support staff, drivers, clearing,
skilled and unskilled labor. To this end, the NTDC will incorporate clauses in the contracts of
civil works contractors that they will give preference to vulnerable and other project APs while
recruiting personnel. The compliance to this effect will be presented regularly in the internal
monitoring reports.

5.3 Training and Employment

In addition to livelihood allowance, the project has made provisions for training, focusing on
strengthening the skills of APs who could be more productive in agricultural activities or be
able to exploit job opportunities that will be generated by the project.

Training will take the form of a two to three-day training at the project location to be provided
by the contractor on skills that will facilitate APs to be employed during project construction.
Alternative training will be provided by local specialists or NGOs employed by NTDC on
efficient agricultural practices, to those APs wishing to continue land cultivation. NTDC will
also hire a local specialist to provide training to women on embroidery and other home-based
work and provide support to women for gainful work.

The contractors will be required to hire local skilled and unskilled laborers. The training part
will be included in the conditions of contract for the contractor with adequate provisions to
develop local skills and capacity.

37
National Transmission and Despatch Company

6 STAKEHOLDERS CONSULTATION AND RESPONSES

6.1 General

This chapter describes the project stakeholders, their views towards the Project and the
process adopted in consulting affected households and communities on relocation and
resettlement, impacts assessment, socio-economic and physical losses due to construction.

6.2 Mapping of Stakeholders

Project stakeholders – both primary and secondary (Table 6-1) – include the APs and
beneficiaries in the project, NTDC and other related government departments/agencies,
district administration, the local governments in Attock, contractors, construction workers, in-
migrants and followers, supply/service providers, financing institutions like the World Bank,
mass media/civil society members, consultants and project advisors.

Table 6-1: Primary and Secondary Stakeholders


Type of Stakeholder Stakeholder’s Profile
 All APs, households, communities, project beneficiaries – for
Primary Stakeholders
instance, residents of the project area.
 Project owner/NTDC, other related departments/agencies of
the GoP, Attock District administration, project contractors,
Secondary construction workers, in-migrants and followers, supply and
stakeholders service providers, financing institutions like the World Bank,
mass media/civil society members, consultants and project
advisors

6.3 Consultation with Stakeholders

Dialogue and consultation with stakeholders including APs is very critical for successful
resettlement and/or compensation of the affected assets. The process of consultations will
continue until implementation of the RAP is completed. In the process of preparing this RAP,
extensive consultations were undertaken with the APs with the objectives to:

• Share information with APs about the Project, its activities, latest interventions in
project development;

• Elicit the views of APs about the selected process of land acquisition, (i.e., through
negotiations) and the compensation process;

• Disseminate the impacts of the project in terms of land acquisition, people affected and
measures proposed to minimize the impacts, entitlements, eligibility and community
access over the GRM;

38
National Transmission and Despatch Company

• Obtain the co-operation and participation of the APs in the negotiation process and
RAP implementation

• Ensure transparency in all the project activities through sharing information

During these consultations, the communities were encouraged to (i) be open and voice their
concerns and claims; (ii) to learn about GRM for lodging complaints; and (iii) allow and give
the necessary assistance to the Monitoring and Evaluation (M&E) team during the RAP
implementation. After the preparation of the payment schedules and actual payment, NTDC
personnel will continue to conduct a series of consultations and counseling of the APs.

6.4 Consultation Approach and Framework

The guiding principle underlying consultations is that the social safeguards planning and
implementation must follow a consultative and participatory process to ensure success of the
project. This was further reinforced by the requirements of the World Bank OP 4.12 and Bank’s
Access to Information Policy (2010), which give high priority to public consultation and
participation in designing and implementation of a socially and environmentally compliant
project (see Table 6-2).

Table 6-2: Framework for Consultation


Legal/Policy Regulations/Safeguard Policy Requirements
Sources
 Land Acquisition Act (LAA) 1894 requires disclosure, (i.e., under
Section/4 – publication of preliminary notification; under Section
/5A public purpose and hearing of objections
 Pakistan Environmental Protection Agency (PEPA) Regulations
2014 and 2000
Government of
Pakistan
 Environmental Protection Agency (EPA) 1997 Guidelines for Public
Consultation requires public consultation and involvement in
project planning and implementation. The policy and procedures
require proponents to consult with affected community and relevant
NGO during preparation reports. The guidelines contain a number
of references to the need for Public involvement.
 OP.4.01, Clause 14, notes that for all Categories A and B projects
proposed for IBRD or IDA financing, during the EA process, the
borrower consults project-affected groups and local
nongovernmental organizations (NGOs) about the project's
environmental and social aspects and takes their views into
account. The borrower initiates such consultations as early as
possible. For Category A projects, the borrower consults these
groups at least twice: (a) shortly after environmental screening and
World Bank
before the terms of reference for the EA are finalized; and (b) once
a draft EA report is prepared. In addition, the borrower consults with
such groups throughout project implementation as necessary to
address EA-related issues that affect them.
 OP 4.12/Involuntary Resettlement: (i) Displaced persons should be
meaningfully consulted and should have opportunities to
participate in planning and implementing resettlement plans; (ii)
APs should be informed about their options and rights pertaining to

39
National Transmission and Despatch Company

Legal/Policy Regulations/Safeguard Policy Requirements


Sources
resettlement; (iii) APs may be involved in the planning,
implementation, and monitoring of the resettlement program,
especially in the process of developing and implementing the
procedures for determining eligibility for compensation benefits and
development assistance; (iv) Establish appropriate and accessible
grievance mechanisms; and (v) Particular attention be paid to the
needs of vulnerable groups among those displaced, especially
those below poverty line, the landless, the elderly, women and
children or other displaced persons who may not be protected
through national land compensation legislation.
 WB Access to Information Policy (2010) – RAP should be disclosed
to the APs for local inputs, including documentation of the
consultation process, in a timely manner, before appraisal formally
begin, in an accessible place and in a form and language that are
understandable to key stakeholders. All documents will be
disclosed in a language that the community and APs understand.

The consultation and participation adopted include: (i) a public participation and consultation
mechanism established in the early scoping stage for effective public participation (ii)
compensation rates at replacement cost formulated through extensive consultations in
transparent manner ensuring smooth implementation of relocation and income rehabilitation.

As part of the project preparatory work, detailed consultations were carried out through village
meetings and focus group discussions (FGDs) with the communities including women in the
project area. Details of this consultation process are described below.

6.5 Consultations Conducted

Public consultations and information disclosure sessions took place during different time
periods (November 2015 - March 2016 and up to July 2019) in the affected village. The APs
were informed regarding the time and venue, prior to meetings, and successive follow up
including telephone calls to local people was undertaken. Meetings were held in an open
encouraging atmosphere where APs expressed their concerns and views freely.

Meetings were held in the form of open hearings, FGDs and individual interviews with men
and woman. In total 275 individuals attended the consultation meetings, among which 126
were women (see Annex B). These meetings proved very useful in information sharing and
group consultation and consensus building.

A final consultation round was undertaken at the end of November – beginning of December
2020. The consultation took the form of a Workshop where affected people had the chance to
receive up to date information on the progress of the project, voice a number of concerns and
assist the project team to update the socioeconomic profile of the local population.

40
National Transmission and Despatch Company

6.6 AP’s Concerns and Project Response

During the consultations, people were asked about their views regarding the proposed project.
Some local NGOs – for example, the Citizen Foundation, and Al Khidmat Foundation - were
consulted for their views and comments. Both viewed the project positively for the
development of the country and recommended that local people must be hired and that
compensation must be based on negotiated rates. The timely payment of compensation was
emphasized by the NGOs. The community concerns, together with the project responses, are
given in Table 6-3.

Table 6-3: Summary of Key Concerns and Responses


No Concerns Responses Responsibility
1 Land price should As per WB standards, compensation for Deputy
be announced losses (land, structures, crops, trees, etc.) will Commissioner
before land be provided prior to NTDC taking possession (DC) & NTDC
acquisition. of the land
2 Without title of land Non-titleholders will also get their land DC & NTDC
will APs be paid compensation but prior to this the land
compensation? transfer record will be updated. NTDC will
closely work with the revenue department in
the transfer of land record so that the
payment disbursement can be completed on
100% basis.
3 What rates will be Following the failure of the private negotiation DC & NTDC
adopted for model, land will be acquired via the Land
compensation to Acquisition Act. Since the rates set by the
the land owners? Deputy Commissioner are below the market
price, NTDC negotiated with DC higher rates.
In addition, NTDC offers a Compulsory Land
Acquisition Surcharge of 15% above the
agreed rate. The resulting rate is PKR
543,950/Kanal (PKR 4,351,600/acre). Other
assets will be compensated on replacement
cost basis.
4 From where will the Local people will be provided employment NTDC &
labor/ workers be during construction stage. For this purpose, Construction
hired during the contractor will be bound by a clause in Contractor
construction contract documents to hire the local labor
phase? during construction phase. This will be
monitored through internal monitors.
However, in case of several candidates for a
job, merit will be followed strictly.
5 Who should we A GRC will be established for complaint NTDC
contact in case of resolution and APs will be given the
any complaint/ representation in the GRC and they can
objection? contact their representatives in case of any
grievance.
6 When will Payments will be initiated once the land LAC&NTDC
payments be made revenue record and field measurements are
for the lost assets? completed and disbursement to affectees will
be completed before taking possession of

41
National Transmission and Despatch Company

No Concerns Responses Responsibility


land and start of civil works.
7 Transparent and Effective monitoring mechanism will be NTDC
fair compensation introduced to make the compensation
procedures should process more transparent and APs
be adopted. representative will be a part of this process.
Monitoring report will be prepared
periodically and in case of non-compliance,
correction action will be
proposed/implemented for immediate
remedial measures.
8 Consultation Meaningful consultation and information NTDC
process should be disclosure will be carried out. The issues
continued along with the proposed measures discussed
throughout the during the meetings will be documented.
project cycle.
9 Vocational Training NTDC will work with concerned NTDC
especially on department/NGOs for the provision of
embroidery work vocational training. In addition, a resource
should be provided person will be hired for these trainings.
to local women for
income generation.
10 There are chances The contractor will comply with the measures Contractor &
of some proposed in environmental management plan NTDC
environmental (which will be annexed to the contract
effects like documents)
noise/vibration and
dust emissions to
the nearby
communities. This
should be
mitigated.
11 Local people’s Alternate routes will be provided for smooth Contractor &
movements should movement. NTDC
not be hindered
during construction
stage.
12 Basic necessities of NTDC will take up the issue with the NTDC &
life, Gas, school, concerned department. concerned
health centers and departments
roads should be
provided by the
project.
13 Shifting of the grid NTDC has informed the affected people that NTDC
station site to the land selected for the grid station cannot
nearby other place be changed in this advance stage as a lot of
technical, environmental and social studies
has been conducted for this site and some
land has also been purchased through
private negotiation. The change of land in this
phase will cause a loss of millions to the
Government of Pakistan.
14 Existing NTDC will ensure with the help of design NTDC &
infrastructure like consultant that impact on the infrastructure is design

42
National Transmission and Despatch Company

No Concerns Responses Responsibility


road, routes and minimized and affected infrastructure is consultant
water channels restored.
should not be
disturbed.
15 Will the cost for the The APs will get the market rate on account NTDC &
installation of bores of loss of tube well. In addition, transportation Consultant
be paid to APs? assistance will be provided for shifting of
machinery.

6.7 Local Responses to the Project

The perspective of project construction and operation has raised local reactions from part of
the affected people. Being anticipated earlier, private negotiation was selected as the way of
acquiring this piece of land. For private negotiation a committee of locals representing all the
land holders negotiated with the five-member committee of the NTDC on rates of land. The
negotiated rate, agreed by both the parties, came out to be 495,000/- per kanal. After
finalization of rate, NTDC started acquiring land as per the set procedure. Approx. 29 acres
were acquired via this process. Meanwhile, a group of people from the village started objecting
their local committee members and became a cause of hindrance in the process of land
acquisition. They denied the previous agreement on rates and demanded either change the
land or increase the land rates. These opposing people started campaigns in the village
against the NTDC and started harassing/bullying the NTDC peoples and warned them not to
visit the area.

Several consultations with the opposing people were held, in the presence of District
administration, in order to resolve the issues of opponents but nothing was sorted out as
instead of negotiating the opponents started abusing.

NTDC raised the issue with the higher ups of the NTDC, Ministry of Energy, and the World
Bank. Two key actions were agreed:

1. Consultations with these affected people having reservations will be continued regularly.
NTDC higher level staff will participate (Project Director, Relevant General Manager or
higher ups) regularly at least in these meetings to discuss and resolve the issues. These
consultations will be documented by NTDC.

2. Rates were further enhanced. It was decided to compensate the people by giving them
land rates higher than already agreed even though acquiring land through Deputy
Commissioner (whose rates are very low compared to the negotiated rates) because of
the inflation. NTDC asked the Deputy Commissioner to assess the rates who constituted
a District Price Adjustment Committee (DPAC) to assess/finalize the rates for land. This
committee comes out with the rate higher than the previous negotiated rate due to inflation.
The enhanced rates have then been approved by NTDC Board of Directors.

43
National Transmission and Despatch Company

The land acquisition process either by negotiations or by using eminent domain, where
negotiations fail, will continue. However, the open hostility demonstrated by those opposing to
project implementation has created notable difficulties in accessing the site and, therefore, in
carrying out (or updating) socioeconomic surveys or stakeholder engagement activities for the
preparation of this RAP.

6.8 Women Involvement in the Consultation Process

6.8.1 Overview of the Process

The fact that women are not seen outside the house makes it difficult to approach them for
information dissemination or stakeholder engagement activities. The problem is exacerbated
for such activities taking place outside the village. For these reasons, during the planning
phase, a gender inclusive consultation process was undertaken. To explore gender related
issues, female staff were included in the team of surveyors. Formal meetings with women
were held to explore their needs, problems and priorities related to project execution. In
addition, individual interviews were also held with affected women to effectively involve them
in the planning process and design tailored programs for women and other vulnerable groups.

6.8.2 Women views and concerns about the Project

The main concerns voiced during the consultation meetings were related to the need for fair
and timely compensation for any lost assets, in a way that their livelihood is not compromised.
Other issues were related to the increased traffic by the construction staff and machinery
during project construction, which may have an impact to the circulation of the community
people, especially women and children. The presence of the construction staff, especially if
they are foreign workers, was also a concern as it may create difficulties to the mobility of local
women and girls.

On the other hand, the project is expected to improve electrification and therefore quality of
life, while project construction was seen as an opportunity for employment of younger
unemployed men and local economic development through the provision of local services.
Women requested that employment is provided to the male members of their families,
combined with skills improvement to increase their chances to work under the project. Skills
development was also mentioned for women and girls, i.e., for embroidery and other in-house
handcrafts that may provide additional sources of income to local households. These issues
will be considered by NTDC during RAP.

During the socioeconomic survey and the consultations, the affected women and vulnerable
groups were explained the structure of compensations, the types of allowances and the
mechanism of disbursements. These are further discussed in appropriate section(s) of the
RAP (see 4.4). It was explained during the consultations that if assets are owned by women,
they will directly receive the compensation and compensation will be paid through cross
cheque. In case of joint ownership of assets (e.g., married couples), the compensation will be
paid to both.

44
National Transmission and Despatch Company

6.9 Disclosure of RAP

The original RAP was disclosed in 2017 both at NTDC and World Bank websites. Updated
RAP will be disclosed to the affected people and will be available on the NTDC website and
Bank’s website for the public at large. NTDC will take the following steps for disclosure of the
RAP:

• Before the start of the RAP implementation, an information booklet containing a


summary of the compensation principles will be prepared specifically for the purpose.
This information booklet or brochure will be translated into Urdu and distributed to all
project APs. This will enable the APs to be aware of their entitlements, unit rates of
compensation/income restoration and rehabilitation assistance and payment
procedures available for various types of APs as given in the Entitlement Matrix. In
addition, the information regarding the GRM will be reflected in the booklet.

• After approval, a shorter version of the RAP (i.e., project footprint, objectives and
benefits, policy framework, entitlement matrix, RAP implementation framework,
responsibility, timeline, costs and budget, M&E framework) will be translated into Urdu
by NTDC and disclosed to APs and other stakeholders by the PMU. The translation of
the RAP will include the Cut-off dates, but exclude the cash compensation amounts to
be paid to the APs.

• RAP will be disclosed to women through a meeting either by a community organization


or project staff. Both versions of RAP (English and Urdu) will be available at the offices
of Project Director, Contractor, and Revenue Department as an official public
document.

• A schedule explaining the date, time and venue for disbursement of compensation
through cheque will be prepared in Urdu and distributed to all APs.

6.10 Consultation Plan during Project Implementation

The consultation will continue during project implementation. A broad framework for the
detailed roadmap is described in Table 6-4 below:

Table 6-4: Consultation and Participation Framework

Description Target Stakeholders Timing Responsibility

- Consultations and - Potential APs; and Before PMU and RAP


participation during communities within implementation Consultants
verification of and around project of project
resettlement impacts area
and AP list
- Location: Village
Kamalpur Miyan and
project area

45
National Transmission and Despatch Company

Description Target Stakeholders Timing Responsibility

- Consultations with the - APs/ Communities Before PMU and RAP


APs/ communities within project area commencement Consultants
during RAP of project
implementation activities and
regularly during
- Location: Village implementation.
Kamalpur Miyan and
project area
- Establishment of GRM - APs/ Communities Before PMU and RAP
and GRCs within project area commencement Consultants
of project
- Location: Village
activities and
Kamalpur Miyan and quarterly during
project area implementation.

- Grievance redress - PMU staff; implementation PMU and RAP


consultants; relevant Stage Consultants
- Location: Village
Kamalpur Miyan and line departments; and
project area APs (as needed).

- Consultations with the - APs/ Communities Construction PMU and RAP


APs/ communities within project area Stage Consultants
during internal
monitoring
- Location: Village
Kamalpur Miyan and
project area
- Fortnightly meetings at - PMU staff; Construction PMU and RAP
project site consultants; and APs Stage Consultants
- Location: Site offices (as needed).

- Consultations with the - APs/ Communities Construction M&E


APs/ Communities within project area Stage Consultants
during the Independent
Monitoring
- Location: Village
Kamalpur Miyan and
project area
- Consultation workshops - APs/ Communities Six-monthly PMU and RAP
to review RAP within project area; during Consultants
implementation, any relevant NGOs implementation
outstanding issues and phase
grievances, views and
concerns of APs; and
actions needed to
address them.

46
National Transmission and Despatch Company

Description Target Stakeholders Timing Responsibility


- Location: site offices
within project area.
- Consultations with the - PMU; project Construction/ PMU;
APs/ Communities consultants; APs Operation Stage WB Mission
during the site visits by
the World Bank Review
Missions.
- Location: Village
Kamalpur Miyan and
project area.

The consultation meetings will be properly reported in the the form of reports (with
pictures/photos) and shared with the communities and posted in the project website.

47
National Transmission and Despatch Company

7 GRIEVANCE REDRESS MECHANISM

7.1 Introduction

NTDC has already prepared a document titled “The Grievance Redress Mechanism (GRM)”,
outlining the processes for documenting, addressing, responding and employing methods to
resolve project grievances (and complaints) that may be raised by APs or community
members regarding major project specific activities such as, environmental and social
performance, the stakeholder engagement process, land acquisition and resettlement and/or
unanticipated social impacts resulting from project activities that are performed and/or
undertaken by NTDC. The document describes the scope and procedural steps and specifies
roles and responsibilities of the parties involved. It applies to all World Bank, ADB and other
foreign donor funded projects, including the proposed one.

7.2 Structure of the Grievance Redress Mechanism

The project will have two-tier GRM with designated staff responsibilities at each level. These
levels comprise the following:

GRC at PMU Level (GRC-P)

NTDC will appoint a Grievance Redressal Committee (GRC-P) at PMU/PIU level to resolve
all grievances and complaints of the APs and the Complainants. The GRC-P shall comprise
of the following members:

• Project Director (or his representative), NTDC as Convener of GRC

• Deputy Manager (Social & Environment), NTDC as Secretary of GRC

• Representative of Land Acquisition Collectors (LAC) as Member

• Independent Consultant (a retired Land Acquisition Collector (LAC) (or equivalent who
has knowledge of the land acquisition and process to resolve issues) as Member

• Representative from the Project Implementation Consultant (male and female)

• Any notable personality from the area to be nominated in writing by the relevant District
Administration in consultation with the community.

• Representatives of the APs

During deliberations, NTDC can call representative from any other Department for
consultation and advisory services for resolution of grievances. There will be a Complaint Box
at the PMU office on site in Islamabad West Grid Station and a dedicated telephone number
for registration of any complaints. The PMU Office will also designate a person, not below the

48
National Transmission and Despatch Company

rank of an Office Assistant, who shall record the complaints and immediately report them to
CO Head/Executive Engineer and concerned officials.

The GRC-P, through an authorized representative, will acknowledge the complainant about
his complaint, scrutinize the record, explore the remedies available and request the
Complainant to produce any record in favor of his claim. After thorough review and scrutiny of
the available record on complaint, visit the field and collect additional information, if required.
Once the investigations are completed, the GRC shall provide with a decision within 21 days
of receipt of the complaint. If the aggrieved person is not satisfied, he/she will be allowed to
elevate the complaint to next level of GRM for resolution of his/her grievances within 07 days
after communication of decision by the GRC-P.

GRC-P has provision for representatives (both male and female) from the community. These
will be nominated by the project affected persons and selected by NTDC in consultation with
them. However, the area is conservative and culturally sensitive and female involvement is
very limited in activities outside their homes. Keeping this in view, female representation in
GRC-P will be difficult. If there are any specific grievance(s) lodged by any female in the project
area, the gender specialist in the project will facilitate the process.

GRC at NTDC Headquarter (HQ) Level

NTDC will constitute a Grievance Redressal Committee (GRC-HQ) at HQ level. The


committee will have the following composition:

• General Managers Projects Delivery North/South (as relevant) as member, being the
convener

• Additional Director General ESIC as member

• Gender Focal Point or NTDC female manager as member

• Representative of the Land Directorate as member

• Representative of the Legal Department as member

This GRC-HQ, through authorized representative, will acknowledge the complainant about his
complaint, scrutinize the record of the GRC-P, investigate the remedies available and request
the complainant to produce any record in favor of his claim. After thorough review and scrutiny
of the available record on complaint, visit the field and collect additional information, if required.
Once the investigations are completed, the GRC-HQ shall give decision within 21 days of
receipt of the complaint. If the complainant is still dissatisfied with the decision, he can go to
the court of law, if he/she wishes so.

Gender representation will be ensured by appointing a female member in both GRCs. The
mechanism will ensure the access of APs to a GRM that openly and transparently deals with
the grievances and makes decision in consultation with all safeguard system.

49
National Transmission and Despatch Company

7.3 Grievance Redress Mechanism

The intention of GRM is to resolve a complaint as quickly and at as low a level as possible to
avoid a minor issue becoming a significant grievance. Irrespective of the stage of the process,
a Complainant has the option to pursue the grievance through the court as his or her legal
right in accordance with law. The details of the process are given below:

7.3.1 Grievance Redress Procedure

a. The grievance or complaint will be addressed to the Convener of GRC-P/HQ with copy
to DMD (AD&M). This can be launched in writing, through telephone or verbally at office. If the
complaint is verbal, the office will arrange to convert verbal complaint in written form;

b. A serial number will be assigned to it together with the date of receipt;

c. A written acknowledgement to the Complainant will be sent promptly within three


working days. The acknowledgement will contain:

i. The name and designation of the authorized representative (if the designated
representative is in another office then the relevant address will also be included) who
will deal with the grievance.

ii. Information that necessary action will be taken within the specified
working days from the date of receipt of the grievance by the authorized representative
concerned.

d. If the office receiving the grievance/complaint is not the one designated to consider
and resolve it, the receiving office will forward it to the designated office, but after having
complied with the requirements at (b to c) above;

e. The GRC will provide an opportunity of hearing to all the concerned parties and
examine the relevant record before making the final decision;

f. The GRC or its representative designated to consider the matter will make every effort
to ensure that grievances/appeals are considered and resolved preferably within the stipulated
period; and

g. The complete records of all activities will be kept and filed into the grievance database
maintained by both GRCs. The GRCs will also be responsible to compile records of the GRM
and make quarterly reports to the WB or any other concerned Authority.

7.3.2 Follow Up and Close Out

The complaint will be considered as resolved and closed when:

• The designated GRC has decided/resolved the grievance/complaint;

50
National Transmission and Despatch Company

• Where the Complainant has indicated acceptance of the response of the GRC in
writing;

• Where the complainant has not responded to the Grievance Redress staff within one
month of being sent the final decision of the grievance officer on his
grievance/complaint;

• Where the Complainant fails to attend the proceedings of the GRC within the stipulated
period of the resolution of the complaint; and

• Where the Complainant withdraws his/her complaint.

7.4 Documentation of GRC Cases

All records of GRC cases shall be properly maintained by the PMU Office, including minutes
of meetings and decisions made by the GRC. The complaints received in writing or received
verbally (or by phone) will be entered and properly recorded and documented. The meeting
minutes at various GRCs will be recorded and decisions made will be as part of the input in
the case record document and filed properly by respective GRCs.

The outcomes of GRC deliberations and decisions will be notified in written form by the Chair
of the GRC within a week from the date of the meeting. The decisions taken are mandatory
on the NTDC with regard to any additional awards or compensation to be paid to the
disputants. The records of all GRC cases must be available for review and verification by
NTDC, WB, Independent monitoring consultants and other interested stakeholders.

7.5 Current Operating Status of GRM

The current status for GRM implementation includes the following;

• the GRM Standard Operating Procedure was approved and notified by NTDC;

• Both GRCs have been notified, trained and made operational;

• Meetings are being held

51
National Transmission and Despatch Company

8 INSTITUTIONAL SETUP FOR RAP IMPLEMENTATION

8.1 General

A Project Management Unit (PMU) has been established within NTDC and has been
mandated to manage the design, procurement, and construction activities of the project. The
PMU is also responsible to ensure compliance with the national as well as WB environmental
and social safeguard requirements including preparation of environmental and social
assessment documents including the present RAP. The PMU will also ensure implementation
of the RAP in line with the national as well as WB safeguard policy requirements. The PMU is
headed by the Chief Engineer/Project Director.

For the implementation of RAP, several entities will be involved including the PMU itself,
Environment and Social Impact Cell (ESIC) established within PMU, Project Consultants
responsible for design and construction supervision of the project, relevant government
departments, APs, and others. Roles and responsibilities of these entities are described
below.

8.2 Institutional Setup

8.2.1 The PMU

As described above, a PMU has been established to manage the project including design,
procurement, construction, testing and commissioning. The PMU is headed by the Chief
Engineer/Project Director. The PMU has its own technical staff, contract specialist,
procurement specialist, Environment and Social Impact Cell (ESIC), and other necessary
officials and staff.

With respect to the RAP implementation, the PMU’s role will be to supervise and support ESIC
to ensure that all aspects of RAP are effectively implemented and that the project complies
with the national regulatory as well as WB safeguard policy requirements.

8.2.2 The ESIC

The ESIC is already in place within PMU and is mandated to ensure compliance with the
national regulatory as well as WB safeguard policy requirements pertaining to environment,
social, and resettlement aspects. Currently the ESIC has three members at the headquarters
(i.e., Deputy Manager, Social and Environment: focal person for environmental, social and
resettlement aspects; Assistant Manager (Social) and Assistant Manager (Environment).
Assistant Manager (Occupational Health and Safety) will be hired soon.

For the RAP implementation, the ESIC will have the following specific functions and
responsibilities:

• Assist and supervise the Project Consultants for the implementation of the approved
RAP in accordance with the procedure and schedule given in this document. The ESIC

52
National Transmission and Despatch Company

will hold monthly meetings with the Project Consultants and PIU to review the RAP
implementation progress, to identify related gaps and issues, and to determine
corrective actions needed;

• Maintaining close liaison and coordination with various project entities including Project
Consultants, project affected persons and Grievance Redress Committee (GRC);

• Maintaining liaison with regulatory agencies/authorities and WB specialists, as


needed;

• Preparation and dissemination of RAP implementation progress reports in coordination


with the Project Consultants;

• Assist and supervise the Project Consultants for updating RAP, if required, at the final
design stage, including additional inventory surveys, measurements, assessment, and
valuation in coordination with concerned departments.

8.2.3 Field-Level Construction Camp Office

Under the PMU-Director, the Project will establish a Field-level Construction Camp Office for
project implementation purposes. The main function of the Camp Office (CO) will be to
coordinate and supervise the construction activities in the field. For the purpose of RAP
implementation, the CO will include the following, in addition to its own technical staff including
an Executive Engineer: (i) Representative of ESIC or a suitable staff designated by NTDC at
CO; (ii) Representatives of contractor; (iii) Representatives of the Project Consultants; (iv)
NTDC Patwari. The responsibilities of CO ESIC Team include the following:

• Maintain liaison and interaction with the APs and local communities to address their
concerns;

• Help the APs to forward their complaints, if any, to the GRC;

• Maintain close liaison with PMU, ESIC, contractor, and relevant government
departments for RAP implementation;

• Distribute the notices to the entitled APs regarding payment of compensation; and

• Facilitate the APs for completing the necessary documentation to receive their entitled
payments.

8.2.4 Project Implementation Consultants (PIC)

Project Implementation Consultant(s) will be responsible to supervise the construction


contractor. They will also be responsible to support for RAP implementation. A representative
of the consultants will be needed at CO to support this with supervision and reporting
responsibilities. Their key responsibilities in this context will include:

53
National Transmission and Despatch Company

• Support implementation of the approved RAP in accordance with the procedure and
schedule given in this document and in coordination with the CO. Maintain an up-to-
date record of RAP implementation. Hold regular meetings with ESIC and CO
regarding the RAP implementation progress, to identify related gaps and issues, and
to determine corrective actions needed;

• Facilitate timely payment of compensation to the APs;

• Support PMU and CO in operating the grievance redress mechanism (GRM) for the
project;

• Maintain close liaison and coordination with various project entities including CO, ESIC
and GRC;

• Maintain close liaison and coordination with various government departments including
Revenue, Forest, C&W and Agriculture;

• Support implementation of framework for community consultations included in RAP


and information disclosure to ensure APs are well aware of the project impacts,
eligibility, entitlements, compensation and allowances, schedule of compensation
disbursement, complaints and grievance redress procedure, and all relevant project
related information;

• Maintain close liaison and coordination with local communities particularly with APs.
Inform APs about the process of compensation disbursement. Facilitate them in
preparation of required documents for compensation payments;

• Maintain liaison with regulatory agencies/authorities and WB specialists, as needed;


and

• Establish and maintain a database for inventory of losses, details of various categories
of APs, compensation amount for each AP, details of compensation payment made to
APs, grievances received, grievances resolved, consultations, and details of
vulnerable APs.

8.2.5 Coordination with Government Departments

The line departments which are relevant for RAP implementation include Forest Department
in case of damage to any forest trees; Agriculture Department for valuation of crop damages;
Public Health Engineering Department in case of any government-owned tube-wells are
affected; C&W Department in case of any damage to local roads. The CO will be responsible
to contact the concerned departments in a timely manner and maintain liaison during the
construction works.

54
National Transmission and Despatch Company

8.2.6 Project Affected Persons’ Committee

The project affected person committee (PAPC) will be formed by NTDC (DTLP) at the field
level with participation from each village. The PAPC will have a chairperson, a secretary and
members. The PAPC will be responsible for the following activities:

• Disclosure of project and RAP information among the communities particularly the
APs.

• Help and facilitate the APs in completing the requisite documents for compensation
payments

• Ensuring payment of compensation in accordance with the entitlement matrix given in


the approved RAP.

• Facilitate early resolution of grievances and complaints raised by the communities


particularly APs.

• Interaction between the community particularly APs and the CO, Project
Implementation Consultants and ESIC.

• Participate in the survey of the affected communities and APs

• Participate in the consultations to be carried out by CO, ESIC, Project Implementation


Consultants, and monitoring consultants.

In sum, the primary purpose to PAPC is to facilitate the implementation of the project with
inputs from the affected communities and to develop a sense of ownership of the project.

8.2.7 Independent Monitoring Consultant (IMC)

NDTC will hire an IMC to conduct independent monitoring for the implementation of RAP. This
is further discussed in Chapter 10 Monitoring and Evaluation (see Section 10.4)

8.2.8 Grievance Redress Committees (GRC)

The GRCs will be established under GRM for addressing conflicts and appeal procedures
regarding eligibility and entitlements during RAP implementation. GRC will receive and
facilitate the resolution of APs’ concerns and grievances. It will ensure that the procedures are
accessible by APs and are gender sensitive. The details have already been discussed in an
earlier chapter.

8.2.9 District Governments

District-based agencies have jurisdiction over land acquisition and compensation activities.
Land acquisition functions rest with the Board of Revenue represented at District level by the
Deputy Commissioner/LAC. LAC maintains official records and also possesses the

55
National Transmission and Despatch Company

Legal/Administrative authority for land titling and therefore assuring eligibility of APs for
compensation.

Other staff members of the Revenue Department, most notably Quanongo and Patwari, carry
out specific roles such as titles identification and verification of the ownership.

During the implementation process LAC would appoint officers to assist in establishing the
identity of the owners of the affected properties. These officers, assisted by PMU staff, would
be in-charge of land records and revenue.

8.3 Organogram

An Organogram showing the institutional arrangements for the implementation of RAP is


illustrated in Figure 8-1 below.

8.4 Capacity Building and Safeguard Training

The ESIC staff, including those to be recruited from the market for project implementation
under the PMU in Construction Camp Office, will be provided with at least one-week training
for social and resettlement capacity building prior to mobilizing to the field. The training will be
conducted by reputed trainers and professionals with experience in resettlement
implementation experience in Pakistan and internationally.

The Project will periodically organize study tours and exposure trips of ESIC/Project staff
within and outside the country. As a start, the ESIC Team will be taken to the Dasu
Hydropower Project for training and exposure to see, observe and learn hands-on how DHP
has been managing the massive resettlement and social development programs and the
implementation challenges. Post-training de-briefing sessions will be held in seminar form to
discuss the learnings and application in the context of the Islamabad West GS project.

8.5 Implementation Schedule

The commencement of civil works will be subject to the satisfactory implementation of this
RAP including completion of payment of compensation of land acquisition, crops, structures
and livelihood assistance and redress of community concerns. It is expected that the
construction of the IWGS will be completed over a period of four years (2021-2025).
Compensation and allowances payment will be complete by mid-2022. RAP completion report
will be prepared after completion of RAP implementation. A preliminary implementation
schedule is given in Figure 8-2. RAP completion report will be conducted after completion of
RAP implementation.

56
National Transmission and Despatch Company

Figure 8-1: Institutional set-up for the Implementation of RAP

NTDC
World Bank
PMU
(CE/ PD)
Project
Implementation
Consultants

Contractor

Environmental and Social


Independent Impact Cell (ESIC)
Monitoring Consultant (PMU)

- Dy. Manager (Social & Env.)


- Assistant Manager (Social)
- Assistant Manager
(Environment)
- Assistant Manager (OHS)

District Level Coordination


Camp Office
- DO (R)/ LAC (At Field Level)
- DO (Agriculture) - Executive Engineer (NTDC)
- Directorate (Horticulture) - DO (Revenue)/ LAC
- DFO - Representatives of ESIC Grievance Redress Committee
- C&W Department - Contractor - Executive Engineer (NTDC)
- WAPDA - Project Consultant (RS, GRS, GS, - DO (Revenue)/ LAC
- PHED M&E, and SMs)
- Representatives of ESIC
- Other concerned - Patwari (Revenue Clerk)
- Representative of Consultants
departments/officials - Representative of APs/ PAPC
(GRS, RS and SM)
- Representative of APs

CE: Chief Engineer


C&W: Communication & Works Affected Persons (APs)
DFO: District Forest Officer
DO: District Officer
DO (R): District Office, Revenue
GS: Gender Specialist
GRS: Grievance Redress Specialist
LAC: Land Acquisition Collector
M&E: monitoring and evaluation
PD: Project Director
PHE: Public Health Engineering
RS: Resettlement Specialist
SM: Social Mobilizer

57
National Transmission and Despatch Company

Figure 8-2: RAP Implementation Schedule


Sr. No Items 2021 2022 2023 2024 2025

1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q

Draft RAP submitted to WB for


1
comments
2 Submission of Final RAP to WB
3 Establishing of GRC
Public Consultation and information
4
disclosure
5 RAP Disclosure
6 Hiring of Independent Consultant
Compensation disbursement
7
Procedure
Payment of compensation including
8
allowances
9 Internal Monitoring
10 External Monitoring
11 Possession of land
12 Contractor works
13 RAP Completion Audit

58
National Transmission and Despatch Company

9 COST AND BUDGET

9.1 General

This section provides the indicative compensation cost for land acquisition and resettlement
for the Islamabad West Grid Station project. Efforts were made to work out realistic cost
estimates/values that lead to fair compensation based on current market rate. For this
purpose, concerned Government Departments, i.e., Forest, Revenue and Agriculture were
consulted. The rates obtained from the departments were escalated using the inflation rates.
In sum, the total resettlement and livelihood restoration cost is PKR 1,260.62 Million (USD 7.5
Million).

The entire budget for RAP will be financed by NTDC. Although, the construction of the
Islamabad West Grid Station will take 3 years, RAP implementation will be completed by the
end of 2023. The Bank will review and monitor RAP implementation. Further, third party
independent verification of the compensation payments will be carried out during the
implementation.

9.2 Provisions for Resettlement Budget

The costs for RAP, including cost of compensation as negotiated and all other implementation
cost, are considered an integral part of Project cost. RAP includes the (i) unit compensation
rates for all affected assets and allowances, (ii) methodology followed for the computation of
unit compensation rates, and (iii) a cost table for all compensation expenses including
administrative costs and contingencies. Costs for external monitoring tasks will also be
allocated under the loan. NTDC will disburse the funds directly through the PMU office to
the eligible persons.

In case compulsory acquisition is applied, funds will be transferred to the DC by NTDC.


Compensation disbursement committees will disburse compensation to APs.

In case of delay in compensation, the compensation amount to be disbursed will be adjusted


as per the current inflation rate and the additional compensation amount due to inflation
adjustment will also be arranged by the NTDC. The provisions for such additional cost have
been taken care in the contingency.

59
National Transmission and Despatch Company

9.3 Itemized Cost Summary

9.3.1 Land

Land will be acquired through private negotiation and compulsory acquisition. In compulsory
acquisition, the rate assessed by the DPAC is PKR 4,351,600/acre 4 which is higher than the
previously negotiated rate. Based on assessment during preparation of RAP the current
estimation for land compensation is about PKR 887.7 million. In total 202 acres of land will
be acquired due to project implementation (plus 2 acres for the extension of the access road).

9.3.2 Crops

The cropping pattern of the Project area is comprised of wheat, maize and vegetables. The
net income per acre from these crops was obtained through the socio-economic survey. The
average yield of wheat in area is 1,024 Kgs per acre 5. The rate per Kg of Wheat as obtained
from the department is PKR 45 per kg (March 2021 rates). The rates were verified by the
Agriculture department.

In total 202 acres of Rabi and Kharif (wheat and Maize crop) are cultivated in the affected land
(plus 2 acres for the extension of the access road).

9.3.3 Trees

A total of 83 trees out of which 11 are fruit trees will be affected due to the project. The
compensation rate for timber trees was obtained from the forest department, and amounts to
7,500 PKR/tree – escalated to 10,650 PKR/tree due to inflation.

9.3.4 Structures

A total of 16 residential structures will be relocated due to project implementation. The rates
of Pucca and Kacha structures were obtained from the market and verified by the Building and
Repair department. These rates were escalated using the inflation rates mentioned in
economic survey of Pakistan 6.

In addition, a total of 8 Tube wells will be relocated due to project implementation and the
compensation rate is PKR 74,760/well.

4 The negotiated rate was PKR 495,000 per Kanal (PKR 3,960,000 per acre). The rate for compulsory acquisition is PKR
543,950/Kanal (PKR 4,351,600/acre). The higher rate will be used for the calculations.
5 Refer to Section 2.2.2 of Chapter 2.
6 ibid.

60
National Transmission and Despatch Company

9.3.5 Vulnerability Allowance

Based on the result of the socioeconomic survey, 60 HHs are considered vulnerable as their
income is below the OPL (27 HHs) or are headed by a female (33 HHs). Vulnerability
allowance will be provided as per the details given in Table 9-1 below.

Table 9-1: Vulnerability Assistance to the APs


No of Affected Total Amount
Description Remarks
Household (PKR)
Based on the official poverty line
(PKR 26,000 X 3 = PKR 78,000),
Assistance to the
60 4.7 Million one-time cash amount equal to be
vulnerable APs
paid to each household living below
the official poverty line.

9.3.6 Livelihood Disturbance Allowance

There is provision of livelihood disturbance allowance for the affected households who lose
their productive agricultural land and have agriculture as their main occupation. The census
showed that almost 647 APs (land owners) are losing their land holding while agriculture is
their main source of income. They are entitled to the amount equal to the market value of
gross harvest of the affected land for 1 year (inclusive of winter and summer crops).

9.3.7 Relocation Allowance

There is a provision of relocation allowance for the affected households for the transportation
of households. There are 16 households that will need to be resettled. They are entitled of
one-time cash allowance of PKR 78,000 plus PKR 5,000 for transportation expenses.

9.4 Summary of Budget

The total requirement of funds for compensation payments, restoration and rehabilitation
measures amounting to PKR 1,260.62 Million (7.5 Million USD) is given in Table 9-2.

61
National Transmission and Despatch Company

Table 9-2: Summary of Cost


Total
Rate Cost
Quantity/Total Cost
No. Description Unit
Number (Million (Million
(PKR)
PKR) USD)
A Land Acquisition Cost
1 Land Compensation 204 Acre 4,351,600 887.7
B Crop Compensation
Acre for
2 Crop Compensation 204 92,160 18.8
two crops
Sub Total (A+B=1+2) 906.5 5.4
C Structures, Trees and Tube wells
6,900 sft (30
3 Pucca Structure sft 1,578 10.9
Nos)
4 Kacha Structure 1,610 sft. (7 Nos) sft 878 1.4
Fruit trees=11
5 Trees No. 10,650 0.9
Timber Trees=72
6 Tube wells 8 No. 74,760 0.6
Total (C=3+4+5+6) 13.8 0.1
D Allowances
Livelihood
Acre for
7 Disturbance 647 APs 92,160 18.6
two crops
Allowance
Vulnerability
8 60 AH 78,000 4.7
Allowance
9 Relocation Allowance 16 AH 83,000 1.4
10 Training Cost Lump Sum 10
Total (D=7+8+9+10) 34.7 0.2
Sub - Total (A+B+C+D) 955.0 5.7
Monitoring and
E Evaluation @ 5% of 47.8
the Total Cost
Operation and
Maintenance of GRM
F 9.6
@ 1% of the Total
Cost
Administrative Cost @
G 9.6
1% of the Total Cost
Contingencies @ 25%
H 238.8
of the Total Cost
Total (E+F+G+H) 305.6 1.8
Grand Total 1,260.62 7.5
Note: The inflation rates of 8.7%, 4.8%, 2.8%, 4.1%, 5.1% and 10.6% mentioned in economic survey of Pakistan for years 2013-
2019 have been adopted to calculate escalation.

62
National Transmission and Despatch Company

10 MONITORING AND EVALUATION

10.1 RAP Monitoring Arrangements

The RAP tasks will be monitored internally and externally. The NTDC will carry out internal
monitoring of RAP by the PMU through ESIC with support from consultants. The external
monitoring will be assigned to an Independent External Monitoring Consultant, hired by NTDC
with the concurrence of WB for monitoring of RAP implementation. The Independent
Monitoring Consultant will be mobilized prior to RAP implementation. The extent of monitoring
activities, including their scope and timing, will be commensurate with the project risks and
impacts. The ESIC is required to carry out the safeguard measures and implement relevant
plans as provided in the legal agreements. Internal Monitoring Reports will be prepared
monthly, quarterly and annually for the project mentioned in the RAP.

10.2 Monitoring Indicators

The RAP implementation progress will be monitored by the following indicators:

• % of affected APs having received compensation for crops;

• % of affected APs having received compensation for trees;

• % of vulnerable HH having received vulnerability allowance;

• Number of APs having received skills training by the Contractor;

• Number of APs having employed by the Contractor; and

• Number of vulnerable APs having employed by the Contractor.

10.3 Internal Monitoring

Internal monitoring will be carried out by the ESIC with support from consultants. Internal
monitoring indicators will relate to process, outputs and results. Information will be collected
directly from the field, and will be reported monthly to the PMU to assess the RAP
implementation progress and adjust the work plan if necessary. Specific Internal monitoring
benchmarks will be based on the approved RAP and cover the following:

• Information campaign and consultation with APs;

• Status of land acquisition and compensation payments;

• Compensation for assets;

• Payments for loss of income;

63
National Transmission and Despatch Company

• Income restoration activities;

• Grievance redress status; and

• Ensure the gender mitigation measures in the RAP are adhered to during the internal
monitoring and reporting process.

Gender disaggregated information will be collected by the PMU which will monitor the day-
to-day resettlement activities of the project through the following instruments:

• Review of project information for all APs;

• Consultation and informal interviews with APs;

• Key informant interviews; and

• Community public meetings.

10.4 External Monitoring and Evaluation

NTDC will appoint an independent agency, (i.e., Independent Monitoring Consultant, IMC) for
external monitoring to ensure complete and objective information. The tasks of the IMC are
to:

• Review and verify internal monitoring reports prepared by ESIC;

• Review of the socio-economic and census and inventory of losses baseline information
of pre-displaced persons;

• Update the baseline data if required;

• Identification and selection of impact indicators;

• Impact assessment through formal and informal surveys with the APs;

• Consult APs, officials, community leaders for preparing review report;

• Assess the resettlement efficiency, effectiveness, impact and sustainability, drawing


lessons for future resettlement policy formulation and planning;

• Ensure the gender mitigation measures in RAP are adhered to during monitoring; and

• Assess verifying and reporting of impacts and compensation measures provided to


affected vulnerable groups such as families below the poverty line.

64
National Transmission and Despatch Company

The ToR for external monitoring and evaluation consultant is attached as Annex C. The
following will be considered as the basis for indicators in monitoring and evaluation of the
project:

• Socio-economic conditions of the APs in the post-resettlement period;

• Communications and reactions from APs on entitlements, compensation, options,


alternative developments etc.;

• Changes in income levels;

• Rehabilitation of severely affected people, and different vulnerable groups;

• Valuation of property;

• Ability to replace lost assets;

• Disbursement of compensation and other entitlements;

• Level of satisfaction of APs in the post resettlement period;

• Quality and frequency of consultation and disclosure; and

• Grievance procedures.

Based on the IMC’s report, if significant issues are identified, a corrective measurement plan
will be prepared, reviewed and approved by World Bank and disclosed to project APs. Internal
and external monitoring and reporting will continue until all resettlement activities have been
completed.

10.5 Monitoring Database Management

The IMC will maintain computerized resettlement database that will be updated quarterly. It
will contain files on each displaced household and will be updated based on the information
collected on successive rounds of data collection. All monitoring database will be fully
accessible to NTDC and the World Bank.

10.6 Reporting and Disclosure

The IMC will submit an external monitoring report to NTDC and directly to World Bank on six
monthly basis. The report should summarize the findings of external monitor, including: (i)
progress of resettlement plan updating and implementation; (ii) identification of problem issues
and recommended solution so that implementing agencies are informed about the on-going
situation and can resolve problems in a timely manner; (iii) identification of specific issues
related to vulnerable households; and (iv) a report on progress of the follow-up of issues and
problems identified in the previous report.

65
National Transmission and Despatch Company

The monitoring reports will be discussed in a meeting between the IMC, the NTDC and PMU
held after submission of the reports. Necessary remedial actions will be taken and
documented.

All the monitoring reports will be translated and disclosed as per World Bank involuntary
resettlement policy and monitoring reports will be publicly open and placed on the NTDC and
WB websites.

10.7 Post-Project Evaluation

The Project will undertake a post-project or RAP completion audit after completion of RAP
implementation to assess the success of the RAP measures and to identify the lessons
learned from the implementation of the Islamabad West GS Project. The audit and evaluation
shall contain a comprehensive review of the implementation processes, institutional capacity,
manpower and costs. The report will further determine and highlight how the measures
adopted have been successful in the restoration of livelihoods of the affected people and/or
presented or minimized impoverization of those affected by the project as a learning exercise
for future RAP management.

66
National Transmission and Despatch Company

Annexes

• ANNEX A: QUESTIONNAIRES FOR SOCIOECONOMIC AND CENSUS SURVEYS

• ANNEX B: LIST OF AFFECTED PERSONS CONSULTED

• ANNEX C - TOR FOR MONITORING AND EVALUATION SPECIALIST

• ANNEX D – EVIDENCE OF SURVEYS AND CONSULTATIONS

67
National Transmission and Despatch Company

Annex A: Questionnaires for Socioeconomic and


Census Surveys
SOCIO-ECONOMIC BASELINE SURVEY QUESTIONNAIRE

Date: __________ID No: Moza # Khasra # AP #

_____________________________________________________________________

1. Identification
1.1 Name of Respondent __________________1.2 Father’s Name_______________

1.3 Status of Respondent


Owner ____Tenant____ Share Cropper ____Lease ____ Squatter ____ Other_______

1.4 Respondent CNIC No: ___________________ 1.5 Tribe _________________

1.6
Address______________________________________________________________

Settlement: ____________________________ Tehsil: _________________________

District: _______________________________ Tel #: _________________________

1.7 Demographic Profile of Respondent’s Household


Children M ___________ F ___________ Total _____________

Relations
Business/

Business/

Last Year
Diseases
Occupati

Occupati
Name of

on (See

on (Rs./
Annum)
Income
Codes)

During
Disability Type

From

hip with
(See Codes)
Education

Househol Family
(Y/N)

No
Age

d Head Membe
. (HH) rs
Second Secondar
(See Main Main
ary y
codes)
1
2
3
4
*Other: Rent from property, remittances, net sale of items during a year, net income
from agriculture etc.
Demographic Codes:

68
National Transmission and Despatch Company

a) Relationship: 1=Self, 2=Wife, 3=Son, 4=Daughter, 5=Father, 6=Mother,


7=Brother, 8=Sister, 9=Grand Father, 10=Grand Mother, 11=Bhabhi,
12=Nephew, 13=Father-in-Law, 14=Mother- in- Law, 15=Others
b) Sex: 1=Male, 2=Female
c) Education: 1= Primary 2= Middle 3= Matric, 4= Intermediate, 5= BA/BSc, 6=
MA/MSc, 7=LLB, 8=Engineer, 9=MBBS, 10=Technical Diploma, 11=Dars-e-
Nizami, 12=Can Read Quran, 13= Can Insert Signatures, 14= Illiterate,
d) Occupations: 1=Agriculturist, 2=Shopkeeper, 3= Trader, 4= Govt. Servant,
5=Private Servant, 6=Labour, 7=General Labour, 8=Livestock, 9=Fishing, 10=
8=Driver, 11=Health Related, 12=Educator/Teacher, 13=House-Maid, 14=
House Wife, 15=Gone Abroad, 16=Gone out City within Pakistan 17 Retired
e) Diseases: 1=Diarrhea, 2=Measles, 3=Hepatitis, 4=Typhoid, 5=HIV/AIDS,
6=Polio, 7=Cholera, 8=Tuberculosis, 9=Heart Disease, 10=No Disease,

2. Average Monthly Expenditure on Food and Non-Food Items


2.1 Monthly Expenditure on Food & Non-Food Items (Rs.)
a) Exp. On Food Items
Sr.
Item Qty. / Month Expenditure (Rs.)
No.
1. Wheat / Atta (Flour)
2. Maize Flour
3. Ghee
4. Sugar
5. Pulses
6. Vegetables
7. Tea Leaves
8. Milk
9. Other Specify
10. Meat
Total:

b) Exp. On Non-Food Items:


1. Fire wood
2. Gas Cylinder
3. Kerosene Oil
4. Washing Material
5. Shoes and Clothing
6. Medicines
7. Education
8. Social Obligations
9. Others

69
National Transmission and Despatch Company

Total:

2.4 Av. Monthly utility bills for: Electricity (Rs.) ________________


Communication (Rs.) __________ Water (Rs.) ___________________

3. Possession of Household Goods


Value Value
Item No. Item No.
(Rs.) (Rs.)
Television Car
Washing machine Vehicle
Geyser Tractor
Electric fan Telephone/Mobile
Electric iron Electric Water Pump
Sewing machine Computer
Motor cycle/ scooter Other
Total:

4. Credit
4.1 Have you obtained credit during last year? Yes [ ], No. [ ], if yes, source of
credit:
Formal [ ], Informal [ ]
4.2 Please write the name of relevant source

Formal source (s) _____________________________________________

Informal source (s) ____________________________________________

Percentage of interest _________________________________________

4.3 Purpose of Loan (Tick)


Purchase House  Rs. _____________
Business  Rs. _____________
Repair of House  Rs. _____________
Medicare of Family Member  Rs. _____________
Family/ Social matters  Rs. _____________
Agriculture inputs  Rs. _____________

70
National Transmission and Despatch Company

Livestock  Rs. _____________


Education  Rs. _____________
Other (specify)  Rs. _____________

4.4 Mode of repayment (Tick the relevant)

1) One time [ ] 2) Through installments [ ],

i) Quarterly installments [ ] ii) Six monthly [ ],

iii) Annual [ ] iv) Other (specify) _________

4.5 How much repayment has been made so far? a) 100% [ ], b) 75% [ ], c) 50%
[ ],
d) 25% [ ], Less than 25 % [ ], Not paid yet [ ]

5. Housing Conditions
5.1 Do you have your own house?

1) Yes ____ 2) No. ____

If yes then

Total Area of the house: square ft/Marla.________ Present Value________Rs.

Semi
Pacca
Type of Room No. of Room Katcha (tick) Pacca
(tick)
(tick)
Living rooms
Verandah
Animal shed
Other shed
Bathroom/Latrine
6. Access to Social Amenities (Tick)

Social Amenities Available Satisfactory Non-Satisfactory


Electricity

71
National Transmission and Despatch Company

Social Amenities Available Satisfactory Non-Satisfactory


Sui Gas
Water Supply
Telephone
Sewerage/Drainage
Health Facility
Education Facility
Others

7 Land Use and Status


7.1 Number of shareholders in ownership ____________
7.2 Land use arrangement
Self __________
Tenant (tenure of tenancy) ________ years/Months
Lease (tenure of lease) ___________ Years/Months
Rent (Rs. / acre) ____________
Share Cropper (Arrangements) ___________
Other _______________

Land Acre Kanal Marla


a. Total Area owned
b. Total Cultivated Area
• Area Under Rabi( winter) Crops
• Area Under Kharif (summer) Crops
c. Uncultivated Area
• Waste land
• Area Under Farm Houses
• Barren Land

7.3 Cropping Pattern, Yield and Cost


Area Sown Price/40 Total Cost
Av.
Sr.
Major Crops Production kgs Incurred
No. Acre Kanal (Kgs) (Rs.) (Rs.)
1 Wheat
2 Maize
3 Tobacco
4 Rice

72
National Transmission and Despatch Company

Area Sown Price/40 Total Cost


Av.
Sr.
Major Crops Production kgs Incurred
No. Acre Kanal (Kgs) (Rs.) (Rs.)
5 Sugarcane
6 Orchards
7 Vegetables
8 Other
Grand Total:

8. Livestock Inventory
Livestock No. Present Value (Rs.)
Buffaloes
Cows
Horse
Donkey
Beefarm
Sheep
Goat
Poultry
Other

9. Trees Inventory Fruit Trees _______ Other Trees _______Total _______


10. Social Organizations
10.1 Are there any existing village/social organizations in your area? _____ (Y/N)

Category Y/N
Religious
Educational
Skill Development Centre
Social Welfare
Women Organization
Other

73
National Transmission and Despatch Company

10.2. Pattern of Decision Making


Which types of decisions are influential in village matters?

Sr.No. Person / Status Decision Pattern %


1 Court
2 Jirga

10.3 Were their decisions considered final and implemented successfully?


1. Yes 2. No

i) Level of acceptability (%) _______ ii) Successful implementation (%)


___________

10.4 Were you involved in any dispute in the past 01 years? 1. Yes 2.
No

10.5 If yes, what was the nature of dispute and how was it resolved

Nature of Dispute Method of Resolution


1. ___________________ _____________________________
2. ___________________ _____________________________
3. ___________________ _____________________________

11. Women’s Participation and Decision Making in Different Activities


11.1 Women participation in different household activities:

Activities Participation (y/n) Decision Making (y/n)


Household activities
Jobs
Farm/Crop activities
Livestock rearing
Sale & Purchase of properties
Social obligations (marriage,
birthday & other functions)
Local representation (councilor/
political gathering)
Education
Others

74
National Transmission and Despatch Company

11.2 Women issues in the project area_____________________________________

12. Proposed Impact of the Project


Increase Decrease
− Employment opportunities
− Marketing facilities opportunities
− Living standard
− Unemployment
− Income generating activities
− Mobility (Access to Resources)
− Quality of drinking water
− Agriculture water
− Other specify________________________________

12.1 General Remarks of the Respondents

13. Resettlement Part


13.1 Ownership of Affected Structures_____________ (Self/rented/landlord
property/relative property

13.2 Affected residential structures


Types of Construction Total Area (sft) Affected Area
Structures Semi
Kacha Pacca Sq. ft. Rft.
Pacca
Houses
Boundary Wall
Ladder
Other
Total

13.2 Impact on Houses

Structures Type of Construction Total Area Affected Area


(Sft)
Kacha Pacca SemiPacca Sq.ft Rft.
Rooms
Cattle Shed

75
National Transmission and Despatch Company

Structures Type of Construction Total Area Affected Area


(Sft)
Kacha Pacca SemiPacca Sq.ft Rft.
Boundary Wall
Other

13.3 Impact on Commercial Structures


Type of Construction Total Area Affected Area
Structures
Kacha Pacca SemiPacca Sq.ft
Shop
Wooden Cabin
DPC
Iron Cabin
Other

13.4 Impact on Community Structure

Type of Affected Structure Type of


Name Size (Sft)
(room/open area/wall) Construction

Schools
Mosque
Graveyard
Health Centre
Shrine
Others
Total:

13.5 Impact on Tube wells


Yes ______ No ______
If yes then
Types of Tube wells No.
Electric
Diesel
Turbine
Other
Total:

76
National Transmission and Despatch Company

13.6 Impact on Utility

Yes ______ No ______


If yes then
Types Nos. / Area
Electric poles
Transformer
Transmission line
Telephone
Other
Total:

13.7 Miscellaneous Impact of the Project


Types Nos. / Area
Hand Pump
Watercourse
Lawn
Other

14. Do you have any alternate residence place?


Yes No
If yes then (tick relevant)
Distance from
House Yes/No Location
current residence (km)
Owned
Tenancy
Relative
Other

15. Vulnerability
_____________________________________________________________
___________________________________________________________________
16. People concern about the project?
_______________________________________________________________

17. Views / Comments of Interviewers


__________________________________________________________________
77
National Transmission and Despatch Company

Name & Signature of Interviewer: _______________________ Date: ____________

Checked By: _____________________ Signature ___________ Date: ____________

78
National Transmission and Despatch Company

B. QUESTIONNAIRE FOR CENSUS SURVEY

ID # [ ]
Date:___________
1. IDENTIFICATION
Name of Respondent ___________________________ Father’s

Name

Village/Mouza:_________________

Address_____________________________

2. CATEGORY OF RESPONDENT:
Status of Respondent (Tick the relevant):

Resident Owner [ ], Resident Tenant [ ], Resident Owner cum Tenant [ ], Resident Absentee [ ]

Business Owner [ ], Business Tenant [ ], Business Owner cum Tenant [ ], Business Absentee [ ]

Farm HH [ ] Tenant [ ], Owner cum Tenant [ ], Land Owner Absentee [ ]

3. DEMOGRAPHIC PROFILE
Total Family member (No.) [_______] Male (No.) [______] Female (No.) [______]
Children below 10 years (No.) [______] Male (No.) [______] Female (No.) [______]
Source of
Occupation Monthly Income (Rs.) Other
Other* Income
Sex Age Annual
Education Main
Sr. (M / F) (Yrs.) Secondary Earnings
Main Secondary Occupati (Rs.)
No. Occupation
on

*Other: Rent from property, remittances, pension and other incomes during the year.

3.1. Total Annual Income (Rs.) __________________________

Total Expenditures (Rs.):__________________________________

Total Expenditures on Food items (Rs.):______________________

Total Expenditures on Non-Food Items (Rs.):__________________

79
National Transmission and Despatch Company

3.2. Social set-up/ethnicity (castes, tribe, decision making etc.)


____________________________________________________________

4. INVENTORY OF STRUCTURES

Nature Size
Sr. Type of of Est. Cost
Remarks
No. Structure Construct L (m) W (m) (Rs.)
ion

5. INFRASTRUCTURE
Nature Size
Type of Est. Cost
Sr. of
Infrastru (Rs.) Remarks
No. Constru L (m) W (m)
cture
ction

6. TREES

Est.
Sr. Type of No. of Total Cost of Remarks
Av. Age Cost
No. Trees Trees the Trees (Rs.)
(Rs. /tree)

7. LAND
Land Use Total
Category Cost of
(such as Land Land
Total Affecte Name Share- Cost of
Sr. agri., Khew Owner- (Rs.)
Land d Land of holders Per
No. barren, at No ship
(acres) (acres) Owner (no.) Acre
residential, (S/M)
commercial,
other)

80
National Transmission and Despatch Company

8. CROP

Affected Cost of
Total Cost
Total Cropped Cropped Crop/ 40kg
No. Name Crop Name of Crop
Area (Acre) Area
(Rs)
(Acre)

9. EMPLOYEES DESCRIPTION
Have you engaged any employ, yes [ ], No [ ], If yes,
How many employees do you have (Nos.)? [ ].
Stay at Site (Tick) Total Fem-
Average Other* Male Children
Family ale
No. Name of Employee Monthly Annual
with Member (No.) (No.)
Income (Rs.) Income Alone (No.)
Family (No.)

*Other: Rent from property, remittances, net sale of items during a year, net income from agriculture etc.

10. DESCRIPTIVE QUESTIONS


1 For this project government need to resettle/relocate you, do you have some
other place to move? Yes [ ], No. [ ]

If Yes: 1. How far away from this place? ___________ km


2. Do you own that alternate place Yes [ ], No. [ ]

81
National Transmission and Despatch Company

2 MODE OF COMPENSATION
1. Land for Land Compensation: Yes [ ], No. [ ]

2. Compensation by Cash: Yes [ ], No. [ ]

3. Both (Land +Cash): Yes [ ], No. [ ]

Community Perceptions associated with the project and what kind of assistance you
expect from the Government/Project?

11. IN CASE OF TENANT:


i) Name of Owner: _____________ ii) Name of your Occupation/Business______
iii) Address of Owner
_____________________________________________________

iv) Av. Monthly Income of Tenant (Rs.) _______v) Av. Monthly Rent (Rs.) ____
vi) Have you made any investment: Yes [ ], No [ ]
If yes, how much amount you have invested Rs. [ ]

12. GENERAL REMARKS OF THE


RESPONDENT:
______________________________________________________________________

______________________________________________________________________

12. GENERAL OBSERVATIONS OF THE


INTERVIEWER:
______________________________________________________________________
______________________________________________________________________

Name & Signature of Interviewer: ___________________________

82
National Transmission and Despatch Company

Annex B: List of Affected Persons Consulted


Survey of 2016

No. Name Occupation Village


1 Sadaqat Ali Farming Kamalpur Miyan
2 Khan Afsar Retired Army Kamalpur Miyan
3 Amanat Khan Laborer Kamalpur Miyan
4 Maqsood Khan Farming Kamalpur Miyan
5 Allah Ditta Mason Kamalpur Miyan
6 Tariq Mahmood Farming Kamalpur Miyan
Mehmood Khan Retired (Wah Kamalpur Miyan
7
Factory)
8 Muhammad Ismail Farming Kamalpur Miyan
9 Iftikhar Ali Laborer Kamalpur Miyan
10 Muhammad Safoor Building Contractor Kamalpur Miyan
11 Doctor Zubair Naib Nazim Kamalpur Miyan
12 Azim Kham Farming Kamalpur Miyan
13 Muhammad Nawaz Khan Farming Kamalpur Miyan
14 Dr. Zahid Political Leader Kamalpur Miyan
15 Muhammad Azim Potential Farmer Kamalpur Miyan
16 Muhammad Maqsood Farming Kamalpur Miyan
17 Ghulam Rasool Farming Kamalpur Miyan
18 M. Shakeel Farming Kamalpur Miyan
19 Abdul Waheed Farming Kamalpur Miyan
20 Muhammad Imran Farming Kamalpur Miyan
21 Muhammad Munir Farming Kamalpur Miyan
22 Aslam Hayat Farming Kamalpur Miyan
23 Ghulam Hussain Farming Kamalpur Miyan
24 Tabarakh Hussain Farming Kamalpur Miyan
25 Gul Zaman Government Servant Kamalpur Miyan
26 Tqriq Khan Farming Kamalpur Miyan
27 Malik Rehmat Farming Kamalpur Miyan
28 Shehzada Khan Farming Kamalpur Miyan
29 Rab Nawaz Farming Kamalpur Miyan
30 Nawazish Farming Kamalpur Miyan
31 Meer Afzal Farming Kamalpur Miyan
32 Abdul Khaliq Farming Kamalpur Miyan

83
National Transmission and Despatch Company

No. Name Occupation Village


33 Muhammad Rafiq Farming Kamalpur Miyan
34 Mushtaq Ahmad Farming Kamalpur Miyan
35 Mubarkh Ali Farming Kamalpur Miyan
36 Niaz Ahmad Farming Kamalpur Miyan
37 Sultan Ali Farming Kamalpur Miyan

Survey of 2020

No. Name Occupation Village


1. Abdul Khaliq S/O Ali Gohar Driver Kamalpur Miyan
2. Azra Begum D/O Sher Zaman Kamalpur Miyan
3. Taimoor Ahmad S/O Abdul Khaliq Private Job Kamalpur Miyan
4. Resham Jan Widow/O Sher Zaman Kamalpur Miyan
5. Pension Ex-Army Kamalpur Miyan
Aurang Zeb S/O Sher Zaman
Man
6. Mubarak Khan D/O Mohammad Khan Teacher Kamalpur Miyan
7. Mohammad Javaid S/O Sher Zaman Labourer Kamalpur Miyan
8. Nusrat Ali S/O Sher Zaman Government Service Kamalpur Miyan
9. Akhtar Ali S/O Sher Zaman Government Service Kamalpur Miyan
10. Gulnaz Malik D/O Mohammad Khan Lawyer Kamalpur Miyan
11. Niaz Begum D/O Sher Zaman Kamalpur Miyan
12. Fiaz Begum D/O Sher Zaman Kamalpur Miyan
13. Nadia Begum D/O Sher Zaman Kamalpur Miyan
14. Nighat Sultana D/O Sher Ahmad Kamalpur Miyan
15. Ahmad Ali S/O Mohammad Mahfooz Agriculture Kamalpur Miyan
16. Akhter Mehmood S/O Sher Ahmad Agriculture Kamalpur Miyan
17. Shamshad Akhtar D/O Ahmad Khan Kamalpur Miyan
18. Khalid Mehmood S/O Sher Ahmad Kamalpur Miyan
19. Nuzhat Sultana D/O Sher Ahmad Kamalpur Miyan
20. Rabnawaz S/O Ahmad Khan Lawyer Kamalpur Miyan
21. Sher Altaf S/O Ahmad Khan Agriculture Kamalpur Miyan
22. Chan Sultan D/O Ahmad Khan Kamalpur Miyan
23. Sajida Perveen D/O Ahmad Khan Kamalpur Miyan
24. Ruqia Bibi D/O Muzaffar Khan Kamalpur Miyan
25. Adil Nawaz S/O Mohammad Nawaz Agriculture Kamalpur Miyan
26. Asif Nawaz S/O Mohammad Nawaz Kamalpur Miyan
27. Taj Khan S/O Feroz Khan Kamalpur Miyan
28. Akbar Khan S/O Mohammad Taj Live Stock Kamalpur Miyan
29. Khalida Bibi D/O Amir Khan Agriculture Kamalpur Miyan
30. Zubair Yousaf S/O Mohammad Yousaf Agriculture Kamalpur Miyan
31. Aziz Yousaf S/O Mohammad Yousaf Agriculture Kamalpur Miyan
32. Umair Yousaf S/O Mohammad Yousaf Agriculture Kamalpur Miyan
33. Tahir Yousaf S/O Mohammad Yousaf Kamalpur Miyan

84
National Transmission and Despatch Company

No. Name Occupation Village


34. Tahira Jabeen Widow/O Tahir Yousaf Agriculture Kamalpur Miyan
35. Rehana Bibi D/O Mohammad Yousaf Agriculture Kamalpur Miyan
36. Rehana Bibi Widow/O M. Siddiq Khan Kamalpur Miyan
37. Irfana Bibi D/O Mohammad Yousaf Agriculture Kamalpur Miyan
38. Irfana Bibi Widow/O M. Tariq Khan Kamalpur Miyan
39. Farah Andleeb D/O Mohammad Kamalpur Miyan
Agriculture
Yousaf
40. Ghazala Bibi D/O Mohammad Yousaf Agriculture Kamalpur Miyan
41. Liaqat Ali Khan S/O Rahim Dad Khan Agriculture Kamalpur Miyan
42. Nafees Begum D/O Rahim Dad Khan Lady Health Worker Kamalpur Miyan
43. Nafees Begum Widow/O Mohammad Kamalpur Miyan
Agriculture
Iqbal
44. Amina Bilqees D/O Mohammad Iqbal Advocate Kamalpur Miyan
45. Private Job / Kamalpur Miyan
Mohammad Azam Khan S/O
Pension - Ex. Army
Mohammad Aslam Khan
Man
46. Nafees Begam D/O Mohammad Aslam Kamalpur Miyan
Khan
47. Nafees Begum Widow/O Muhmind Kamalpur Miyan
Khan
48. Tanveer Muhmind Khan S/O Muhmind Kamalpur Miyan
Army Man
Khan
49. Iftikhar Ahmad S/O Ghazan Khan Business Kamalpur Miyan
50. Maroof Sultan Widow/O Mohammad Kamalpur Miyan
Live Stock
Nawaz
51. Mohammad Afzal S/O Mohammad Kamalpur Miyan
Nawaz
52. Mohammad Nazakat S/O Mohammad Kamalpur Miyan
Nawaz
53. Sadaqat Ali S/O Mohammad Nawaz Kamalpur Miyan
54. Shagufta Shaheen D/O Mohammad Kamalpur Miyan
Agriculture
Nawaz
55. Shagufta Shaheen Widow/O Kamalpur Miyan
Mohammad Shafqat
56. Narghis Shaheen D/O Mohammad Kamalpur Miyan
Nawaz
57. Fakhira Shaheen D/O Mohammad Kamalpur Miyan
Nawaz
58. Mohammad Iqbal S/O Shahnawaz Kamalpur Miyan
59. Musarat Bibi D/O Ghazan Khan Kamalpur Miyan
60. Noor Khan S/O Karam Elahi Agriculture Kamalpur Miyan
61. Sajjad Ahmed S/O Noor Khan Live Stock Kamalpur Miyan
62. Aslam Khan S/O Noor Khan Govt. Service Kamalpur Miyan
63. Qamar Zaman S/O Ghulam Khan Agriculture Kamalpur Miyan
64. Robina Iqbal D/O Mohammad Iqbal Kamalpur Miyan
Khan
65. Samina Iqbal D/O Mohammad Iqbal Kamalpur Miyan
Khan
66. Aurang Zeb S/O Mohammad Ayub Agriculture Kamalpur Miyan

85
National Transmission and Despatch Company

No. Name Occupation Village


67. Faisal Mushtaq S/O Mushtaq Ahmad Agriculture Kamalpur Miyan
68. Naheed Akhtar Widow/O Mushtaq Kamalpur Miyan
Teacher
Ahmad
69. Farooq Sultan D/O Mohammad Akram Kamalpur Miyan
Khan
70. Anwar Sultan D/O Mohammad Akram Kamalpur Miyan
Khan

86
National Transmission and Despatch Company

Annex C - ToR for Monitoring and Evaluation Specialist


External Monitor expert is required to verify and assess the monitoring information relevant to
the implementation of this RAP of Islamabad West Grid Station. The external expert will (i)
verify the internal monitoring undertaken by PMU; (ii) conduct site visits, (iii) conduct meeting
with relevant stakeholders district and provincial authorities involved in land acquisition and
review implementation of resettlement activities semi-annually; (iv) review records of
compensation payments, verify provision of entitlements to affected people and assess the
significance of identified measures in restoring or enhancing AP’s quality of life or livelihood;
(v) advise PMU on safeguard compliance issue that arise in connection with the Project and
agree on timeline in the conduct of agreed activity; (v) in the event of non-compliance, report
to WB any non-compliance identified and recommend corrective actions to be incorporated in
the corrective action plan to be prepared by the PMU..

Scope of Work

• To prepare a monitoring and evaluation plan, for review and approval by the PMU and
WB. The plan should clearly define the activities and deliverables per reporting,
schedule and highlight the scope and strategy of monitoring system, key indicators
and methodology in the collection and analysis of data;

• Validate the internal monitoring and reporting of PMU. The external monitor is
expected to review the adequacy of PMU’s internal monitoring and reporting
procedure, including the number and qualification of company staff engaged in
implementing the RAP at different stages, determine adequacy and integrity of the
process, recommend corrective actions and agree on the schedule of implementation
of these corrective actions, if necessary;
• Validate the adequacy of public consultation and disclosure of information as designed
and described in the RAP. Where necessary, the External Monitor should advise PMU
if additional public consultation and disclosure of information need to be undertaken.
The External Monitor should validate on ground that appropriate consultations and
information disclosure took place;
• Assess the extent to which the entitlement matrix, list of displaced/APs or households
(authorized representative of affected households), and specific entitlements such as
compensation amount and procedure, are followed including timeliness of payment.
The Monitor must closely look into the veracity/correctness of available proof of
compensation such as receipt or any other document stating acceptance of
compensation by the representative of APs/households;
• Assess the adequacy of income restoration strategy and evaluate the matching of
specific livelihood development activities against the needs of the intended
recipients/beneficiaries. The External Monitor should document the implementation of
each activity and determine effectiveness to affected people including women and
vulnerable groups;

87
National Transmission and Despatch Company

• Assess the adequacy of institutional arrangements, specifically the capacity of PMU,


the local authorities involved in the land acquisition and resettlement process and other
organizations expected to implement the RAP to ensure that the objectives of the RAP
and the OP 4.12 are achieved, and suggest necessary enhancement measures, if
necessary;
• Validate the adequacy of the GRM and suggest necessary enhancement measures,
subject to further public consultations and disclosure, if necessary. Verify on the
ground the level of awareness of the community within the project impact area on the
existing GRM, common issues raised, resolution of each registered case, and level of
satisfaction of community on the GRM;
• Conduct an interim audit of land acquisition and compensation and resettlement
activities for people affected by the Project. As part of the audit, the following will be
conducted:
• The socio-economic survey will be undertaken to gather information on the AP's land
area, land use including farm and livelihood activities, yield and income derived from
the affected land, and APs sources of incomes, etc. prior to the Project taking
possession of the land;
• Audit of the status of compensation payments, use of funds received by the affected
people, and current socio-economic living conditions;
• Audit of project impacts on women as well as their needs and concerns and identify
any additional potential assistance for women in affected villages;
• An assessment of whether compensation at replacement cost has been paid, whether
the livelihoods and standard of living of the APs have been restored and whether all
activities implemented are in line with WB’s policy requirements;
• Based on the findings of the audit, the external monitor will prepare a Corrective Action
Plan with estimated budget, timeline and implementation arrangements;
• When unanticipated involuntary resettlement impacts are found during RAP
implementation, the External Monitor should assess and advise PMU the need to
conduct an additional social impact assessment and/or updating of RAP, and ensure
all existing applicable requirements, entitlements, and provisions are followed;
• Document and highlight major problems/issues encountered and lessons learned;
• Where necessary, participate in discussion with PMU and among various Project
lenders (such as WB) and its consultants;
• The External Monitor will conduct semi-annual site visits, interview affected people and
conduct consultations;
• Immediately after completion of RAP implementation, the External Monitor will
undertake a RAP Completion Audit covering all APs. The audit will also be supported
by findings of the socio-economic survey which will include data on livelihoods and
income levels of affected people that would help to determine whether affected
households have been able to restore or improve their socio-economic status
compared to the pre-Project level;

88
National Transmission and Despatch Company

• In the event that the RAP Completion Audit finds that the objectives of the RAP and
the OP 4.12 have not been met, the External Monitor will continue with the quarterly
site visits during the duration of the implementation of the Corrective Action Plan; and
• Within 2 years following the completion of RAP implementation (or Corrective Action
Plan in case Audit findings show non-compliance), conduct annual site visits to monitor
whether affected people have maintained or improved their socio-economic status.

Deliverables

The External Monitor will deliver the following reports:

 A Monitoring and Evaluation Plan, within one month after the appointment
 Interim Audit Report, within 3 months after completion of land acquisition compensation
 payments
 External monitoring reports
 In the event that a Corrective Action Plan is prepared following the audit, prepare a close-
out report upon completion of CAP implementation.
 Following completion of RAP/CAP implementation, prepare annual monitoring reports
thereafter.

External monitoring reports and all other reports will be submitted simultaneously to PMU and
WB. An evaluation report at the end of the project will be prepared with a critical analysis of
the achievements of the program and performance of the project as well as PMU.

Qualification and Experience of Consultant

The Consultant will have sufficient technical capacity to provide the above services and the
specialists will have a Master degree in social science or relevant field and a minimum of 10
years experience in dealing with social/community development projects and demonstrated
experience in the resettlement monitoring requirements, as per involuntary resettlement/land
acquisition, WB's involuntary resettlement operational policy, Pakistan's Land Acquisition Act
of 1894, etc.

89
National Transmission and Despatch Company

Annex D – Evidence of surveys and consultations


Consultation during the 2020 survey

90
National Transmission and Despatch Company

91
National Transmission and Despatch Company

92

You might also like