SUPERSTRUCTURE WORKS
LABOUR COSTS IN CONCRETE WORKS
REINFORCED CONCRETE FRAME(1:2:4) CLASS 20 CONCRETE
ELEMENT QUANTITY/CM COST /HR CM/HR AMOUNT
Vibrated Reinforced 11 1600 2.5 17600
Concrete Class 20
In Strip Foundation
Column Base pits 19 1600 2.5 30400
Columns 8 1600 2.5 12800
Ring and Internal 12 1600 2.5 19200
beams
Blinding 14 1600 2.5 22400
Slabs 24 1600 2.5 38400
MATERIAL COST IN CONCRETE WORKS
REINFORCED CONCRETE FRAME(1:2:4) CLASS 20 CONCRETE
MATERIAL QUANTITY/CM AMOUNT/CM NO COST AMOUNT
CEMENT 88 5 440 1001 440440
0 0
SAND 88 0.57 50.16 2420 121387.2
0 0
BALLAST 88 0.86 75.68 1947 147349
LABOUR COST COST IN REINFORCEMENT
BAR DIA WORKING HRS QUANTITY IN KG NO HRS/50KG COST Amount
20 5.445 99 2.75 375 2041.875
16 156.9 2615 3 375 58837.5
12 10.2 170 3 375 3825
10 430.72 5384 4 375 161520
8 49.68 621 4 375 18630
MATERIAL COST COST IN REINFORCEMENT
BAR DIA COST/1000KG QUANTITY IN KG COST/kg Amount
20 18000 99 120 11880
0
16 18000 2615 120 313800
0
12 18000 170 120 20400
10 18000 5384 120 646080
8 18000 621 120 74520
EXCAVATION
Excavation to reduce levels 2.4 65 450 2.166667 7800
N.e 0.25m 0 0
0 0
Excavation in base pits deoth 4 51 450 2.833333 10200
N.e 2.0m 0 0
0 0
Excavation in trenches deoth 3.3 58 450 2.658333 9570
N.e 2.0m and width n.e 1.0m 0 0
0 0
Filling to make up levels, average 1 66 450 0.916667 3300
thickness not exceeding 0.25 m 0 0
0 0
Disposal of excavated material 1 87 450 1.208333 4350
wheeling not exceeding 50 m
HARDCORE FILL LABOUR
hardcore 300 mm thick to make 1.5 47 450 0.979167 3525
levels,well compacted and rolled in
100 mm thick
HARDCORE FILL MATERIAL
hardcore 300 mm thick to make 65 2000 433333.3
levels,well compacted and rolled in
100 mm thick
ANTITERMITE labour
Approved antitermite treatment 0.2 158 100 0.438889 351.1111
reatment as “Termidor on hardcore
and foundation walls
ANTITERMITE material
Approved antitermite treatment 0.2
reatment as “Termidor on hardcore
and foundation walls