Densidad T-1 = 2.6
Ancho = 6 Mts
Alto = 6 Mts
Largo T-1 = 35 Mts
Radio Giro Techo = 3.3 Mts
3,3 ts
m ts 3,3 m
1,37 mts 1,37 mts
β Area 2
Area 3 Φ Φ
3 mts 3 mts
Area 1
6 mts
= 2,980.33 M3
= 4,500.30 M3
Factor Esponjamiento = 1.51
Densidad T-2 = 2.2
Ancho = 6 Mts
Alto = 6 Mts
Largo T-2 = 47 Mts
Radio Giro Techo = 3.3 Mts
3,3 ts
m ts 3,3 m
1,37 mts 1,37 mts
β Area 2
Area 3 Φ Φ
3 mts 3 mts
Area 1
6 mts
= 3,386.44 M3
= 5,113.52 M3
Factor Esponjamiento = 1.51
Densidad T-3 = 2.2
Ancho = 6 Mts
Alto = 6 Mts
Largo T-3 = 39 Mts
Radio Giro Techo = 3.3 Mts
3,3 ts
m ts 3,3 m
1,37 mts 1,37 mts
β Area 2
Area 3 Φ Φ
3 mts 3 mts
Area 1
6 mts
= 2,810.02 M3
= 4,243.14 M3
Factor Esponjamiento = 1.51
Densidad T-4 = 2.6
Ancho = 6 Mts
Alto = 6 Mts
Largo T-4 = 45 Mts
Radio Giro Techo = 3.3 Mts
3,3 ts
m ts 3,3 m
1,37 mts 1,37 mts
β Area 2
Area 3 Φ Φ
3 mts 3 mts
Area 1
6 mts
= 3,831.85 M3
= 5,786.09 M3
Factor Esponjamiento = 1.51
Densidad T-5 = 2.5
Ancho = 6 Mts
Alto = 6 Mts
Largo T-5 = 34 Mts
Radio Giro Techo = 3.3 Mts
3,3 ts
m ts 3,3 m
1,37 mts 1,37 mts
β Area 2
Area 3 Φ Φ
3 mts 3 mts
Area 1
6 mts
= 2,783.82 M3
= 4,203.57 M3
9.34
Calculo N° de Tiros Rainura RT (kg/cm2) = 184 kg/cm2
longitud ideal = 3.85 PD = 33,627 kg/cm2
Dth = 0.127 K ( Roca Media) = 0.8
D = 0.0508 E Max = 1.10 Mts
X = 0.47
1er Cuadrante Zapatera 0.7
B1 = 0.18 E Max Corregido = 0.77 Mts
W1 = 0.25 N° Espaciamiento = 8
2do cuadrante Esp. Zapatera = 0.77 Mts
B2 = 0.18 Burden = 0.67 Mts
W2 = 0.43
3er Cuadrante Caja 0.9
B3 = 0.30 E Max Corregido = 0.99 Mts
W3 = 0.72 N° Espaciamiento = 2
4to Cuadrante Esp. Caja = 1.02 Mts
B4 = 0.51 Burden = 0.88 Mts
W4 = 1.23
Corona 0.9
E Max Corregido = 0.99 Mts
N° Espaciamiento = 10
Esp. Corona = 0.99 Mts
Burden = 0.86 Mts
Datos Tiros Auxiliares
RT (kg/cm2) = 184 kg/cm2 Perimetro 1 =
PD = 35,665 kg/cm2 N° espaciamiento =
K ( Roca Media) = 0.8 Espaciamiento =
E Max = 1.13 Mts Burden =
4.24
5 Pozos
0.91 Mts
0.79 Mts
1.77
2 Pozos
0.91 Mts
0.79 Mts
Largo pozo = 3.85 Mts
Taco = 0.80 Mts
Carga Primaria = 0.2 Mts
Carga Columna = 2.85 Mts
2.56
2 Pozos
1.20 Mts
1.04 Mts
Largo pozo = 3.85 Mts
Taco = 0.80 Mts
Carga Primaria = 0.2 Mts
Carga Columna = 2.85 Mts