Before using any method for any structure we need to find center to center length ist
Center to center length is defined as the distance from center of one wall to distance from center
u4)DPC @ 20 Rs /m^2
u7)Inside two coats of white wash @9 Rs /m^2 with one coat of col
Center to
center length of 5 +0.3/2
long wall = +0.3/2 = 5.3
Center to
center length of
shortwall = 4 + 0.3/2 +0.3/2 = 4.3
DETAIL OF MEASUREMENT FORM
Sno Description No Length Breadth Height Quantity Unit
Earthwork in
excavation
1
Longwall 2 6.2 0.9 1.4 15.62 M^3
PCC in
foundation 1 M^3
2
Longwall 2 6.2 0.9 0.3 3.35 M^3
Ist class
brickwork in
foundation
Long wall
DPC
Ist Class
brickwork in
superstructure M^3
5
Longwall 2 5.6 0.3 4 13.44 M^3
Plastering
Inside M^2
6 Longwall 2 5 4 40 M^2
Short wall 2 4 4 32 M^2
Total 72
Outside 1
Longwall 2 5.6 4.4 49.28 M^2
7 Short wall 2 4.6 4.4 40.48 M^2
White wash
Inside 1
Longwall 2 5 4 40 M^2
Short wall 2 4 4 32 M^2
8
Total 72
Outside 1
8
1
Earthwork in
excavation 24.19 M^3 375 Rs /M^3 9072
2 PCC in
foundation 5.18 M^3 380 Rs /M^3 1969.92
3
Ist class
brickwork in
foundation 18.8 M^3 300 Rs /M^3 5644.8
4 DPC 5.76 M^2 20 Rs /M^2 115.2
5
Ist Class
brickwork in
superstructure 23.04 M^3 390 Rs /M^3 8985.6
6 Plastering
Inside 72 M^2 12 Rs /M^2 864
7 Outside 89.76 M^2 15 Rs /M^2 1346.4
8 white wash
Inside 72 M^2 11 Rs /M^2 792
9 white wash out 89.76 M^2 11 Rs /M^2 987.36
Total 29777.3 RS
Add
Continge
ncy 3% 893.1 RS
Add
work
charge
establish
ment 2% 595.4 RS
Overall
cost 31265.8 RS
Qno 2
Prepare a detailed estimate of a single room as per the plan and elevation given u
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3
u4)DPC @ 20 Rs /m^2
u7)Inside two coats of white wash @9 Rs /m^2 with one coat of col
Center to
center length of 6 +0.3/2
long wall = +0.3/2 = 6.3
Center to
center length of
shortwall = 4 + 0.3/2 +0.3/2 = 4.3
Earthwork in
excavation
1
Longwall 2 7.2 0.9 1.4 18.14 M^3
PCC in
foundation 1 M^3
2
Longwall 2 7.2 0.9 0.3 3.89 M^3
DPC
Ist Class
brickwork in
superstructure M^3
5
Longwall 2 6.6 0.3 4 15.84 M^3
Plastering
Inside M^2
6 Longwall 2 6 4 48 M^2
Short wall 2 4 4 32 M^2
Total 80
Outside 1
Longwall 2 6.6 4.4 58.08 M^2
7 Short wall 2 4.6 4.4 40.48 M^2
White wash
Inside 1
Longwall 2 6 4 48 M^2
Short wall 2 4 4 32 M^2
8
Total 80
Outside 1
Longwall 2 6.6 4.4 58.08 M^2
Short wall 2 4.6 4.4 40.48 M^2
Total 98.56 M^2
Abstract of estimated cost
1 Earthwork in
excavation 26.71 M^3 375 Rs /M^3 10017
2 PCC in
foundation 5.72 M^3 380 Rs /M^3 2175.12
3
Ist class
brickwork in
foundation 20.8 M^3 300 Rs /M^3 6232.8
4 DPC 6.36 M^2 20 Rs /M^2 127.2
5
Ist Class
brickwork in
superstructure 25.44 M^3 390 Rs /M^3 9921.6
6 Plastering
Inside 80 M^2 12 Rs /M^2 960
7 Outside 98.56 M^2 15 Rs /M^2 1478.4
8 white wash
Inside 80 M^2 11 Rs /M^2 880
9 white wash out 98.56 M^2 11 Rs /M^2 1084.16
Total 32876.3 RS
Add
Continge
ncy 3% 986.1 RS
Add
work
charge
establish
ment 2% 657.4 RS
Overall
cost 34519.8 RS
Qno 3
Prepare a detailed estimate of a single room as per the plan and elevation given u
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3
u4)DPC @ 20 Rs /m^2
u7)Inside two coats of white wash @9 Rs /m^2 with one coat of col
Center to
center length of 4+0.3/2
long wall = +0.3/2 = 4.3
Center to
center length of
shortwall = 3 + 0.3/2 +0.3/2 = 3.3
Earthwork in
excavation
1
1
Longwall 2 5.1 0.8 1.1 8.98 M^3
PCC in
foundation 1 M^3
2
Longwall 2 5.1 0.8 0.6 4.90 M^3
Ist class
brickwork in
foundation
Long wall
DPC
Ist Class
brickwork in
superstructure
5
Longwall 2 4.6 0.3 3.4 9.38 M^3
DEDUCTIONS
LINTELS OVER
DOORS 1 1.4 0.3 0.15 0.06 M^3
LINTELS OVER
WINDOWS 3 1.6 0.3 0.15 0.22 M^3
Total 3.18
Total quantity 12.33 M^3
Plastering
Inside M^2
Longwall 2 6 4 48 M^2
Short wall 2 4 4 32 M^2
Total 80 M^2
6 Deductions
Doors 1 1.2 2.1 2.52 M^2
wndows 3 1.4 1.7 7.14 M^2
Total 9.66 M^2
Final quantity 70.34 M^2
Outside 1
Longwall 2 6.6 4.4 58.08 M^2
Short wall 2 4.6 4.4 40.48 M^2
Total 98.56 M^2
7
Deductions
7
Doors 1 1.2 2.1 2.52 M^2
wndows 3 1.4 1.7 7.14 M^2
Total 9.66 M^2
Final quantity 88.90 M^2
White wash
Inside 1
Longwall 2 6 4 48 M^2
Short wall 2 4 4 32 M^2
Total 80
Deductions
Doors 1 1.2 2.1 2.52 M^2
wndows 3 1.4 1.7 7.14 M^2
Total 9.66 M^2
8 Final quantity 70.34 M^2
Outside 1
Longwall 2 6.6 4.4 58.08 M^2
Short wall 2 4.6 4.4 40.48 M^2
Total 98.56 M^2
Deductions
Doors 1 1.2 2.1 2.52 M^2
wndows 3 1.4 1.7 7.14 M^2
Total 9.66 M^2
Final quantity 88.90 M^2
Abstract of estimated cost
1 Earthwork in
excavation 13.38 M^3 375 Rs /M^3 5016
2 PCC in
foundation 7.30 M^3 380 Rs /M^3 2772.48
3
Ist class
brickwork in
foundation 9.0 M^3 300 Rs /M^3 2690.4
4 DPC 4.2 M^2 20 Rs /M^2 84
5
Ist Class
brickwork in
superstructure 12.327 M^3 390 Rs /M^3 4807.53
6 Plastering
Inside 70.34 M^2 12 Rs /M^2 844.08
7 Outside 88.9 M^2 15 Rs /M^2 1333.5
8 white wash
Inside 70.34 M^2 11 Rs /M^2 773.74
9 white wash out 88.9 M^2 11 Rs /M^2 977.9
Total 19299.6 RS
Add
Continge
ncy 3% 579.9 RS
Add
work
charge
establish
ment 2% 386.6 RS
Overall
cost 20266.1 RS
ter length ist
er of one wall to distance from center of another wall
wall + Half Breadth on One Side + Half Breadth on the Other Side.
adth on One Side- Half breadth of another side
earthwork to brickwork, and the length of the short wall is increased
walls in a building is first calculated, then the center line length is multiplied with the
spective item to get the total quantity at a time.
@300 Rs /m^3
1:4)@390 Rs /m^2
ide @15 Rs /m^2
^2 with one coat of colour wash @11 Rs /m^2
Remarks
Height is from
ground level till
bottom
length of long wall
= 5.3 + 0.9/2
+0.9/2
length of Short
wall = 4.3 - 0.9/2
-0.9/2
length of Short
wall = 4.3 - 0.8/2
-0.8/2
length of Short
wall = 4.3 - 0.6/2
-0.6/2
length of Short
wall = 4.3 - 0.5/2
-0.5/2
1:4)@390 Rs /m^2
ide @15 Rs /m^2
^2 with one coat of colour wash @11 Rs /m^2
Remarks
Height is from
ground level till
bottom
length of long wall
= 6.3 + 0.9/2
+0.9/2
length of Short
wall = 4.3 - 0.9/2
-0.9/2
length of Short
wall = 4.3 - 0.8/2
-0.8/2
length of Short
wall = 4.3 - 0.6/2
-0.6/2
length of Short
wall = 4.3 - 0.5/2
-0.5/2
@300 Rs /m^3
1:4)@390 Rs /m^2
ide @15 Rs /m^2
^2 with one coat of colour wash @11 Rs /m^2
Remarks
Height is from
ground level till
bottom
length of long wall
= 4.3 + 0.8/2
+0.8/2
length of Short
wall = 3.3 - 0.8/2
-0.8/2
length of Short
wall = 3.3 - 0.7/2
-0.7/2
length of Short
wall = 3.3 - 0.6/2
-0.6/2
VOLUME OF DOOR
VOLUME OF
WINDOW
Length of Lintel =
length of opening
+ 2 side bearings lintel bearing = 10 cm
Length of Lintel =
length of opening
+ 2 side bearings lintel bearing = 10 cm