Qno1

Prepare a detailed estimate of a masonry platform as per the plan and elevation
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3

u3) PCC in foundation (1:2:4) @ 380 Rs /m^3

u4)DPC @ 20 Rs /m^2

u5) Ist class brick work in super structure (1:4)@390 Rs /m^2

u6) Plastering inside @12 Rs /m^2 and outside @15 Rs /m^2

u7)Earthfill at center @380 rs

u8)Outside two coats of white wash @ 9Rs /^2

Center to center
length of long 5 +0.3/2
wall = +0.3/2 = 5.3 N= 2

Center to center
length of
shortwall = 4 + 0.3/2 +0.3/2 = 4.3 N= 2

DETAIL OF MEASUREMENT FORM


Sno Description No Length Breadth Height Quantity Unit Remarks

Height is
from
ground
Earthwork in level till
excavation bottom

length of
1 long wall
= 5.3 +
0.8/2
Longwall 2 6.1 0.8 1 9.76 M^3 +0.8/2
1

length of
Short
wall =
4.3 -
0.8/2
Short wall 2 3.5 0.8 1 5.60 M^3 -0.8/2
Total 15.36 M^3

PCC in
foundation 1 M^3

length of
long wall
= 5.3 +
2 0.9/2
Longwall 2 6.1 0.8 0.3 2.93 M^3 +0.9/2

length of
Short
wall =
4.3 -
0.9/2
Short wall 2 3.5 0.8 0.3 1.68 M^3 -0.9/2
Total 4.61 M^3

Ist class
brickwork in
foundation
Long wall

length of
long wall
= 5.3 +
0.6/2
Step 1 2 5.9 0.6 0.4 2.83 M^3 +0.6/2

length of
long wall
3 = 5.3 +
0.5/2
step 2 2 5.8 0.5 0.3 1.74 M^3 +0.5/2
Short wall
3

length of
Short
wall =
4.3 -
0.6/2
Step 1 2 3.7 0.6 0.3 1.33 M^3 -0.6/2

length of
Short
wall =
4.3 -
0.5/2
step 2 2 3.8 0.5 0.3 1.14 M^3 -0.5/2
Total 7.04 M^3

Ist Class
brickwork in
superstructure M^3

length of
long wall
4 = 5.3 +
0.3/2
Longwall 2 5.6 0.3 4 13.44 M^3 +0.3/2

length of
Short
wall =
4.3 -
0.3/2
Short wall 2 4 0.3 4 9.60 M^3 -0.3/2
Total 23.04 M^3

5 Earth fill at
center 1 5 4 4 80 M^3

Plastering
Outside 1

6 Longwall 2 5.6 4 44.8 M^2 outer length of room u

Short wall 2 4.6 4 36.8 M^2 outer length of room u

Total 81.6 M^2

7
white wash
Outside 1
7
Longwall 2 5.6 4.4 49.28 M^2 outer length of room u

Short wall 2 4.6 4.4 40.48 M^2 outer length of room u


Total 89.76 M^2

8
Concrete floor at
center 1 5 4 0.05 1 M^3

9
2 mm top plaster
floor 1 5.6 4.6 25.76 M^2

Abstract of estimated cost

Sno Description Quantity Unit Rate Per unit Amount Unit

1
Earthwork in
excavation 15.36 M^3 375 Rs /M^3 5760

2 PCC in
foundation 4.60 M^3 380 Rs /M^3 1748

3
Ist class
brickwork in
foundation 7.5 M^3 300 Rs /M^3 2247

5
Ist Class
brickwork in
superstructure 23.04 M^3 390 Rs /M^3 8985.6

6 earth fill at
center 80 M^3 280 Rs /M^3 22400

7 PlasteringOutsid
e 81.6 M^2 15 Rs /M^2 1224
8
concrete floor 1 M^3 380 Rs /M^3 380
9 white wash outsi 81.6 M^2 11 Rs /M^2 897.6

10
2 mm top plaster
floor 25.76 M^2 15 Rs /M^2 386.4
Total 44028.6 RS

Add
Continge
ncy 3% 1320.84 RS

Add
work
charge
establish
ment 2% 880.4 RS
Overall
cost 46229.8 RS

Qno2
Prepare a detailed estimate of a masonry platform as per the plan and elevation
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3

u3) PCC in foundation (1:2:4) @ 380 Rs /m^3

u4)DPC @ 20 Rs /m^2

u5) Ist class brick work in super structure (1:4)@390 Rs /m^2

u6) Plastering inside @12 Rs /m^2 and outside @15 Rs /m^2

u7)Earthfill at center @380 rs

u8)Outside two coats of white wash @ 9Rs /^2

Center to center
length of long 6 +0.4/2
wall = +0.4/2 = 6.4

Center to center
length of
shortwall = 4 + 0.4/2 +0.4/2 = 5.4
DETAIL OF MEASUREMENT FORM
Sno Description No Length Breadth Height Quantity Unit Remarks

Height is
from
ground
Earthwork in level till
excavation bottom
1
length of
long wall
Longwall 2 M^3 =
length of
Short
Short wall 2 M^3 wall =
Total 0.00 M^3

PCC in
foundation 1 M^3

length of
long wall
= 5.3 +
2 0.9/2
Longwall 2 M^3 +0.9/2

length of
Short
wall =
4.3 -
0.9/2
Short wall 2 M^3 -0.9/2
Total 0.00 M^3

Ist class
brickwork in
foundation
Long wall
length of
long wall
Step 1 2 M^3 =
Step 2 2 M^3
3 length of
long wall
Step 3 2 M^3 =
Short wall
3

length of
Short
Step 1 2 M^3 wall =
Step 2 2 M^3
length of
Short
Step 3 2 M^3 wall =
Total 0.00 M^3

Ist Class
brickwork in
superstructure M^3

length of
long wall
4 = 5.3 +
0.3/2
Longwall 2 M^3 +0.3/2

length of
Short
wall =
4.3 -
0.3/2
Short wall 2 M^3 -0.3/2
Total 0.00 M^3

5 Earth fill at
center 1 M^3

Plastering
Outside 1

6 Longwall 2 M^2 outer length of room u

Short wall 2 M^2 outer length of room u

Total 0 M^2

white wash
Outside 1
7
Longwall 2 M^2 outer length of room u
7

Short wall 2 M^2 outer length of room u


Total 0 M^2

8
Concrete floor at
center 1 M^3

9
2 mm top plaster
floor 1 M^2

Abstract of estimated cost

Sno Description Quantity Unit Rate Per unit Amount Unit

1
Earthwork in
excavation M^3 375 Rs /M^3 375

2 PCC in
foundation M^3 380 Rs /M^3 380

3
Ist class
brickwork in
foundation M^3 300 Rs /M^3 300

4
Ist Class
brickwork in
superstructure M^3 390 Rs /M^3 390

5 earth fill at
center M^3 280 Rs /M^3 280

6 PlasteringOutsid
e M^2 15 Rs /M^2 15
7
concrete floor M^3 380 Rs /M^3 380
8 white wash outside M^2 11 Rs /M^2 11

9
2 mm top plaster
floor M^2 15 Rs /M^2
Total RS

Add
Continge
ncy 3% 1527.3 RS

Add
work
charge
establish
ment 2% 1018.2 RS
Overall
cost 2545.5 RS

Qno3
Prepare a detailed estimate of a masonry platform as per the plan and elevation
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3

u3) PCC in foundation (1:2:4) @ 380 Rs /m^3

u4)DPC @ 20 Rs /m^2

u5) Ist class brick work in super structure (1:4)@390 Rs /m^2

u6) Plastering inside @12 Rs /m^2 and outside @15 Rs /m^2

u7)Earthfill at center @380 rs

u8)Outside two coats of white wash @ 9Rs /^2

Center to center
length of long 6 +0.4/2
wall = +0.4/2 = 6.4

Center to center
length of
shortwall = 6 + 0.4/2 +0.4/2 = 6.4

DETAIL OF MEASUREMENT FORM


Sno Description No Length Breadth Height Quantity Unit Remarks
Height is
from
ground
Earthwork in level till
excavation bottom
1
length of
long wall
Longwall 2 M^3 =
length of
Short
Short wall 2 M^3 wall =
Total 0.00 M^3

PCC in
foundation 1 M^3
length of
2 long wall
Longwall 2 M^3 =
length of
Short
Short wall 2 M^3 wall =
Total 0.00 M^3

Ist class
brickwork in
foundation
Long wall
length of
long wall
Step 1 2 M^3 =
Step 2 2 M^3
3 length of
long wall
Step 3 2 M^3 =
Short wall
length of
Short
Step 1 2 M^3 wall =
Step 2 2 M^3
length of
Short
Step 3 2 M^3 wall =
Total 0.00 M^3
Ist Class
brickwork in
superstructure M^3
4 length of
long wall
Longwall 2 M^3 =
length of
Short
Short wall 2 M^3 wall =
Total 0.00 M^3

5 Earth fill at
center 1 M^3

Plastering
Outside 1

6 Longwall 2 M^2 outer length of room u

Short wall 2 M^2 outer length of room u

Total 0 M^2

white wash
Outside 1
7
Longwall 2 M^2 outer length of room u

Short wall 2 M^2 outer length of room u


Total 0 M^2

8
Concrete floor at
center 1 M^3

9
2 mm top plaster
floor 1 M^2

Abstract of estimated cost


Sno Description Quantity Unit Rate Per unit Amount Unit

1
Earthwork in
excavation M^3 375 Rs /M^3 375

2 PCC in
foundation M^3 380 Rs /M^3 380

3
Ist class
brickwork in
foundation M^3 300 Rs /M^3 300

4
Ist Class
brickwork in
superstructure M^3 390 Rs /M^3 390

5 earth fill at
center M^3 280 Rs /M^3 280

6 PlasteringOutsid
e M^2 15 Rs /M^2 15
7
concrete floor M^3 380 Rs /M^3 380
8 white wash outside M^2 11 Rs /M^2 11

9
2 mm top plaster
floor M^2 15 Rs /M^2
Total RS

Add
Continge
ncy 3% 1527.3 RS

Add
work
charge
establish
ment 2% 1018.2 RS
Overall
cost 2545.5 RS
an and elevation given use following specifications

0 Rs /m^2
5 Rs /m^2
outer length of room upto ground level

outer length of room upto ground level


outer length of room upto ground level

outer length of room upto ground level


an and elevation given use following specifications

0 Rs /m^2
5 Rs /m^2
outer length of room upto ground level

outer length of room upto ground level

outer length of room upto ground level


outer length of room upto ground level
an and elevation given use following specifications

0 Rs /m^2
5 Rs /m^2
outer length of room upto ground level

outer length of room upto ground level

outer length of room upto ground level

outer length of room upto ground level


Qno1
Prepare a detailed estimate of a masonry platform as per the plan and elevation gi
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3

u3) PCC in foundation (1:2:4) @ 380 Rs /m^3

u4)DPC @ 20 Rs /m^2

u5) Ist class brick work in super structure (1:4)@390 Rs /m^2

u6) Plastering inside @12 Rs /m^2 and outside @15 Rs /m^2

u7)Earthfill at center @380 rs

u8)Outside two coats of white wash @ 9Rs /^2

Center to
center length 5 +0.3/2
of long wall = +0.3/2 = 5.3 N 2

Center to
center length
of shortwall = 4 + 0.3/2 +0.3/2 = 4.3 N 2
total center to center length = 5.3X2 + 4.3 x2 = 19.2
outside length for plastering = 5.6x2+4.6x 2 = 20.4 m

DETAIL OF MEASUREMENT FORM


Sno Description No Length Breadth Height Quantity Unit

1
Earthwork in
excavation 1 19.2 0.8 1 15.36 M^3

2 PCC in
foundation 1 19.2 0.8 0.3 4.608 M^3

Ist class
3 brickwork in
foundation
3
Step 1 1 19.2 0.6 0.4 4.61 M^3
step 2 1 19.2 0.5 0.3 2.88 M^3
Total 7.49 M^3

4 Ist Class
brickwork in
superstructu
re 1 19.4 0.3 4 23.28 M^3

5 Earth fill at
center 1 5 4 4 80 M^3

6 Plastering
Outside 1 20.4 4 81.6 M^2

white wash
Outside 1 20.4 4 81.6 M^3

8 Concrete
floor at
center 1 5 4 0.05 1 M^3

9
2 mm top
plaster floor 1 5.6 4.6 25.76 M^2

Abstract of estimated cost

Sno Description Quantity Unit Rate Per unit Amount Unit

1
Earthwork in
excavation 15.36 M^3 375 Rs /M^3 5760

2 PCC in
foundation 4.60 M^3 380 Rs /M^3 1748
3
Ist class
brickwork in
foundation 7.5 M^3 300 Rs /M^3 2247

4 Ist Class
brickwork in
superstructu
re 23.04 M^3 390 Rs /M^3 8985.6

5 earth fill at
center 80 M^3 280 Rs /M^3 22400

7 PlasteringOu
tside 81.6 M^2 15 Rs /M^2 1224
8 concrete
floor 1 M^3 380 Rs /M^3 380
9 white wash ou 81.6 M^2 11 Rs /M^2 897.6

10
2 mm top
plaster floor 25.76 M^2 15 Rs /M^2 386.4
Total 44028.6 RS

Add
Continge
ncy 3% 1320.6 RS

Add
work
charge
establish
ment 2% 880.4 RS
Overall
cost 46229.6 RS

Qno2
Prepare a detailed estimate of a masonry platform as per the plan and elevation gi
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3

u3) PCC in foundation (1:2:4) @ 380 Rs /m^3


u4)DPC @ 20 Rs /m^2
u5) Ist class brick work in super structure (1:4)@390 Rs /m^2

u6) Plastering inside @12 Rs /m^2 and outside @15 Rs /m^2

u7)Earthfill at center @380 rs

u8)Outside two coats of white wash @ 9Rs /^2

Center to
center length 6 +0.4/2
of long wall = +0.4/2 = 6.4 N 2

Center to
center length 5 + 0.4/2
of shortwall = +0.4/2 = 5.4 N 2
total center to center length = 6.4X2 + 5.4 x2 = 23.6
outside length for plastering = 6.8x2+5.8x 2 = 25.2

DETAIL OF MEASUREMENT FORM


Sno Description No Length Breadth Height Quantity Unit

1
Earthwork in
excavation 1 M^3

2 PCC in
foundation 1 M^3

Ist class
brickwork in
3 foundation
Step 1 1 M^3
Step 2 1
Step 3 1 M^3
Total 0.00 M^3
4 Ist Class
brickwork in
superstructu
re 1 M^3

5 Earth fill at
center 1 M^3

6 Plastering
Outside 1 M^2

white wash
Outside 1 M^3

8 Concrete
floor at
center 1 M^3

9
2 mm top
plaster floor 1 M^2

Abstract of estimated cost

Sno Description Quantity Unit Rate Per unit Amount Unit

1
Earthwork in
excavation M^3 375 Rs /M^3 375

2 PCC in
foundation M^3 380 Rs /M^3 380

3
Ist class
brickwork in
foundation M^3 300 Rs /M^3 300
4 Ist Class
brickwork in
superstructu
re M^3 390 Rs /M^3 390

5 earth fill at
center M^3 280 Rs /M^3 280

7 PlasteringOu
tside M^2 15 Rs /M^2 15
8 concrete
floor M^3 380 Rs /M^3 380
9 white wash outside M^2 11 Rs /M^2 11

10
2 mm top
plaster floor M^2 15 Rs /M^2 15
Total 2146 RS

Add
Continge
ncy 3% 1320.6 RS

Add
work
charge
establish
ment 2% 880.4 RS
Overall
cost 4347 RS

Qno3
Prepare a detailed estimate of a masonry platform as per the plan and elevation gi
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3

u3) PCC in foundation (1:2:4) @ 380 Rs /m^3

u4)DPC @ 20 Rs /m^2

u5) Ist class brick work in super structure (1:4)@390 Rs /m^2

u6) Plastering inside @12 Rs /m^2 and outside @15 Rs /m^2


u7)Earthfill at center @380 rs
u8)Outside two coats of white wash @ 9Rs /^2

Center to
center length 6 +0.4/2
of long wall = +0.4/2 = 6.4 N 2

Center to
center length
of shortwall = 6 + 0.4/2 +0.4/2 = 6.4 N 2
total center to center length = 6.4X2 + 6.4 x2 = 25.6
outside length for plastering = 6.8x2+6.8x 2 = 27.2

DETAIL OF MEASUREMENT FORM


Sno Description No Length Breadth Height Quantity Unit

1
Earthwork in
excavation 1 M^3

2 PCC in
foundation 1 M^3

Ist class
brickwork in
3 foundation
Step 1 1 M^3
Step 2 1
Step 3 1 M^3
Total 0.00 M^3

4 Ist Class
brickwork in
superstructu
re 1 M^3
5 Earth fill at
center 1 M^3

6 Plastering
Outside 1 M^2

white wash
Outside 1 M^3

8 Concrete
floor at
center 1 M^3

9
2 mm top
plaster floor 1 M^2

Abstract of estimated cost

Sno Description Quantity Unit Rate Per unit Amount Unit

1
Earthwork in
excavation M^3 375 Rs /M^3 375

2 PCC in
foundation M^3 380 Rs /M^3 380

3
Ist class
brickwork in
foundation M^3 300 Rs /M^3 300

4 Ist Class
brickwork in
superstructu
re M^3 390 Rs /M^3 390

5 earth fill at
center M^3 280 Rs /M^3 280
7 PlasteringOu
tside M^2 15 Rs /M^2 15
8 concrete
floor M^3 380 Rs /M^3 380
9 white wash outside M^2 11 Rs /M^2 11

10
2 mm top
plaster floor M^2 15 Rs /M^2 15
Total 2146 RS

Add
Continge
ncy 3% 1320.6 RS

Add
work
charge
establish
ment 2% 880.4 RS
Overall
cost 4347 RS
per the plan and elevation given use following specifications

@300 Rs /m^3

(1:4)@390 Rs /m^2
side @15 Rs /m^2

Remarks

Height is from
ground level till
bottom
per the plan and elevation given use following specifications

@300 Rs /m^3
(1:4)@390 Rs /m^2
side @15 Rs /m^2

Remarks

Height is from
ground level till
bottom
per the plan and elevation given use following specifications

@300 Rs /m^3

(1:4)@390 Rs /m^2
side @15 Rs /m^2
Remarks

Height is from
ground level till
bottom

You might also like