Professional Documents
Culture Documents
attention.
As suggested earlier in the discussion of the exponential rule for estimating, the
value of the cost exponent may influence the decision whether extra capacity should be built
to accommodate future growth. Similarly, the
economy of scale may also influence the decision on rehabilitation at a given time. As the
rehabilitation work becomes extensive, it becomes a capital project with all the implications of its
own life cycle. Hence, the cost estimation of a rehabilitation project may also involve capital and
operating costs.
DETAILED ESTIMATE
Method of estimating
Before undertaking the construction of a project it is necessary to know its probable
cost which is worked out by estimating. An estimate is a computation or calculation of the quantities
required and expenditure likely to be incurred in the construction of a work. The primary object of
the estimate is to enable one to know beforehand, the cost of the work (buildings, structures, etc).
The estimate is the probable cost of a work and is determined theoretically by mathematical
calculations based on the plans and drawing and current rates. Approximate estimate may be
prepared by various methods but accurate estimate is prepared by Detailed Estimate Method.
Detailed estimate
Preparation of detailed estimate consist of working out the quantities of different
items of work and then working out the cost ie, the estimate is prepared in two stages.
Quantity
Abstract of estimated cost
The cost under item of work is calculated from the quantities already computed at workable rate,
and the total cost is worked out in a prescribed form, Abstract of Estimate Form. A percentage of 3
to 5 percent is added for contingencies, to allow for petty contingent expenditures, unforeseen
expenditures, changes in design, changes in rates, etc. which may occur during the execution of the
work. Apercentage of 1.5 to 2 per cent is also added to meet the expenditure of work‐ charged
establishment. The grand total thus obtained is the estimated cost of the work
In this method, measure or find out the external length of walls running in the longitudinal
direction generally the long wall out‐to‐out, and the internal lengths of the walls running in the
transverse direction in‐to‐in ie, of cross or short walls in‐ to‐in, and calculate quantities
multiplying the length by the breadth and the height. The same rule applies to the excavation in
foundation, to concrete in foundation and to masonry.
Height
Item Particulars of Lengt Breadth or Total
No Quantity Explanatory note
No Items h(m) (m) Depth Quantity
(m)
1 Earth work in
excavation
in foundation
Length = 5.30 + 0.90 =
2 6.20 0.90 0.90 10.04
long wall 15.55 6.20 m
cum Breadth = 4.30 ‐
2 3.40 0.90 0.90 5.51
Short wall 0.90=3.40 m
2 Concrete in
foundation 5.18
Long wall 2 6.20 0.90 0.30 3.35 cum
Short wall 2 3.40 0.90 0.30 1.83
3 Brick work in
foundation
and plinth
Long wall First
Length = 5.30+0.60 =
2 5.90 0.60 0.30 2.13
footing second 5.90 m
Length = 5.30+0.50 =
2 5.80 0.50 0.30 1.74
footing 5.80 m
Length = 5.30+0.40 =
2 5.70 0.40 0.60 2.74
Plinth walls 5.70 m
10.95
Short wall First
cum
Length = 4.30‐0.60 =
2 3.70 0.60 0.30 1.33
footing second 3.70 m
Length = 4.30‐0.50 =
2 3.80 0.50 0.30 1.14
footing 3.80 m
Length = 4.30‐0.40 =
2 3.80 0.40 0.60 1.87
Plinth walls 3.90 m
4 Brick work in
superstructure
20.16 Length = 5.30+0.30 =
2 5.60 0.30 3.50 11.76
Long wall cum 5.60 m
Length = 4.30‐0.30 =
2 4.00 0.30 3.50 8.40
Short wall 4.00 m
Method‐ II
In this method known as centre line method sum‐total length of centre lines of walls, long and
short, has to be found out. Find the total length of centre lines of walls, of same type, long and short
having same type of foundations and footings and then find the quantities by multiplying the total
centre length by the respective breadth and the height. In this method, the length will remain same
for excavation in foundation, for concrete in foundation, for all footings and for superstructure
(with slight different when there are cross walls or number of junctions). This method is quick but
requires special attention and consideration at the junctions, meeting points of partition or cross
walls, etc.
Height or
Item Particulars of Breadth Total Explanatory
No Length(m) Depth (m) Quantity
No Items (m) Quantity note
1 Earth work in Total centre
excavation length of all
15.55 walls = 19.20
1 19.20 90.00 0.90 10.04
in foundation cum m
2 Concrete in
5.18
foundation
cum
Long wall 1 19.20 0.90 0.30 3.35
3 Brick work in
foundation
and plinth
First footing 1 19.20 0.60 0.30 3.46
second footing 1 19.20 0.50 0.30 2.88 10.95
cum
Plinth walls 1 19.20 0.40 0.60 4.61
4 Brick work in
20.16
superstructure
cum
1 19.20 0.30 3.50 20.16
Height
Item Breadth or Total
Particulars of Items No Length(m) Quantity
No (m) Depth Quantity
(m)
1 earth work excavation (a)
Foundation trenches centre
line method 1 16.40 0.70 0.90 10.32
L&S Wall method
Long wall 2 5.00 0.70 0.90
short wall 2 3.20 0.70 0.90 10.32