Professional Documents
Culture Documents
2.0
A) Detailed Estimate:
The complete work is divided into various items of work such as Earth work ,
Concreting work, Brick work, R.C.C. work, Plastering work etc.
The details of measurements are taken from drawings and entered in respective
columns of prescribed pro-forma ( Table- 1). The quantities are calculated by
multiplying the values that are entered in the respective column as shown
below:
1
S.No. Description No Length Breadth Depth/ Quantity Explanatory
or (L) (B) Height of Item Notes
Particulars m m D/H m
2) Revised Estimate:
3) Supplementary Estimate:
2
Annual Repair or Annual Maintenance Estimate is a detailed estimate and
is prepared to maintain the structure or work in proper order and in safe
condition. This includes white washing, painting, minor repairs etc.
√ √ √ √ √
2.2 Building cost Index: This is the index indicating the increase or
decrease of the cost above certain base year. The cost index depends on the
increase or decrease of the cost of materials, labour, transportation cost etc.
The department uses this index above or below the SOR to indicate the present
rate.
4
concrete deduct one breadth of trench or concrete from the total centre length.(
½ breadth for one Junction i.e. 1 breadth for 2 Junctions)
EX.-1:
From the Drawing given below determine:
(a) Earth work in excavation,
(b) CC (1:5:10) Bed ,
(c) Brick Masonry in C.M.(1:4) in footing and plinth
(d) Brick Work in C.M.(1:6).
Single Roomed Building (Load Bearing type structure)
5
Measurement of item of Works
6
Measurement of item of Works
EXERCISE:
1. List the difference between centre line method and long wall-short wall
method of taking out measurements.
2. What are the rules to be followed while taking the measurements?
3. Mention the units for the following items.
a) flooring b) R.R. Masonry c) Plastering for pointing d) Damp proof course e)
R.C. sunshade (Specified width and thickness)
7
EX.2
From the Drawing given below, determine the
(a) Earth work in excavation;
(b) PCC work in (1:5:10) for Bed;
(c)Brick Masonry in CM. (1:6) in foundation and plinth;
(d)4cm thick DPC in (1:1.5:3)
(e) Brick Work in C.M.(1:6) in super structure by
(i) long wall - short wall method and
(ii) Centre line Method.
8
Measurement of Materials and Works
9
a) Long Walls 2 8.1 0.3 3.45 16.767 L= 7.8+.15+.15=8.1
b) Short Walls1 3 4.2 0.3 3.45 13.041 L= 4.5-.15-.15=4.2
c) Short Walls2 1 3.6 0.3 3.45 3.726 L= 3.9-.15-.15=3.6
33.534 Cum
Deductions: Doors 2 1.1 0.3 2.1 1.386
Windows 5 1 0.3 1.5 2.25
Ventillators 5 1 0.3 0.5 0.75 Ht of verandah 2.4m
Verandah 1 5.6 0.3 2.4 4.032 L=3.9+1.7=5.6m
8.418
Net Total = 33.534-8.418= 25.116
No of Joints=4
10
Ex. :3
Calculate the abstract of estimate for the Ex.2
ABSTRACT OF ESTIMATE
Sl DESCRIPTION OF ITEMS No Qnty Unit Rate Per Amount
Rs
1 Earth work in Excavation 1 27.9 Cum 110.50 Cum 3082.95
2 PCC Work in foundation 1 6.2 Cum 837.05 Cum 5189.71
1st class Brick Work in c.m. 1:5 in 1
3
foundation and plinth 21.66 Cum 1120.00 Cum 24259.20
4 2.5 cm DPC in 1:1.5:3 1 9.76 Sqm 350.10 Sqm 3416.98
1st class Brick Work in c.m. 1:4 in 1
5
Super Structure 25.12 Cum 1237.50 Cum 31086.00
TOTAL Rs. 67034.84
Contingencies @ 3% of the
6.
estimated cost 3% of =
Supervision Charges @8% of the
7.
estimated cost 8% of =
TOTAL Rs.
EX.4
From the given plan and section of a RCC framed building prepare a detailed
estimate for the RCC works and the quantity of steel reinforcements for the
following items of works :
a) Footings
b) Plinth and roof beams
c) Columns and
d) Roof slabs.
Consider following percentage of steel for different RCC works
i) Footing - 0.5%
ii) Beams- 1%
iii) Columns- 1.5%
iv) Roof slab- 0.8%
Solution:-
C to C Length of Long walls = 3.6+3.6+2X(.3/2)+.3=7.8m
C to C Length of Short walls1 = 4.2+2X(.3/2)=4.5m
C to C Length of Short walls2 = 3.6+2X(.3/2)=3.9m
11
Ht./D
Sl Description of items No L(m) B(m) Qnty Remarks
(m)
RCC Work in 1:2:4 in cols, beams slabs and chajjas etc. fair finished excluding steel reinforcement but
including centering and shuttering and binding steel
FOOTINGS
Sq. bottom 8 1 1 0.2 1.60
Trapezoidal Portion =
h/6( A1+A2+ 4 Am)
8 0.156 1.248
=0.3/6(1x1+0.4x0.4 +
4x0.7x0.7)=0.156
2.85
TOTAL =
Cum
2.952 Ht= 0.5+0.6+3.6-0.3-0.3-
COLUMNS 8 0.3 0.3 4.10
cum =4.10 m
PLINTH BEAMS
4
( excl. columns)
1.30
long walls 2 7.2 0.3 0.3 L=7.8-0.6=7.20 ,,
Short walls1 1 4.2 0.3 0.3 0.38 L=4.5-0.3=4.2 ,,
2 3.9 0.3 0.3 0.70 L=4.2-0.3=3.9 ,,
Short walls2 1 3.6 0.3 0.3 0.32 ,,
ROOF BEAMS
long walls 2 7.2 0.3 0.3 1.30 ,,
Short walls1 1 4.2 0.3 0.3 0.38 ,,
2 3.9 0.3 0.3 0.70 ,,
Short walls2 1 3.6 0.3 0.3 0.32 ,,
TOTAL = 5.40 Cum
ROOF SLAB 1 9.1 5.8 0.12 6.33 L=7.8+.3+2x0.5=9.1m
12
B=4.5+.3+2X0.5=5.8m
Steel reinforcement including bending in RCC
Footing @ 0.5% 2.85 0.50% 78.5 1.12 qntles
Columns @1.5 % 2.84 1.50% 78.5 qntles
3.35
5 Plinth and roof beams @1.0% 5.40 1.00% 78.5 qntles
4.24
13