Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
Validity: Three year from the date of approval or till completion of the specified activity.
Facility / Department: Job Location: Specify Activity to be assessed: - Assessment team members Signature
Reviewed By (Marafiq coordinating Dept.) Reviewed By (Marafiq OHS Section) Approved By (Marafiq
Operations Dept.)
Name:
Name:
Signature: Name:
Signature
Date: Signature:
Date:
Time: Date:
Time:
Time:
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 2of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
Table – a: Risk Heat Map Table Table – b: Risk Bands / Risk Levels
Likelihood Risk Bands Score Range (RPN) Risk Level
Medium Critical Critical 1–4 1 Low
5 Expected High (10) High (15)
(5) (20) (25) 5–9 2 Medium
Highly Medium Critical 10 – 19 3 High
4 Low (4) High (12) High (16)
likely (8) (20) 20 – 25 4 Critical
Medium
3 Likely Low (3) Medium (9) High (12) High (15)
(6)
Medium Table – d: Environmental Impact Scale
2 Slight Low (2) Low (4) Medium (6) High (10) Score Description Environment
(8)
Medium Environmental catastrophe
1 Not likely Low (1) Low (2) Low (3) Low (4)
(5) Long-term environmental damage (require >5 years to recover)
5 Severe
Minor Moderate Important Material Severe Require SAR >40 million to restore or rectify
Impact 1 2 3 4 5 Revoke of EPO
Significant environmental damage
Table – c: Mitigation strategies of the Risk Level Table Medium-term environmental damage (require >1-5 years to recover)
4 Material
Require SAR >4 million up to 40 million to restore or rectify
Score Risk Level Typical Mitigation Strategies
RCER Class III violations (continuous environmental violation)
Range
Short-term environmental damage (require >24 hours but <1 year to
1–4 Low (1) Accept and continually monitor the risk.
recover)
3 Important
5–9 Reduce/transfer the risk to acceptable level based on some Require SAR >400,000 up to 4 million to restore or rectify
logical analysis (preferably cost-benefit analysis). RCER Class II violations (frequent environmental violation)
Medium (2)
Otherwise accept and continually monitor the risk. Marginal environmental damage which can be corrected within 24
hours
10 – 19 Reduce/transfer/avoid the risk to acceptable level – 2 Moderate Require SAR >100,000 up to 400,000 to restore or rectify
High (3) priority action/decision required. RCER Class I violations
Negligible environmental damage which can be corrected within 2
20 – 25 Critical (4) Reduce/transfer/avoid the risk to acceptable level – high
hours
priority or immediate action/decision required. 1 Minor
Require SAR 40,000 up to 100,000 to restore or rectify
RCER Class 0 violations
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 3of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
The Initial and Residual risks shall be calculated as per the rating criteria detailed in tables d, e, f & g above to decide on at Risk Priority Number (RPN) from the table b.
RPN is calculated as ‘RPN=Impact X Likelihood’.
Use table ‘a’, the 5x5 Risk Heat Map to identify the rate for the Impact and likelihood.
1. Mobilization of Tools, Vehicle Physical Injuries Comply with RPN= I X L Do not exceed RPN= I X L
PROPRIETARY NOTICE Reviewed By DC: Stamp Control
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE THEREOF IS EXPRESSLY
PROHIBITED EXCEPT UPON THE WRITTEN PERMISSION OF MARAFIQ.
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 4of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 5of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
entering
congested
area.
2. Installation of New Tire Slip, Trip and Personal injury, Barricade the 3(I)*2(L) Comply with 2(I)*1(L)
Stopper fall. Property area with RPN=6 Marafiq RPN=2
damage warning tape OHSMS
safety Level procedure for Level
signboards. 2 housekeeping 1
Maintain
housekeeping
Inhalation of Respiratory TBT must be 3(I)*2(L) Hover up the 2(I)*1(L)
dust particles problems and conduct RPN=6 dust don’t RPN=2
skin problems before start sweep
may happen of work to Ensure strict use
workers. Level of PPE’S at Level
Use face 2 working time 1
shield, Filter
mask type (N-
95) (FFP-
1).safety
gloves, safety
glass.
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 6of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
Noise May cause Comply with 3(I)*2(L) Ensure strict use 2(I)*1(L)
temporary Marafiq RPN=6 of PPE’S at RPN=2
hearing disability OHSMS working time
Procedure for Provide regular
Noise and Level breaks from high Level
Vibration. 2 noise work 1
Must wear
earplugs and
earmuff.
Provide anti
vibration
gloves.
Vibration It could damage Provide Anti 3(I)*2(L) Comply with 2(I)*1(L)
joints and leads Vibration RPN=6 Marafiq OHSMS RPN=2
to vibration Gloves. procedure for
white finger Ensure Level Noise and Level
regular job 2 Vibration 1
breaks
Electrical shock Burns/ fatality Use insulated 4(I)*2(L) Comply with 3(I)*2(L)
and Fire and property cord wire and RPN=8 Marafiq OHSMS RPN=6
damage cord wire procedure for Hot
must be Level work and Hot Level
2 work safety. 2
mounted if
Comply with
not it may
Marafiq OHSMS
have tripping procedure for
hazard. Hand and
Inspect the Portable power
work area tools
PROPRIETARY NOTICE Reviewed By DC: Stamp Control
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE THEREOF IS EXPRESSLY
PROHIBITED EXCEPT UPON THE WRITTEN PERMISSION OF MARAFIQ.
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 7of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
before start
work may be
the area is
flammable,
Explosive
area.
Ensure
electrical
equipment’s
are not
overloaded
Comply with
PTWC
Provide a Fire
Extinguisher
6kg(DCP).
Sharp objects Cut and physical Sharp Objects 4(I)*2(L) Comply with 3(I)*1(L)
injury to the must have RPN=8 Marafiq RPN=3
body safety guard. OHSMS
Tools must be procedure
in good Level Level
condition 2 1
Heat Stress Exposure to Provide cool 4(I)*2(L) Comply with 3(I)*1(L)
extreme heat will water during RPN=8 OHSMS RPN=3
result in heat working guidelines for
stroke, interval Level heat stress. Level
exhaustion, Drink plenty of 2 1
syncope, cramps water to
and rashes which prevent
leads to fatal dehydration
PROPRIETARY NOTICE Reviewed By DC: Stamp Control
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE THEREOF IS EXPRESSLY
PROHIBITED EXCEPT UPON THE WRITTEN PERMISSION OF MARAFIQ.
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 8of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 9of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
4. Covid -19 Symptoms: Wear PPE’S like 4(I)*3(L) Comply with 3(I)*1(L)
Infection from elevated mask safety RPN=12 ministry of RPN=3
corona virus temperature gloves and health guidelines
respiratory illness safety glass. Level for preventing Level
which leads to Keep social 3 corona virus 1
death distancing
avoid hand
contact with
others
Wash hand
frequently with
soap and water
and use
sanitizers
frequently.
Comply OHSMS
PROPRIETARY NOTICE Reviewed By DC: Stamp Control
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE THEREOF IS EXPRESSLY
PROHIBITED EXCEPT UPON THE WRITTEN PERMISSION OF MARAFIQ.
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 10of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 11of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018
Power and Water Utility Company for Jubail and Yanbu
Page 12of 13
Rev. No.: 1
RISK ASSESSMENT
Date: 09 01 2019
Sr. Tools and other work equipment Qty Sr. Safety and Emergency items Qty
9 Safety Signs LS
10 Warning Tape LS
11 Water Cooler 01
12 Safety Shoes LS
IMPORTANT
Only documents with stamps are considered official.
Document ID No : MEHF-1-SF- 018