You are on page 1of 2

Check List No wr/MFG/06

WORK INSTRUCTION
Rev No 00
PROCEDT'R.E FOR FRP LAMINATION Rev. Date: or /04 /2ot7
(HAND LAY-T'P} Page No Page 1 of 1

Sr. No Procedure
1 Purpose To describe the procedure for FRP Lamination

2 Responsibility Production Supervisor

3 Procedure
First of all mould is prepared. The outside diameter of the mould should kept
3.1
as inside diameter of the tank.be
A film of Polyvinyl alcohol (PVA) which acts as a mould release agent is
3.2
applied over the wax polished surface of the mould.
Then a thin layer of resin is applied on the mould surface to give the
c.c moulding a smooth surface and to protect the glass fibre from e)dernal
influences
Then a layer of surface mat is applied on the mould. A resin is applied on the
Surface mat with help of brush. Surface mats are the thin tissues of glass
3.4 fibre which absorbs a high percentage of resin which gives the resin rich
surface and good corrosion resistance. Sometimes a Ethylene tissue is also
used which improves the impact and abrasion resistance of FRP laminate
.E A roller is used to remove the air bubbles from the FRP laminate.
Subsequent layers of chopped strand mat and woven roving are applied
5.b
along with the resin until the required thickness rs achieved
A suitable glass trssue is used as a final layer of reinforcement to have a
37 smooth Surface flnish.
All the FRP laminates can be post cured in accordance with the resin
3.8
suppliers lnshuctions.

End of Document

n'-pared by : (MFG) p Controlled Copy Stamp Approved by:


. rte Ot lO4 /2Or7 (Managing Director)

p)
wy'
Date : Ol lO4l2ol7

Simature: Signature:
Check List No wr/MFG/07
WORK INSTRUCTION
Rev No 00
PROCEDI'RE rlOR FABRICATION OF Rev. Date or /04 /2or7
LINED FRP EQIIIPMETITS Page No: Page 1 of 1

Sr. No Procedure

1 Purpose To describe the procedure for Fabrication of lined FRP equipments


2 Responsibility Production Supervisor
3 Procedure 1 First of all wooden mould is prepared. The outside diameter of the mould
should be kept as inside diameter of the tank.
2 Thermoplastic sheets are welded and placed on the mould and again welded.

3 The welding is spark tested to ensure that there is no pinhole

4 The welding is backed up in a conductive manner using carbon veil so


that spark testing could be done even after erection at site
5 On top of the thermoplastic sheet, a coat of resin is applied.

6 This is followed by CSM and WR impregnated each layer of resin as per


the lay- up sequence
7 Lamination is completed with Surfacing mat and flood coat of resin.

8 Connection are fixed and mould is to be removed

9 lnside thermoplastac welding is to be done

End of the Document


Prepared by : (MFG) M c6 p Controlled Copy Stamp Approved by:
Date : Ol lO4l2Ol7 (Managing Director)
Date:. Ol lO4l ot7
*
4 n
Signature; Signature

You might also like