1 Galian tanah biasa A.2.3.1.1. 17.28 m3 31,877.00 550,834.56
2 Urugan tanah kembali A.2.3.1.9.1. 22.06 m3 10,625.66 234,402.06
3 Beton sloof 20/25 (S1)
- Beton K 175 (menggunakan alat) A.4.1.1.5.2. 1.50 m3 1,141,284.56 1,711,926.84
- Pembesian A.4.1.1.17.1a. 222.43 Kg 15,674.53 3,486,485.71
- Bekisting A.4.1.1.21 15.00 m2 162,527.08 2,437,906.20
4 Beton sloof Selasar 20/20 (S2)
- Beton K 175 (menggunakan alat) A.4.1.1.5.2. 0.48 m3 1,141,284.56 547,816.59
- Pembesian A.4.1.1.17.1a. 59.18 Kg 15,674.53 927,618.69
- Bekisting A.4.1.1.21 4.80 m2 162,527.08 780,129.98
5 Beton FootPlat (FP1)
- Beton K 125 (menggunakan alat) A.4.1.1.2.2. 0.20 m
3 1,062,940.56 212,588.11
- Beton K 225 (menggunakan alat) A.4.1.1.7.2. 1.42 m
3 1,141,284.56 1,620,624.08
- Pembesian A.4.1.1.17.1a. 161.64 Kg 15,674.53 2,533,631.03
- Bekisting A.4.1.1.21 2.86 m
2 162,527.08 464,827.45
- Pasir Urug A.2.3.1.11. 0.20 m3 176,910.80 35,382.16
6 Beton FootPlat (FP2)
- Beton K 125 (menggunakan alat) A.4.1.1.2.2. 0.40 m
3 1,062,940.56 425,176.22
- Beton K 225 (menggunakan alat) A.4.1.1.7.2. 2.84 m
3 1,141,284.56 3,241,248.15
- Pembesian A.4.1.1.17.1a. 181.75 Kg 15,674.53 2,848,845.83
- Bekisting A.4.1.1.21 2.86 m
2 162,527.08 464,827.45
- Pasir Urug A.2.3.1.11. 0.40 m3 176,910.80 70,764.32
7 Beton FootPlat (FP3)
- Beton K 125 (menggunakan alat) A.4.1.1.2.2. 0.11 m
3 1,062,940.56 116,923.46
- Beton K 225 (menggunakan alat) A.4.1.1.7.2. 0.91 m
3 1,141,284.56 1,038,568.95
- Pembesian A.4.1.1.17.1a. 31.21 Kg 15,674.53 489,202.08
- Bekisting A.4.1.1.21 1.20 m
2 162,527.08 195,032.50
- Pasir Urug A.2.3.1.11. 0.11 m3 176,910.80 19,460.19 24,454,222.60
III PEKERJAAN LANTAI
1 Urugan Pasir Bawah Lantai A.2.3.1.11. 3.81 m3 176,910.80 674,030.15
2 Beton K 125 A.4.1.1.2.2. 3.81 m3 1,062,940.56 4,049,803.53
3 Lantai Kramik 40x40 kw 1 (4 Ruang ) A.4.4.3.7.1. 120.00 m2 156,954.29 18,834,514.80 23,558,348.48
IV PEKERJAAN DINDING
1 Beton Kolom 30/30 (KS)
- Beton K 225 (menggunakan alat) A.4.1.1.7.2. 1.12 m3 1,212,140.56 1,357,597.43
- Pembesian A.4.1.1.17.1a. 168.89 Kg 15,674.53 2,647,271.37
- Bekisting 2x pakai A.4.1.1.22.3. 8.40 m2 276,864.28 2,325,659.95
2 Beton Kolom 30/30 (K1) -
- Beton K 225 (menggunakan alat) A.4.1.1.7.2. 6.30 m3 1,212,140.56 7,636,485.53
- Pembesian A.4.1.1.17.1a. 1,307.98 Kg 15,674.53 20,501,971.75
- Bekisting 2x pakai A.4.1.1.22.3. 42.00 m2 276,864.28 11,628,299.76
3 Beton Kolom 30/30 (K2) -
- Beton K 225 (menggunakan alat) A.4.1.1.7.2. 1.26 m3 1,212,140.56 1,527,297.11
- Pembesian A.4.1.1.17.1a. 168.89 Kg 15,674.53 2,647,271.37
- Bekisting 2x pakai A.4.1.1.22.3. 8.40 m2 276,864.28 2,325,659.95
4 Beton Kolom teras 20/20 (K3) -
- Beton K 225 (menggunakan alat) A.4.1.1.7.2. 0.56 m3 1,212,140.56 678,798.71
- Pembesian A.4.1.1.17.1a. 118.94 Kg 15,674.53 1,864,328.60
- Bekisting 2x pakai A.4.1.1.22.3. 5.60 m2 276,864.28 1,550,439.97
5 Beton Balok Sunduk 8/25 (BS) -
- Beton K 175 (menggunakan alat) A.4.1.1.5.2. 0.17 m3 1,141,284.56 194,018.38
- Pembesian A.4.1.1.17.1a. 27.46 Kg 15,674.53 430,422.59
- Bekisting A.4.1.1.23. 4.93 m2 291,315.14 1,436,183.64 58,751,706.11
V PEKERJAAN KUSEN
1 Kusen Pintu, Jendela Kayu Kruing A.4.6.1.1.4. 0.16 m
3 10,768,040.50 1,722,886.48
3 Daun Jendela Kaca Kayu Kruing A.4.6.1.6.4. 0.84 m
2 416,908.20 350,202.89
4 Jalusi Kayu Kruing A.4.6.1.7.4. 1.29 m
2 758,749.00 978,786.21
5 Cat Kayu Baru A.4.7.1.5. 11.28 m
2 62,822.24 708,634.87
8 Engsel Jendela A.4.6.2.6. 8.00 bh 22,450.04 179,600.32
9 Kait Angin A.4.6.2.9. 4.00 bh 30,375.64 121,502.56
10 Grendel Jendela A.4.6.2.11.2 4.00 bh 25,650.08 102,600.32
11 Kaca Bening A.4.6.2.17.1. 1.48 m
2 104,625.06 154,845.09 4,319,058.73
VI PEKERJAAN PLAFOND
1 Pemasangan List A.4.5.1.9. 132.80 m1 21,178.74 2,812,536.67
2 Pengecatan Plafond + List A.4.7.1.10.1 78.64 m2 17,915.99 1,408,913.45 4,221,450.13