You are on page 1of 4

Nama : Dwinanda Taufiq B

NIM : 5150211235

9.5
a.
A B C D
A 0 30 60 90
B 30 0 30 60
C 60 30 0 30
D 90 60 30 0

Load x distance
A B C D Total
A - 14,400 33,000 5,400 52,800
B 10,500 - 6,000 0 16,500
C 0 0 - 21,750 21,750
D 0 0 0 - 0
Cumulative 91,250
From the table, the cumulative "load x distance" = 91,050 Feet
Based on the flows, one should expect that the Centers A and B will be next to each
other as they have the highest number of moves (830) between each other
Based on the flows, one should expect that the Centers C and D will be next to each
other as they have the highest number of moves (725) between each other

b. The flows between A and the other two work centers B or C will be independent of
whether they are placed between A and D or not as A would be only 30 away from them
in either of the positions. So, the number of flows between B or C and D will decide
which work center will be placed in between A and D
Total number of moves between B and D = Number of moves between B and D +
number of moves between D and B
=0+0=0
Total number of moves between C and D = Number of moves between C and D +
number of moves between D and C
= 725 + 0 = 725
Hence, the work center that should be located between A and D is 'C'
The distance grid will be as follows

A B C D
A 0 30 30 60
B 30 0 60 90
C 30 60 0 30
D 60 90 30 0

Load x distance

A B C D Total
A - 14,400 16,500 3,600 34,500
B 10,500 - 12,000 0 22,500
C 0 0 - 21,750 21,750
D 0 0 0 - 0
Cumulative 78,750
From the table, the cumulative “load x distance” = 78,750

9.15
5 2
A F

3
E

1.5 3 4
B C D
3.5 2 2
H I J

3
G

Workstation 1 A, B, G
Workstation 2 E, C
Workstation 3 F, D
Workstation 4 H
Workstation 5 I

Cycle time = 10 min

Workstation = ∑ti / cycle time


∑ti = 5 + 1.5 + 3 + 4 + 3 + 2 + 3 + 3.5 + 2 + 2 2.9 approx 3

Efficiency = total task time / (actual number of workstation x largest assigned cycle time)
= 0.966667 it is 96% efficient hence theoretical minimum will be reached when workstation are
assigned

9.2
a. Total Cost for Plan A = Total demand weighted distance * Cost per workpiece per feet
= [(600*20) + (1800*12) + (200*8) + (400*6) + (200*10) + (1800*4)]* 0.5
= $ 23400

b. Similarly, for plan B, Total Cost = Total demand weighted distance * Cost per workpiece
per feet
= [(600*20) + (1800*8) + (200*12) + (400*10) + (200*6) + (1800*4)]* 0.5
= $ 20600

c. Total Cost for Plan C = Total demand weighted distance * Cost per workpiece per feet
= [(600*20) + (1800*10) + (200*6) + (400*8) + (200*12) + (1800*4)]* 0.5
= $ 22000

d. Plan B has the lwoest total cost of $ 20600. Hence, Plan B is the best layout from a cost
perspective

9.13
a. Precedence diagram
A

C D E F

B H

b. Cycle time = production time available per day


Unit required per day = 480 minutes
480 minutes / 50 chairs = 9.6 ~ 10 mins / chair

c. Total task time = 4 + 7 + 6 + 5 + 6 + 7 + 8 + 6 = 49 mins


Minimum number of workstations = total task time = 49 mins
Cycle time 10 mins
49 mins / 10 mins = 4.9 ~ 5 workstations

d.

4 mins 6 mins
A C

Sation 1
5 mins 6 mins 7 mins
D E F

Station 4 Station 5 Station 6


7 mins 6 mins
B H

Station 2 Station 7
8 mins
G

Station 3

e. The idle time per cycle is 10 minutes

f. Idle time = (actual number of workstation x largest assigned cycle time) – total task
times
= (7 x 10) – 8
= 70 – 8
= 62 mins

g. Efficiency = task time / (actual numner of workstation) x (largest assigned cycle


time)
= 49 minutes / (7 stations) x (10 minutes)
= 70%

You might also like