Professional Documents
Culture Documents
NIM : 5150211235
9.5
a.
A B C D
A 0 30 60 90
B 30 0 30 60
C 60 30 0 30
D 90 60 30 0
Load x distance
A B C D Total
A - 14,400 33,000 5,400 52,800
B 10,500 - 6,000 0 16,500
C 0 0 - 21,750 21,750
D 0 0 0 - 0
Cumulative 91,250
From the table, the cumulative "load x distance" = 91,050 Feet
Based on the flows, one should expect that the Centers A and B will be next to each
other as they have the highest number of moves (830) between each other
Based on the flows, one should expect that the Centers C and D will be next to each
other as they have the highest number of moves (725) between each other
b. The flows between A and the other two work centers B or C will be independent of
whether they are placed between A and D or not as A would be only 30 away from them
in either of the positions. So, the number of flows between B or C and D will decide
which work center will be placed in between A and D
Total number of moves between B and D = Number of moves between B and D +
number of moves between D and B
=0+0=0
Total number of moves between C and D = Number of moves between C and D +
number of moves between D and C
= 725 + 0 = 725
Hence, the work center that should be located between A and D is 'C'
The distance grid will be as follows
A B C D
A 0 30 30 60
B 30 0 60 90
C 30 60 0 30
D 60 90 30 0
Load x distance
A B C D Total
A - 14,400 16,500 3,600 34,500
B 10,500 - 12,000 0 22,500
C 0 0 - 21,750 21,750
D 0 0 0 - 0
Cumulative 78,750
From the table, the cumulative “load x distance” = 78,750
9.15
5 2
A F
3
E
1.5 3 4
B C D
3.5 2 2
H I J
3
G
Workstation 1 A, B, G
Workstation 2 E, C
Workstation 3 F, D
Workstation 4 H
Workstation 5 I
Efficiency = total task time / (actual number of workstation x largest assigned cycle time)
= 0.966667 it is 96% efficient hence theoretical minimum will be reached when workstation are
assigned
9.2
a. Total Cost for Plan A = Total demand weighted distance * Cost per workpiece per feet
= [(600*20) + (1800*12) + (200*8) + (400*6) + (200*10) + (1800*4)]* 0.5
= $ 23400
b. Similarly, for plan B, Total Cost = Total demand weighted distance * Cost per workpiece
per feet
= [(600*20) + (1800*8) + (200*12) + (400*10) + (200*6) + (1800*4)]* 0.5
= $ 20600
c. Total Cost for Plan C = Total demand weighted distance * Cost per workpiece per feet
= [(600*20) + (1800*10) + (200*6) + (400*8) + (200*12) + (1800*4)]* 0.5
= $ 22000
d. Plan B has the lwoest total cost of $ 20600. Hence, Plan B is the best layout from a cost
perspective
9.13
a. Precedence diagram
A
C D E F
B H
d.
4 mins 6 mins
A C
Sation 1
5 mins 6 mins 7 mins
D E F
Station 2 Station 7
8 mins
G
Station 3
f. Idle time = (actual number of workstation x largest assigned cycle time) – total task
times
= (7 x 10) – 8
= 70 – 8
= 62 mins