Professional Documents
Culture Documents
GENERAL SPECIFICATION
Welding - Materials
GS RC WAM 001
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Contents
Foreword ........................................................................................................................ 4
1. Subject ..................................................................................................................... 4
1.1 Introduction ..................................................................................................................... 4
1.2 Purpose .......................................................................................................................... 4
3. Applicability ............................................................................................................. 7
4. Definitions of terms................................................................................................. 7
7. Welding processes................................................................................................ 13
7.1 Acceptable welding processes ...................................................................................... 13
7.2 Welding Process restriction ........................................................................................... 13
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 2/56
General Specification Date : 12/2012
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 3/56
General Specification Date : 12/2012
Foreword
Engineering Companies and Design Offices that are contractually bound to TOTAL are obliged
to always check that the applicable regulations, in particular regarding SAFETY, QUALITY and
protection of the ENVIRONMENT, do not impose more restrictive measures. If they do,
alternative solutions in accordance with the regulations must be submitted in writing to TOTAL.
Except for when it is used internally, the application of this specification is systematically
covered by a contract.
Caution, for new equipment, this specification supersedes the following specifications:
• GS RM WAM 006 Rev 02 dated 01/2012
• GS RM WAM 001 Rev 00 dated 07/2003
• GS TP WAM 001 Rev 00 dated 12/2008
1. Subject
1.1 Introduction
This Specification defines the welding, thermal treatment, for shop and field fabrication of
Pressure Vessels, Shell and Tube Heat Exchangers, and Air Cooled Exchangers.
For licensed units, this specification will have to be applied together with applicable licensor
specifications. The more stringent requirements shall govern.
This specification is not applicable for aluminium and copper base materials
1.2 Purpose
This Specification supplements the Codes listed in § 2, the project equipment specifications and
the project equipment data sheets/drawings.
For examination and testing requirements, additional requirements are defined in TOTAL
specification GS RC WAM 002.
For pressure equipments in Wet H 2 S Services, additional requirements are defined in TOTAL
specification GS RC WAM 011.
For Duplex Stainless steel additional requirements are defined in TOTAL specification
GS RC WAM 010.
For Cr-Mo steel additional requirements are defined in TOTAL specifications GS RC PVE 004
and GS RC PVE 005.
For Titanium and its alloys, additional requirements are defined in Appendix 7.
2. Reference documents
The reference documents listed below form an integral part of this General Specification. Unless
otherwise stipulated, the applicable version of these documents, including relevant appendices
and supplements, is the latest revision published at the EFFECTIVE DATE of the CONTRACT.
Standards
Reference Title
ISO 4063 Welding and allied processes – Nomenclature of welding processes and
reference number
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 4/56
General Specification Date : 12/2012
Reference Title
ISO 5817 Welding - Fusion welded joints in steel, Nickel, Titanium and their alloys
(beam welding excluded) - Quality levels for imperfections
ISO 6520-1 Welding and allied processes – Classification of geometric imperfections
in metallic materials – Fusion welding
ISO 9692-1 Welding and allied processes - Recommendations for joint preparation -
Part 1: Manual metal arc welding, gas shielded metal arc welding, gas
welding, TIG welding and beam welding of steels
ISO 9692-2 Welding and allied processes - Recommendations for joint preparation -
Part 1: submerged arc welding of steels
ISO 10474 Steel and steel products - Inspection documents
ISO 14344 Welding and allied processes - Flux and gas shielded electrical welding
processes - Procurement guidelines for consumables
ISO 15614 8 Specification and qualification of welding procedures for metallic materials
Professional documents
Reference Title
American Society for Testing and Materials
ASTM A263 Standard specification for stainless chromium steel-clad plate
ASTM A370 Standard test methods and definitions for mechanical testing of steel products
ASTM A380 Practice for cleaning and descaling stainless steel parts, equipment and
systems
American Petroleum Institute
API RP 577 Welding inspection and metallurgy
API RP 582 Welding guidelines for the chemical oil gas industries
API RP 660 Shell-and-tube heat exchangers
American Welding Society
AWS A3.0 Standard welding terms and definitions
AWS A4.2M Standard procedure for calibrating magnetic instruments to measure the
delta ferrite content of austenitic and duplex austenitic-ferritic stainless
steel weld metal
AWS A4.3 Standard methods for determination of the diffusible hydrogen content of
martensitic, bainitic, and ferritic steel weld metal produced by arc welding
AWS A5.1/A5.1M Specification for carbon steel electrodes for shielded metal arc welding
AWS A5.4/A5.4M Specification for stainless steel electrodes for shielded metal arc welding
AWS A5.18/A5-18M Specification for carbon steel electrodes and rods for gas shielded arc welding
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 5/56
General Specification Date : 12/2012
Reference Title
AWS A5.20/A5-20M Specification for carbon steel electrodes for flux cored arc welding
AWS D18 2 Guide to weld discoloration levels on inside of austenitic stainless steel tube
Regulations
Reference Title
European Directive of the European Parliament and of the Council on the
Directive approximation of the laws of the Member States concerning pressure
97/23/EC dated equipment (PED)
29 may 1997
Codes
Reference Title
American Society of Mechanical Engineers boiler and pressure vessel code
ASME B46.1 Surface texture (surface roughness, waviness, and lay)
ASME Section II, Welding Rods, Electrodes, and Filler Metals
Part C
ASME Section V Non-destructive Examination
ASME Section VIII, Pressure Vessels
Division 1
ASME Section VIII, Pressure Vessels - Alternative Rules
Division 2
ASME Section IX Welding and Brazing Qualifications
SNCT
CODAP Code de construction Des Appareils à Pression non soumis à la flamme
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 6/56
General Specification Date : 12/2012
Reference Title
GS RC WAM 011 Additional Requirements for pressure equipments in Wet H 2 S Services
Other documents
Reference Title
Not applicable
2.2 Deviations
Any deviation from the requirements of this specification may be suggested by the General
contractor, Engineering company, Manufacturer or Contractor, if he considers such deviation
beneficial for reducing the cost and/or completion time, provided that it does not compromise
the safety of personnel or the regulatory requirements (when such regulations apply).
Deviations must be submitted to TOTAL, as a variant with the necessary justifications, and must
receive the written approval of TOTAL.
3. Applicability
This specification applies to all new equipment covered by the § 2, in refineries and
petrochemicals plants operated by TOTAL.
Full or partial application of this specification for equipment to be repaired or for components of
existing equipment shall by confirmed by TOTAL.
For category D as per RG RC PVE 001, this specification is not applicable to all new equipment
covered by the § 2.
4. Definitions of terms
For the purposes of this Specification, the following definitions shall apply:
• Company / Entity: TOTAL
• Contractor: The party which carries out all or part of the design, engineering, procurement,
construction and commissioning for the project.
• Manufacturer / Vendor / Supplier: The party(s), which manufactures and/or supplies
equipment and services to perform the duties specified by the CONTRACTOR.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 7/56
General Specification Date : 12/2012
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 8/56
General Specification Date : 12/2012
5.3.1 General
All welding procedures shall be qualified in accordance with the requirements of construction
code supplemented as follows:
• all welding procedure qualification tests shall be witnessed and certified by an
Independent Inspecting Authority approved by CONTRACTOR, unless the Vendor is
holding a valid construction code stamp and if this is not required by the CE stamp. In that
case VENDOR shall be authorised to qualify by himself the Welding Procedure
Qualification and responsible to grant necessary PQR's qualification from construction
code Authorised Inspector,
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 9/56
General Specification Date : 12/2012
• European Directive 97/23/EC (PED) Appendix 1 § 3.1.2, if applicable, for the approval by
a competent third party for pressure equipments category II, III and IV,
• Except for carbon steel pressure vessel in normal service conditions (excluded CS in
corrosive service like H 2 S or with MDMT/TME<-10°c or other special design conditions),
PQRs can only be used in the same workshop where they had been done, or in
workshops of same country,
• for any pressure vessels requiring PWHT for Code or Service reasons, welding procedure
qualifications shall be subject to hardness testing,
• the nominal fabrication PWHT temperature shall be the qualified PWHT temperature ±
10°C for Cr Mo steels and ± 20°C for others,
• in the event where existing PQR does not include hardness testing results, hardness test
may be performed on additional weld test coupons (as per § 5.3.2) before fabrication and
using the same parameters of the WPS (grade, thickness, parameters ...),
• shop welding procedure qualification for site application may be acceptable provided site
machine and associated equipment are identical to those used for qualification.
All welding procedure qualification shall include a welding parameters monitoring sheet. The
monitoring sheet shall monitor all welding parameters during the qualification stage by run and by
process. This includes at least electrical parameters, speed, ROL (Run of length) for SMAW
process and interpass temperature. For manual welding several monitoring shall be done per run.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 10/56
General Specification Date : 12/2012
A minimum of 2 traverse line measurements shall be performed for thickness less than 20 mm
and 3 for thickness above (one at the intersection).
In the HAZ, the first indentation shall be located as close as possible of the fusion line.
Unless otherwise specified the maximum Hv10 hardness shall not exceed following values
[minimum individual value], on base metal, HAZ and weld metal.
Material group according to ASME IX Material Type Without PWHT PWHT
P1 Carbon steel 300 235 (Notes 1 & 2)
P3 C-½Mo 320 235 (note 1)
P4 1Cr-½Mo, 1¼ r- Not applicable 235 (Note 2)
1
/ 2 Mo
P5A 2¼Cr-1Mo Not applicable 235 (Note 3)
P5B 5Cr-½Mo Not applicable 248
Note 1: A maximum of 248 HV10 shall apply in the HAZ
Note 2: For equipment in sour wet H 2S services as defined in NACE-8X194, a maximum of 210 HV10 shall apply in base metal and
weld deposit and maximum of 248 HV10 shall apply in the HAZ. Specifications GS RC WAM 011 shall govern
Note 3: TOTAL specification GS RC PVE 005 shall govern when applicable
Note 4: TOTAL specification GS RC PVE 004 shall govern when applicable
In addition, surface hardness test (Brinell, Vickers or Rockwell) shall also be included on PQR
as per method and acceptance criterias specified in Appendix 1 of GS RC WAM 002 for Post
Weld Heat Treated vessels.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 11/56
General Specification Date : 12/2012
If hardness test are required by code, service or specifications, tests shall also be include in fillet
weld PQRs, according to § 5.3.2.
5.3.4 Ferrite
6. Welders qualification
Welders and welding operators shall be qualified in accordance with construction code
supplemented by:
• European Directive 97/23/EC (PED) Appendix 1 § 3.1.2, if applicable, for the approval by
a competent third party for pressure equipments category II, III and IV.
For tube to tube-sheet strength welding, the qualification tests shall be in accordance with
Appendix 1.
Existing qualifications remains in effect if in accordance with construction code requirements.
A recognised Inspection Authority shall qualify welders and welding operators, unless the Vendor
is holding a valid construction code stamp and if this is not required by the EC stamp. In that case
any welder satisfying construction code qualification requirements shall be acceptable to
CONTRACTOR. Welder's certificates shall be made available to the review of the
CONTRACTOR’s Inspector.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 12/56
General Specification Date : 12/2012
7. Welding processes
7.1 Acceptable welding processes
For all welds (pressure parts, and non-pressure retaining part e.g. attachment, skirt,
manufacturer’s name plate, saddle…), following welding processes are acceptable with all the
requirements described in § 7.2:
Welding processes AWS Designation ISO 4063
Shielded Metal Arc Welding SMAW 111
Gas Tungsten Arc Welding GTAW 141
Plasma Arc Welding PAW 15
Automatic Submerged Arc Welding SAW 121
136
Flux Cored Arc Welding FCAW
138
Gas Metal Arc Welding GMAW 135
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 13/56
General Specification Date : 12/2012
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 14/56
General Specification Date : 12/2012
− non-pressure retaining part including those welded on pressure part but excluding all
parts of the lifting devices:
o for all thicknesses, provided 100% PT or MT (butt and fillet welds) are performed,
o for thickness above 15 mm, provided 10% UT or RT (butt welds only) are performed,
o all fillet welds shall be qualified by a butt weld PQR and a representative fillet PQR.
Other application of FCAW process (automatic welding, root pass, internal welds, other P
number …) shall be subjected to COMPANY prior approval and shall require, test coupons,
screening tests and additional NDT.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 15/56
General Specification Date : 12/2012
8. Welding consumables
8.1 General
Filler metal shall be as specified in construction code or equivalent AWS/ISO/EN Specification.
Certified Material Test Report's (CMTR) shall be supported by "Type 3.1" document according
to ISO 10474 for chemical analysis.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 16/56
General Specification Date : 12/2012
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 17/56
General Specification Date : 12/2012
ER 80SG
0.5 Mo SFA 5.5 E 70XXA1 (H4R) SFA 5.28
(0.5 Mo)
0.5 Cr - 0.5 Mo E 8018 B1 (H4R) ER 80C B2 (L) *
SFA 5.5 SFA 5.28
1 Cr - 0.5 Mo E 8016 B2 (H4R) ER 80S-G *
E 8018 B2 (H4R) ER 80C B2 (L) *
1 ¼ Cr - 0.5 Mo SFA 5.5 SFA 5.28
E 8016 B2 (H4R) ER 80S-G *
E 9018 B3 (H4R) ER 90C B3 (L) *
2 ¼ Cr - 1 Mo SFA 5.5 SFA 5.28
E 9015 B3 (H4R) ER 90S-G *
2 ¼ Cr - 1 MoV SFA 5.5 E 9015-G (H4R) SFA 5.28 ER90S-G
5 Cr - 0.5 Mo SFA 5.5 E 8015/16 B6 SFA 5.28 ER 502 *
E 7018 C1L
2 ¼ Ni SFA 5.5 SFA 5.28 ER 80C Ni2
E 7015 C1L
ER 80C Ni3
E 8018 C2 SFA 5.28
3 ½ Ni SFA 5.5 ER80S-Ni3
E 8015 C2 SFA 5.23
ENi3
(*) For the welding of 0.5% to 5% of chromium steels, the wire-flux combination for submerged arc welding (SAW) shall conform
to ASME SFA 5.23, or equivalent ISO/EN Specification.
TABLE 1 - Guideline
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 18/56
General Specification Date : 12/2012
When TOTAL specifications GS RC PVE 004 and GS RC PVE 005 are applicable, welding
consumable shall meet also the requirements from these specifications.
8.3.3 General provisions for the use of filler metals to weld austenitic stainless steels
The criteria used to select filler metals are defined in table 2.
ASME Coated ASME
Base metal Welding wires
Specification Electrodes (2) specification
304 L SFA 5.4 E 308 L 15/16 (1) SFA 5.9 ER 308 L (1)
316 L SFA 5.4 E 316 L 15/16 (1) SFA 5.9 ER 316 L (1)
304 SFA 5.4 E 308 15/16 * SFA 5.9 ER 308 *
E 308 L 15/16 (1) ER 308 L (1)
316 SFA 5.4 E 316 15/16 * SFA 5.9 ER 316 *
E 316 L 15/16 (1) ER 316 L (1)
321 SFA 5.4 E 347 15/16 SFA 5.9 * ER 347
347 SFA 5.4 E 347 15/16 SFA 5.9 ER 347
309 SFA 5.4 E 309 15/16 SFA 5.9 ER 309
304 LN SFA 5.4 E 308 L (1) SFA 5.9 ER 308L (1)
316 LN SFA 5.4 E 316 L (1) SFA 5.9 ER 316 L (1)
(1) Filler metal recommended for cryogenic applications. Weld metals containing Nb shall not be used.
Impact tests shall be carried out per lot at design temperature or at a lower temperature. The test
results shall include the lateral expansion and absorbed energy values.
(2) EXXL-17 electrodes may be used by Vendor if previously agreed by Company
(*) For applies to high temperatures beyond 540°C (in order to avoid long term embrittlement), type 308
welding consumables shall be approval by CONTRACTOR and shall meet additional requirements
TABLE 2
For service temperature above 315°C filler metals shall be selected to produce weld deposits
that fall within the ferrite number (FN) range of 3 to 10 as determined by the WRC (Welding
Research Council) diagram which is included in AWS A5.4.
Welding wires or bare wires that are not listed in the AWS/ISO/EN specifications shall not be used.
All GTAW filler wires shall be degreased prior to use and shall subsequently be handled with clean
gloves. The degreasant shall leave no chloride or sulphide containing residues on the surface.
8.3.4 General provisions for the use of filler metals to weld ferritic stainless steel
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 19/56
General Specification Date : 12/2012
8.3.5 General provisions for the use of filler metals to weld non ferrous metals -
Selection criteria for filler metals – Ni-base alloys
TABLE 3
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 20/56
General Specification Date : 12/2012
Otherwise "Buttering" layer of highest alloy steel with a lower alloy steel filler metal followed by
PWHT may be considered. Subsequent welding of the buttered layer to lower alloy steel
material is then carried out with weld metal matching the lower alloy steel filler metal.
1 Carbon steel A A A A A A A A B B B B B B B B B B B C D C
2 Carbon-Molybdenum Steel A E C E E E E E B B B B B B B B B B B C D C
3 2.25% Nickel & 3.5% Nickel steel A E C B B B B B B B B C C C
4 9% Nickel Steel A E C C C C C C C C C C C C
5 1% Cr - 0.5% Mo steel A E F F F F B B B B B B B B C D C
6 1.25% Cr - 0.5% Mo steel A E F F F F B B B B B B B B C D C
7 2.25% Cr - 1% Mo Steel A E F F F G B B B B B B B B C C C
8 5% Cr - ½% Mo Steel A E F F H H B B B B B B B B C C C
9 9% Cr - 1% Mo Steel A E F F G H J J B B B B B B B B C C C
10 Type 405 Stainless steel B B K X B B B B B B B C C C
11 Type 410S Stainless steel B B J K K B B B B B B B B C C C
12 Type 410 Stainless steel B B J K X B B B B B B B B C C C
13 Type 304 Stainless steel B B B C B B B B B B B B L L P L L O O C C C
14 Type 304L Stainless steel B B B C B B B B B B B B L M M L M O O C C C
15 Type 321 Stainless steel B B B C B B B B B B B B L M N L M O O C C C
16 Type 347 Stainless steel B B B C B B B B B B B B P M N P M P P C C C
17 Type 316 Stainless steel B B B C B B B B B B B B L L L P Q O O C C C
18 Type 316L Stainless steel B B B C B B B B B B B B L M M M Q O O C C C
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 21/56
General Specification Date : 12/2012
NOMENCLATURES:
A - AWS A5.1 classification EXX15, EXX16, EXX18. J - AWS A5.4, classification E505-XX.
B - AWS A5.4 and A5.11, classification E309-xx (only K - AWS A5.4 and A5.11, classification E410-XX,
for service temperature up to 315°C), ENiCrFe-3 E410 Cb-XX, E309-XX, ENiCrFe-3 (Inconel
(Inconel 182), or ENiCrFe-2, E NiCrMo3 182), or ENiCrFe-2 (Inco-Weld A).
C - AWS A5.11 classification ENiCrFe-3 (Inconel 182) L - AWS A5.4, classification E308-XX.
or ENiCrFe-2 (Inco-Weld A), E NiCrMo3
D - AWS A5.11, classification ENiCrFe-3 (Inconel 182), M - AWS A5.4, classification E308L-XX.
ENiCrFe-2 (Inco-Weld A), or ENiCr-7 (Monel 190).
E - AWS A5.5, classification E7015-A1, E7016-A1, or N - AWS A5.4, classification E347-XX.
E7018-A1.
F - AWS A5.5, classification E8016-B2, or E8015-B2L, O - AWS A5.4, classification E309-XX or E308-XX.
E8018-B2L
G - AWS A5.5, classification E9015-B3, E9016-B3, P - AWS A5.4, classification E308-XX or E347-XX.
E9018-B3 or E9015-B3L, E9018-B3L
H - AWS A5.5, classification E8018B6 or E8018B6L Q - AWS A5.4, classification E316-XX or E316L-XX.
I - AWS A5.4, classification E7Cr-XX. R - AWS A5.4, classification E309-XX
NOTES:
1. Blank spaces in Table 1 indicate combination that are considered unlikely or unsuitable
2. Table 1 refers to coated electrodes. For bare wire welding (SAW, GMAW, GTAW), use equivalent electrode classifications
(AWS A5.9, A5.14, A5.17, A5.18, A5.20, A5.23, and A5.28).
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 22/56
General Specification Date : 12/2012
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 23/56
General Specification Date : 12/2012
Double welded groove joints shall have their root passes back gouged to sound metal on the
reverse side before welding on that side. In case where double welding is impractical, the root
pass shall be made by the Gas Tungsten Arc Welding (GTAW) process.
When air arc gouging is used, the carburized and hardened surfaces shall be removed by
grinding to a bright metal finish and shall be examined by PT or MT.
Permanent backing rings and consumable inserts shall not be used. Temporary fabrication
attachment welds on pressure shells shall be removed. The surface under such welds and
under backing rings that have been removed shall be properly conditioned to eliminate surface
stress risers. Such surfaces shall be inspected by the magnetic particle or liquid penetrant
method in accordance with GS RC WAM 002.
Temporary attachments, backing rings or bars intended to be removed after weld completion
shall essentially match the analysis of the base metal.
Weld joint preparation shall be made by machining, grinding, or thermal cutting. When thermal
cutting is performed, the edges shall be mechanically cleaned to sound metal prior to welding.
If nibbling machine is used, the edges shall be mechanically cleaned by machining or grinding
prior to welding.
For P no.6 and higher base materials only plasma or mechanical cutting shall be allowed.
Materials that require preheat for welding (see § 11) shall be preheated in the same manner for
thermal cutting or gouging.
Surfaces for welding shall be clean and free from paint, oil, dirt, scale, oxides, and other foreign
material detrimental to the integrity of the weld.
Grinding wheels and wire brushes used on austenitic or other higher nickel shall not have been
previously used on carbon or low alloy steels, copper alloys, aluminium or zinc coatings (paint
or galvanizing).
Only austenitic stainless steel wire brushes shall be used on austenitic or other higher nickel alloys.
Grinding wheels and wire brushes shall be used only for a single type of material.
Grinding discs containing sulphur (iron sulphate) or other harmful components shall not be used
on stainless steels, 9% nickel steel or non ferrous materials.
For nozzle connections, when forged piece with lip is required, the butt weld nozzle attachment
shall be ground smooth and flush on the double side.
Also, for junction between skirt en Y forged piece, the root pass shall be ground smooth and
flush on the internal face with 100% PT (instead of MT which is often impossible).
As a general rules bevel preparation should be in accordance with ISO 9692-1 and ISO 9692-2.
10. Fabrication
10.1 General
Compliance with this Specification and authorization of WPS, PQR and weld map shall in no
way relieve the VENDOR of the responsibility of providing welds suitable to the services for
which they are intended.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 24/56
General Specification Date : 12/2012
All tack welds shall be made in accordance with a previously approved welding procedure and
shall be performed by qualified welders. Tack welds shall be of sufficient cross-section and
length in order to avoid cracks, especially on high strength steel materials.
Temporary welds for temporary handling attachments, lugs, etc. shall be minimized.
When temporary welding is deemed necessary, welding shall be performed with the same care,
materials, electrodes, minimum preheat and procedures as for the main fabrication welding.
The temporary welds shall subsequently be removed and ground flush with the base material,
and then inspected by non-destructive methods (magnetic particle or dye penetrant).
Any defect found during this inspection shall be removed and repaired by a qualified welder
using welding procedures approved by the CONTRACTOR. The method of removing
attachments shall not injure the metal surface (i.e. they shall not be removed by hammering off).
Attachments such as lugs, clips, support rings and similar items shall not be located on a weld
seam.
Removable starting and stopping tabs shall be used for longitudinal welding where automatic
welding processes are used.
Weld techniques shall be selected to assure that specified tolerances for straightness and out-
of-roundness are not exceeded. If such tolerances are not stated in the drawings, standards or
specifications, the applicable section of the relevant code shall govern.
Cleaning of the surfaces to be welded shall be done in a manner that will not lead to
contamination of the weld or base metal. Only stainless steel brushes and tools dedicated to
stainless steel shall be used on stainless steels and nickel-alloyed materials.
Peening is only permitted to the extent necessary to clean slag from the weld.
Preparation for welding, types and sizes of electrodes, current amperages and voltages used,
preheating requirements, etc. shall be the same for production welding as those defined in the
applicable qualified welding procedures.
Adequate precautions shall be taken and suitable equipment shall be available on site or shop
open areas in order to protect the welds (and welders) from adverse weather conditions (rain,
wind...) at the time of welding. If weather conditions become too severe, welding operations
shall be stopped. No welding shall be done on wet base materials.
Chemical cleaning, passivating procedures, if applicable, shall be subject to CONTRACTOR’s
approval.
When weld overlay and/or clad restoration is required, Appendix 2 becomes applicable.
Welding is prohibited after final PWHT.
When internal visual examination of welds is impossible (Pressure vessels whitout manhole 24
“diameter, part of pressure vessel without final access), the closure seam shall be done after all
others welds have been done and inspected in the internal side of the pressure vessel. This
requirement shall be considered as an HOLD point of the inspection and test plan
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 25/56
General Specification Date : 12/2012
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 26/56
General Specification Date : 12/2012
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 27/56
General Specification Date : 12/2012
Interpass temperatures shall not be greater than the highest interpass temperature recorded
during the welding procedure qualification test.
The preheat temperature shall be measured on the face opposite to that being heated when
possible. When this is not possible, allowance shall be made for temperature equalization, e.g.
remove heat source and allow period of one minute for each 25 mm thickness of material to
elapse, before measuring temperature.
Measurement of preheat and interpass temperatures shall be done by temperature indicating
crayons, contact pyrometer or other approved method of temperature measurement. Temperature
indicating crayons shall not be applied to surfaces where weld metal is to be deposited.
• The minimum width of the heated zone shall be 2t (t = wall thickness) or 100 mm
whichever is greater.
• Special attention shall be paid to the extent of heated bands in order not to aggravate the
problems related to residual stress distribution, such as cracking, buckling and distortion.
• For preheat temperatures above 150°C (regardless of thickness) or material with wall
thickness greater than 25 mm with preheat temperature at or above 80°C. If flame is used,
heated area or burners shall be in motion.
Maximum interpass temperature limits shall be specified on the WPS. The maximum interpass
temperature for austenitic stainless steel shall be 150°C.
PREHEAT
MATERIAL (3)
Wall Thickness (mm) Minimum Temperature (°C)
< 30 20 (1)
Carbon and Carbon Manganese Steels 30 to 50 20 (2) (1)
> 50 100
< 50 100
HLE
> 50 125
0.3-0.5 Mo Steel All 100
1 Cr -0.5 Mo,
All 150
1.25 Cr -0.5 Mo
2.25 Cr - 1 Mo All 200
5 Cr - 0.5 Mo, All 250
2.5 Ni All 120
3.5 Ni All 150
12 - 17 Cr Martensitic Steels All 200
(1) If ambient temperature is below 5°C, preheat to 40°C is mandatory.
(2) 80°C minimum if specified UTS is equal or greater than 490 MPa (minimum tensile strength value specified in the no /
specification of the base metal) and weld heat input less than 20kJ.
(3) In case of dissimilar welds, preheat temperature shall the highest of the two.
TABLE 5 - PREHEAT
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 28/56
General Specification Date : 12/2012
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 29/56
General Specification Date : 12/2012
Appendix 1
1 Scope
Whatever the Construction Code, This chapter is applicable when strength welded tube/tube
sheet connections have been specified and is intended to supplement to construction code.
2 General
No production welding shall be carried out until the proposed welding procedures have been reviewed
and accepted by the CONTRACTOR in accordance with the requirements of this Chapter.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 30/56
General Specification Date : 12/2012
Appendix 1
4.5 Hardness
Hardness test results shall not exceed limits given in § 5.3.2 of this specification.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 31/56
General Specification Date : 12/2012
Appendix 1
5 Welding process
• GTAW Welding shall be carried out preferably with automatic orbital machine.
• Welding shall include two weld passes minimum for strength welds, with minimum one
pass with filler metal.
• The use of other processes require the prior acceptance of the CONTRACTOR.
8 Leak detection
When specified by CONTRACTOR, the final hydrostatic test shall be preceded by a low
pressure air test and/or by a gas leak test.
• Air testing:
The tube to tube sheet welded joints shall be tested for leak detection by applying 2
pressure tests of 0.05 bar and after 0.5 bar. While the shell is under pressure, a soap
detergent shall be used to indicate any leakage.
• Leak investigation:
All leaking weld locations shall be marked for repair.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 32/56
General Specification Date : 12/2012
Appendix 1
9 Repairs
Faulty welds shall be completely removed to sound metal and repaired using the repair
procedure.
Minor faults associated with fully automatic GTAW welding incorrect settings or tracking, may be
rectified by rewelding at corrected settings or locally repaired by manual GTAW process. When
any defects occur, particularly cracking, the cause shall be established prior to repair.
11 Hydraulic testing
The hydraulic test shall be carried out after all welding, pneumatic tests, tube expansion and
heat treatment has been completed.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 33/56
General Specification Date : 12/2012
Appendix 2
1. Scope
This Attachment defines the method, procedure, and acceptance criteria for fabrication of weld
overlay and clad restoration.
In this specification the term “Alloy Lining” is a general term that does not imply a specific
fabrication or manufacturing process.
Strip lining is not allowed unless specified on the project specifications.
Alloy lining for shells and heads shall be integrally bonded cladding or weld deposit overlay.
3. Welding processes
The following processes or combinations thereof are acceptable for application of overlay or
clad restoration.
4. Filler metals
Filler metal composition shall match the alloy cladding or specified weld overlay material as
specified on the CONTRACTOR’s equipment drawings or data sheets, except for first layer and
ferritic stainless steel as detailed on the following table.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 34/56
General Specification Date : 12/2012
Appendix 2
5. Surface preparation
Assembly joints shall be tested before clad restoring or weld overlay performance
Surfaces to be welded shall be free from surface irregularities and foreign matter such as scale,
spatter, grease, etc.
The base metal for clad restored seams shall be completely welded before the clad restoration
is applied. The base metal surface at the cladding interface shall be ground flush before
cladding restoration.
Weld preparation for clad restoration shall be in accordance with Appendix 7.
Stainless steel clad removal shall be verified by testing with a saturated copper sulphate
solution in accordance with ASTM A380, or equivalent ISO/EN Specification.
7. Testing
Assembly joints shall be tested before clad restoring or weld overlay performance.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 35/56
General Specification Date : 12/2012
Appendix 2
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 36/56
General Specification Date : 12/2012
Appendix 2
• All weld overlay and clad restored weld surfaces, as well as attachments to those
surfaces, shall be 100 percent examined by liquid penetrant. Examination shall be
performed after PWHT for final acceptance purpose when PWHT is performed.
• Surfaces examined shall be free of cracks, lack of fusion, porosity and other defects,
which would reduce the effectiveness of the overlay.
All cracks, lack of fusion, surface slag/scale overlaps, undercuts, arc strikes and surface
porosity are unacceptable.
8.3.2. WO surface
When integrally WO surface vessels are used, a minimum of 10% of the WO surface shall be
ultrasonic examined in accordance with Appendix 5 of this specification.
9. Welding repairs
Unacceptable defects shall be removed by mechanical means and/or dressed down and
rewelded, if necessary.
Areas excavated for repair shall be examined by (PT) to ensure complete removal prior to
welding. VENDOR shall be notified of any defect extending into the base material, prior to
repair.
Weld overlay, clad or liner restoration welds requiring welding repairs shall be welded with the
original welding procedure or an authorized welding repair procedure and shall be examined by
RT when applicable, and by PT after repair with the method and criteria defined respectively in
§ 8.2 to 8.4 of Appendix 2.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 37/56
General Specification Date : 12/2012
Appendix 3
1 Scope
This chapter is applicable when strength expanded tube/tube sheet connections have been
specified in Data sheet of guide drawings.
2 General
Mock up testing shall be used for procedure and operators performance qualification.
Expansion procedure shall include expansion method, expanding tools definition and torque
definition within maximum and minimum deviation of 5%.
No production expansion joint shall be carried out until the proposed expansion procedures
have been reviewed and accepted by the CONTRACTOR in accordance with the requirements
of this Chapter.
with:
− X: tube wall thickness reduction
− H: tube hole diameter
− D o : tube outside diameter
− D i : tube inside diameter after expansion
− d i : tube inside diameter the tube wall thickness reduction shall be in accordance with
Table 4 § 9.10.1 of API RP 660.
• expansion length,
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 38/56
General Specification Date : 12/2012
Appendix 3
4 Qualification test
The expanding procedure and operators shall be qualified as per requirements of below and
approved by a competent third party as per European Directive 97/23/EC (PED) § 3.1.2 for
pressure equipment in PED category II, III and IV.
Other qualification method according to CODAP may be used with CONTRACTOR/ COMPANY
prior approval
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 39/56
General Specification Date : 12/2012
Appendix 3
6 Test report
Test Report shall include as a minimum:
• pull out test results on production test piece,
• expansion ratio on a mock up and on random basis on production (1% mini, no less than
5 tubes),
• expanded length.
This test report shall be included in the manufacturing dossier.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 40/56
General Specification Date : 12/2012
Appendix 4
1. Scope
This specification covers general requirements for the material, fabrication, welding and
inspection of pressure vessel and heat exchangers in 5Cr-½Mo steel (ASTM P5B) with or
without weld overlay cladding with austenitic stainless steel.
2. Base material
2.1. General
All base material shall be supported by 3.1 inspection certificate according to EN 10204.
2.2. Plates
2.2.1. Base material plates
The plates to be used for fabrication of equipment the reactor shall comply with all requirements
of grade SA 387 Grade 5 or equivalent ISO/EN Specification with supplementary requirements
S1, S2, S3, S5, S8, S12 and the following additional requirements.
2.2.3. Testing
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 41/56
General Specification Date : 12/2012
Appendix 4
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 42/56
General Specification Date : 12/2012
Appendix 4
Ultrasonic examination procedure from plate supplier shall be submitted to CONTRACTOR for
approval.
2.2.5. Dimensional/visual
Any under thickness beyond to code acceptance limit shall be cause of rejection of the plates.
Unless otherwise agreed by the CONTRACTOR, repair by welding shall not be permitted.
2.3. Forging
2.3.1. Base material
Forgings including those used for shell, heads, flanges and nozzles, shall conform to all
requirements of SA 336 Grade F5, or equivalent ISO/EN Specification.
2.3.3. Testing
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 43/56
General Specification Date : 12/2012
Appendix 4
For thicknesses below 75 mm, one set of three Charpy V-notch impact tests shall be taken
from each forging at each tensile test location. The test specimens shall be oriented transverse
to the direction of greatest forging elongation. Impact test specimens shall be taken from the
1/4T thickness location.”
Impact tests shall be conducted in accordance with code requirements, except that there shall
be no exemptions from impact testing, and the test temperature shall be the Minimum Design
Metal Temperature with the following requirements:
• 55 Joules for minimum average value,
• 48 Joules for minimum individual value.
Lateral expansion and percent shear fracture for each specimen shall be reported.
2.3.3.5. Macro hardness testing
Hardness survey shall be performed on macro cross section according to the Vickers hardness
test method defined in the European norm EN 1043-1, under 10 kg load.
Each specimen shall include hardness survey across the wall thickness of the plate and shall
not exceed 250 HV10 with a target at 235 HV10 max.
2.3.4. Non destructive examination
All forgings, except those produced in standard dies, shall be machined after heat treatment and
prior to final magnetic particle and ultrasonic examination. The surface finish shall be Ra 6.3µm
/ 250µinch AA (See ASME B46.1) or smoother:
• all forgings shall be 100% ultrasonically tested in accordance with ASTM A 388 using both
straight and angle beam. Acceptance criteria shall be as specified in ASME Section VIII
Division 2 § AM 203.2 or equivalent ISO/EN Specification,
• all forgings shall be examined either by magnetic particle or dye penetrant examination.
Ultrasonic examination procedure from the forging supplier shall be submitted to
CONTRACTOR for approval.
Unless otherwise advised by the CONTRACTOR repair by welding are prohibited.
2.3.5. Dimensional/visual
Any under thickness beyond to code acceptance limit shall be cause of rejection of the plates.
Unless otherwise agreed by the CONTRACTOR, repair by welding shall not be permitted.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 44/56
General Specification Date : 12/2012
Appendix 4
3. Welding qualifications
Same testing as per base material
4. Preheating
Refer to main part § 11.
5. Post heating
Heating rate ≤ 100°C per hour up to 150°C and then ≤ 150°C per hour to the holding
temperature.
Minimum heating rate shall not be less than 50°C/hour.
Degassing temperature shall be at least 50°C above the equipment operating temperature where
possible, but always at least 20°C lower than material tempering temperature and 250°C minimum.
The recommended degassing holding temperature range is between 350°C and 400°C. Holding
time shall be 15 minutes per 5 mm-wall thickness or part thereof. For metal thickness above
40 mm degassing time shall be at least 5 min per mm of wall thickness.
Cooling rate ≤ 150°C per hour down to 200°C and then cool in still air. Minimum cooling rate
shall not be less than 50°C/hour.
Cooling shall be slow down under fibber glass.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 45/56
General Specification Date : 12/2012
Appendix 4
PWHT procedures shall be submitted to the CONTRACTOR for review prior to setting up the
qualified welding procedure.
PWHT procedures shall include as a minimum the following information:
• temperature range,
• holding time,
• heating and cooling rates,
• number and location of thermocouples reported on a sketch,
• calibration of thermocouple,
• furnace type,
• support type number and location,
• extent of heat treatment/sequences.
All welding shall be completed before final Post Weld Heat Treatment.
7.1. Welds
After Final After
Type of Joint Before PWHT
PWHT Hydrostatic test
Butt RT 100% (1) UT 100% (1) MT 100%
MT 100% MT 100%
PMI (3) Hardness (5)
Corner UT 100% UT 100% (1) MT 100%
MT 100% MT 100%
PMI (3) Hardness (5)
Tee and nozzles connexions RT or UT 100% RT or UT 100% (1) MT 100%
full penetrated MT 100% MT 100%
PMI (3) Hardness (5)
Fillet welds MT 100 % MT 100 % N.A
Repaired welds RT 100% (1) RT 100% (1) N.A
MT 100% MT 100%
Hardness (5)
Temporary welds 100% MT or PT 100% PT N.A.
Notes:
(1) In case of difficulties, RT may be substituted by UT with approval of CONTRACTOR. Substitution possible when thickness over
35 mm with double wall technique and thickness over 50 mm with single wall technique
(3) 100% of welds and components.
(5) Hardness test shall consist of at least one HV Vickers hardness measurements in weld metal which shall be taken on each longitudinal and
circumferential weld seam and each diameter of branch connection nozzle. Each welding procedure used shall be tested
Hardness results shall not exceed 250 HV10
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 46/56
General Specification Date : 12/2012
Appendix 5
1. Scope
This annex describes the requirements for manual ultrasonic examination by contact of the weld
overlay and clad restoring
2. Stage examination:
Before PWHT: Extent 100% weld overlay,
After PWHT: Extent by grid 100 x 100 mm.
3. Personnel Certification
UT examination shall be performed by personnel certified in accordance with ASNT
Recommended Practice SNT-TC-1A, European norm EN 473 or ISO 9712 for Ultrasonic
examination in the relevant industrial sector (Welding).
4. Examination Equipment
The instrument type to be used shall be an impulsion generator (pulse-echo type).
The examination is carried out with Impulsion generator capable of frequencies between 1 to 5 Mhz.
The Impulsion generator shall have been checked at the beginning of each period of extended
use or every 3 months (whichever is less) according to the appendices I and II of ASME Section
V Article 4.
The scanning speed shall not exceed 150mm/s.
5. Coupling
The coupling will be, cellulose glue added with water or equivalent.
The couplants used on austenitic stainless steel or titanium shall not contain more than 250 ppm
of halides (chlorides plrs fluorides).
The couplants used on nickel base alloys shall not contain more than 250 ppm of sulphur.
6. Surface finish
All scanning surfaces shall be clean, sufficiently uniform and smooth to maintain a satisfactory
acoustic coupling.
7. Examination
7.1. Scanning from base material side
7.1.1. Probes
OL 0° E/R ø 10 or 24 mm, 4 MHz if Th. < 100 mm or 2 MHz if Th. ≥ 100 mm.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 47/56
General Specification Date : 12/2012
Appendix 5
7.1.3. Calibration
Calibration is made using a calibration block according to the following sketch.
The gain shall be set so that this response on artificial defect) is 80% (+/-5%) of full screen
height (Reference A %).
7.1.4. Scanning
The scanning is performed according to the following sketch.
During search, the gain shall be increased + 6dB minimum.
The examination may be performed from base material and the search unit may be moved
perpendicular or parallel to the weld direction.
7.2.1. Probes
OL 0° E/ R separated (dual probe) φ 10 or 24 mm, 4 MHz.
7.2.2. Calibration
Calibration is made using a calibration block according to the following sketch.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 48/56
General Specification Date : 12/2012
Appendix 5
The gain shall be set so that this response on artificial defect is 80% (± 5%) of full screen height
(reference A%).
7.2.4. Scanning
Scanning is performed according to the following sketch.
During search, the gain shall be increased + 6dB minimum.
The examination shall be performed from weld overlay side with the plane separating the
elements of the dual element search unit positioned parallel to the axis of the weld bead.
The search unit shall be moved perpendicular to the weld direction.
For Weld Overlay on Tube Sheet, scanning shall be performed only from the WO side.
8. Recording Examination
All indications with a amplitude ≥ 50% (reference A%) shall be recording.
When grid scanning is performed an indication (≥ 50% reference A%) is detected along a given
grid line, the entire surface area of the squares adjacent to these indications shall be scanned.
9. Evaluation of indication
9.1. Scanning
All the scanning shall be performed from the carbon steel side. When it’s impossible, scanning
from WO side is allowed.
An indication is considered as a surface indication if its reply is corresponding to the reply of the
flat hole Ǿ 10 mm on the calibration block.
An indication is considered as elongated if its reply is corresponding to the reply of the Groove
width 3 mm on the calibration block.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 49/56
General Specification Date : 12/2012
Appendix 5
9.2. Measurement
In all cases, the indication size shall be determined by the WO side.
The indication will be dimensioned by the – 6 dB fall method.
For an indication considered as a surface indication, its Surface S (mm²) shall be determined.
For an indication considered as a volumique elongated indication, its Length L (mm) shall be
determined.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 50/56
General Specification Date : 12/2012
Appendix 5
• number report,
• the examination stage and extend,
• the equipment used (flaw deflector, probe and calibration block),
• the calibration conditions,
• the examination results and cartography of the indications ≥ 50% of Reference A%,
• operator’s name, level and signature,
• date of examination.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 51/56
General Specification Date : 12/2012
Appendix 6
Figure D-1 Procedure Details for Welding Alloy and Clad Plate
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 52/56
General Specification Date : 12/2012
Appendix 6
Figure D-2 Butt Joint Design for Welding Clad Steel from Both Sides
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 53/56
General Specification Date : 12/2012
Appendix 6
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 54/56
General Specification Date : 12/2012
Appendix 7
Welding processes
Only manual or automatic TIG welding with direct current straight polarity (DCSP) shall be
admissible.
• Back shielding gas shall always be used.
• The nozzle shall be chosen with a large diameter to prevent entrainment of air. The
shielding argon gas flow shall in no case be disrupted by any external flows (suction or
blowing).
• The welding cycle shall always include a shielding gas time delay before arc striking
(pregas) and after arc fading (post gas).
• The welding sets shall have a "High Frequency" generator for contactless arc striking.
• The welding current shall be gradually decreased (arc fading) to minimise the crater and
shrinkage effect.
Welding products
• The filler metal shall be the same grade as the base metal.
• The argon used shall be of quality U (high purity).
Welding method
The welding shall be carried out:
• either in a sealed enclosure which can be placed under a vacuum at 10-2 mm Hg then
filled with argon;
• or under trailing shields (made of porous sintered metal) designed to shield the front and
back of the weld in order to cool the bath under argon after welding.
In addition, for fast automatic welding of longitudinal joints, copper blocks shall be placed on
either side of the weld to provide good lateral cooling.
For welding tubes which are generally thin (thickness less than one millimetre) to tube sheets
which are generally thin, the following grooved preparation shall be used. Its use allows a more
constant preparation for the sheet/tube weld, the groove must be at a distance (b) from the
drilled hole and shall be at least equal to the tube thickness (e).
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 55/56
General Specification Date : 12/2012
Appendix 7
Inspections
The inspections to be carried out shall be, in addition to the 100% radiographic inspection:
• two tensile tests in the crosswise direction;
• one bend on the front side and one on the back side, the ram shall have a width of 2 x e
for non-alloyed titanium or Pd alloyed titanium and 4 x e for the other titanium alloys;
• a hardness profile.
• No repairs to the welds shall be permitted. All welds containing at least one unacceptable
defect shall be completely reworked.
This document is the property of DGRC. It must not be stored, reproduced or disclosed to others without written authorisation from DGRC.
Page 56/56