Professional Documents
Culture Documents
SYSTEM (ExSPRO)
Setiawan Bin Hardono, Ishak Bin Mohamad, Zuraidah Bt Razali, Fauzul Azhan Bin Abd
Aziz, Suzianah Bt Sahar, Mohd Hairi Bin Abdullah Hashim
Abstract
“This paper aims to present the process of consultation that the author has undertaken
to assist in the process of re-aligning the Excellent Student Project System (ExSPRO)
by the Center for Research and Innovation (CFRI), Department of Polytechnic and
follow-up to the issues faced by the Center for Research and Innovation (CFRI) in terms
agency, which can be considered a non-profit organization and at the same time is
relatively tied to certain policies and bureaucracies. The consulting process for ExSPRO
Introduction
This paper aims to present the process of consultation that the author has
undertaken to assist in the process of re-aligning the Excellent Student Project System
undertaken to meet the requirements of the Government of Malaysia and the Industrial
Revolution 4.0.
The development of the ExSPRO system has been underway since 2017 and is
provisions. The budget allocation only involves budgeting for workshops and meetings
colleges.
CFRI was established in mid-2007 and has been in operation for almost ten years.
ii. Plan and manage research activities such as federal grants or industry
iii. Plan and manage innovation and acquisition of intellectual property including
iv. Plan and manage funding for innovation activities and acquisition of
external bodies.
vi. Plan and manage the financing of commercialization and technology transfer
innovation and bank ideas to serve as an advisory and reference center for
The planned project is a follow-up to the issues faced by the Center for Research
as follows:
i. Existing systems such as MyMOHES, SPMP and CIDOS are just a data
storage system for internal use for polytechnic and community college
ii. There is still no online system in the Departments and Institutions that
provides the opportunity and opportunity for the general public and the
outside industry to view student innovation work directly for the purpose of
iii. Existing systems are not integrated and do not conform to the requirements of
iv. The current system is slowing down the work process of the project consisting
v. Users need longer time to complete the work process as they have to use
different systems.
APPLIED CONSULTING AND PROCESS IN FACILITATING ODC: CASE OF EXCELLENT STUDENT PROJECT SYSTEM (ExSPRO) 5
Therefore, the CFRI, DPCC plans to develop an integrated system that can manage
more. This process will involve DPCC divisions such as CFRI and the Digital
the headquarters and several polytechnics and community colleges. The project is
Problem Statements
The ExSPRO project is behind the proper development schedule. The project is
only 15% of the development after 13 months of running the project. As an organization
The Challenges
Organizational
sector, it also interferes the project's smooth operation (Emelander, 2019). Uncertainties
APPLIED CONSULTING AND PROCESS IN FACILITATING ODC: CASE OF EXCELLENT STUDENT PROJECT SYSTEM (ExSPRO) 6
in government policy changes can sometimes lead to sudden changes in the course of
Team Leadership
strategic goals. Teamwork for projects is critical and is an environment where project
managers bridge the gap between director and leader. The transformation of the model,
one aspect of the leadership model that is perfect for the team, provides an inspiring
efforts of the project manager to build strong teams. Project teams usually rely on
specialists from the organization’s various areas, such as marketing, engineering, and
production.
Consulting
that allow clients to interpret, understand and act on process events occurring in both
internal and external environments to improve the situation as defined by the client. PC
Start Up.
The first stage begins with the initial consultant-client contact. The consultant
describes the problem or issue that needs assistance with the client. Listening during
this process is an essential capacity. The consultant should understand clearly the key
issues facing the company. The consultant should also initiate a discussion during this
stage about the expectations that she and the client have of each other, and the roles
that each will play throughout the consultation process. This phase may need to be
updated throughout the process if the project does not proceed as planned or if
The contractor helps the company determine the outcome expected during this
process. These include factors such as increased productivity, higher profits, increased
public profile, and improved working relationships between managers and their
employees. The consultant must also determine the type of product the user wants to
course. Each step allows the contractor to specify the type of data they need in the next
process to collect. Consultants also need to take some time to identify possible
Diagnosis.
Consultants continue to collect data on the main issues posed by the company in
this process. Different methods, such as surveys and questionnaires, evaluation and
Intervention
The criteria for an effective intervention include the right and useful information,
It is intended to provide all the details of the organizational issues raised during
the diagnostic process with the correct and useful information. The content is not the
consultant's or customer's business, but it is a reality and is a real part of the operations
of the company. However, the data is important to the issue being addressed, so it is
valuable for enhancing the organization. Consequently, a consultant's first task is to find
the best and useful information. If this function is ineffective, this means that the expert
APPLIED CONSULTING AND PROCESS IN FACILITATING ODC: CASE OF EXCELLENT STUDENT PROJECT SYSTEM (ExSPRO) 9
does not provide the appropriate and applicable information and that the correct solution
is challenging.
Free will means that the decision-making place is in the position of the client.
During decision making, consumers are entitled to choose alternatives. It's not about the
forced to take it. The freedom of choice is thus stressed that the individual does not
remain bound by the plan or decision made to be implemented. Customers who have
freely made efforts to strengthen their organization in a particular way, are responsible
for implementing them in this situation. This relationship is very important because the
essence of the building activities of the company lies in the bond between the people
involved from the beginning until the constructing effort of the organization is finished.
Transition
involves evaluating the outcomes of the initiative and overseeing the institutionalization
Feedback from members of the company on the results of the action provides
suspended.
APPLIED CONSULTING AND PROCESS IN FACILITATING ODC: CASE OF EXCELLENT STUDENT PROJECT SYSTEM (ExSPRO) 10
non-profit organization and at the same time is relatively tied to certain policies and
departments.
Initial Phase
This stage began when, we were contacted by the project director to ask about
our personal views on the issues he or she encountered in the course of the project.
Generally, he touches on projects that have been delayed from the implementation
schedule
Informally, we already know about the existence of this project. In the meantime,
we are in the process of consulting for another project run by a separate division of the
department for many years. To a lesser degree, we have understood the nature and
flow of process in this department. This situation gives us the opportunity to continue
this phase of contract approval. The initial pre-contract discussions last about a month.
This phase is followed by an explanation of the initial objectives that the project
Find out the root cause of the project that led to it being late.
months.
Provide teams with strong ties to each other during the development and
maintenance phases.
Consultants serve as observers and third parties who highlight anything that may
Data Collection
In this phase, we have several options for collecting data related to the
Questionnaire survey.
APPLIED CONSULTING AND PROCESS IN FACILITATING ODC: CASE OF EXCELLENT STUDENT PROJECT SYSTEM (ExSPRO) 12
Group discussion.
However, the questionnaire survey was rejected because it did not fit the objectives
outlined.
The five main aspects that being focused in this phase are:
Workflow Process
Technological.
During this phase, several data and information gathering activities were conducted:
Obtain and review key papers and authority documents from the ICT Steering
Committee.
A formal group discussion and rekick-off meeting was also held in early October
2019. This 6-hour session aimed at investigating the real issues behind the
Qualitative data obtained through interviews were analyzed and clustered into several
categories:
addition, the uncertainty is also in the technical aspects of the platform on the
The system development server also cannot determine its functionality and
existence.
Database Formation Documents and Data Dictionaries also fail to detect and
exist poorly and are properly filed. Poor documentation has also caused
difficulties for the ExSPRO system to integrate with other systems such as
MyMOHES.
Communication.
APPLIED CONSULTING AND PROCESS IN FACILITATING ODC: CASE OF EXCELLENT STUDENT PROJECT SYSTEM (ExSPRO) 14
by the lack of documentation that makes every team member not likely to be on
understand the flow of the ExSPRO business process themselves. 'Pluck The
Figure From The Sky' syndrome occurs among programmers. The development
Providing Feedback
It is not an easy task to present findings that may otherwise be unheard of and
and afterwards.
APPLIED CONSULTING AND PROCESS IN FACILITATING ODC: CASE OF EXCELLENT STUDENT PROJECT SYSTEM (ExSPRO) 15
acceptance and formation for change and new actions to implement the
To accomplish this stage, we have designed and implemented the following strategies
the need to present the concise, prudent and authentic findings available to all
team members.
It is said that the presence of the ODC is not to find fault but rather to add
team.
The feedback session was successful for 6 hours and the team decision was formally
obtained and published. It is important that the ODC offer only options and suggestions
Intervention
After the discussions were over and the ExSPRO system development team was
able to accept the fact that the status and circumstances of the project were not
favorable. ODC began to plan and present intervention offers to project directors and
Team
real-time tasks.
independent module.
branding.
October 2019.
processed.
Document management
o Issue: The absence of technical documents such as flow charts, data flow
standards.
During this phase, most of the interventions were well received and co-authored by
Follow up
Therefore, we recommend that live streaming meetings using the GSuite application be
held every 2 weeks. In addition, any development related discussions will be held on the
Conclusion
intervention in the processes and sub-processes involved. Material reward factors need
We hope the intervention and transitions of the ExSPRO project will achieve its
References
Emelander, S. (2019, August 1). Project Management Challenges in Government. Retrieved October 17,
government.
Nickols, F. (2003). The Consulting Process A “Bare Bones” Outline. Retrieved October 17, 2019, from
Schmidt, Alexandra. (2019, October 17). The Phases Of Consulting. bizfluent.com. Retrieved from
https://bizfluent.com/info-8636969-phases-consulting.html