Professional Documents
Culture Documents
PERT is a three point activity estimating technique that considers estimation uncertainty and risk by using three
estimates to define an approximate probability for an activity’s cost or duration. The three estimates used are:
Most likely (M) - The cost/duration of the activity, based on a realistic effort assessment for the
required work and any predicted expenses.
Optimistic(O) - The activity cost/duration based on an analysis of the best-case scenario for the activity.
Pessimistic(P) - The activity cost/duration based on an analysis of the worst-case scenario for the
activity.
How can PERT help us at activity level?
At activity level PERT can help us to determine a more realistic estimate. Let us take the following
estimates for five project activities as an example:
Let us assume that we obtained the following three estimates for Activity A. Optimistically we can complete the
activity in five (5) days. Pessimistically we estimate that it can take us up to Fifteen (15) days, while most likely
it will take us only seven (7) days.
PERT calculates a weighted average as the PERT estimate by using the formula : Pert Estimate = (Optimistic +
(4 X Most Likely) + Pessimistic)/6. That means that we are weighting the most likely estimate by a factor of
four (4) and then determining the average of the weighted most likely time, the best case scenario and the worst
case scenario. In the case of Activity A that will be (5 +(4 X 7) +15)/6. The pert estimate is therefore calculated
as 8 days. If we compare the PERT estimate of 8 days with the normal average of the three estimates of 9 days
(5 + 7 + 15 /3 = 9) we can see that the PERT estimated is weighted towards the most likely estimate. We use a
weighted average calculation because statistically we find that the largest portion of a randomly occurring
population of data will be found close to the mean as can be seen from the following bell curve, also called a
normal distribution curve:
This bell curve shows us that if we divide the data into 6 equal portions, then by far the majority of the instances
will be found in the 2 portions next to and on both sides of the middle line (mean) while the probability of the
occurrence falling in either the optimistic or pessimistic block is much lower. We divide the graph into 6 equal
block by calculating the standard deviation also called the sigma (identified by the sigma symbol “ϭ”). By using
the simple formula Sigma = (Pessimistic – Optimistic) / 6 we divide the graph in 6 equal blocks. From this we
can see that the PERT estimating formula using (Optimistic + (4 X Most Likely) + Pessimistic)/6 is based on
this natural distribution. This also gives us a tool with which we can quantify the probability of how the data
will be distributed. Statistically we know that:
68% of the data will be found in one standard deviation from the mean in other words between the mean
minus one standard deviation and the mean plus one standard deviation. We can also say that there is a
68% probability that the activity will be completed within one standard deviation from the mean.
We also see that 95% of the data will be found within two standard deviations or, put another way, that
we can say with 95% certainty that the activity will be completed withing the two sigma range.
At three sigma there is a 99,7% probability.
From the above bell curve we can thus predict that there is:
A 68% probability of completing the activity between 6.3 and 9.7 days.
A 95% probability of completing the activity between 4.6 and 11.3 days.
A 99.7% probability of completing the activity between 3.0 and 13.0 days.
The same formulas can be used to calculate the one, two and three sigma figures for all the activities:
The project standard deviation can be calculated by determining the square root of the sum of the PERT
variances. As per the above table the sum of the PERT variances is 41.8. The square root of 41.8 is 6.5.
Therefore one standard deviation for the project as a whole is 6.5 days. This value can now be used to calculate
the values for one, two and three sigma for the total project:
There is a 68% probability that the project will be completed between 53.8 and 66.8 days.
There is a 95% probability that the project will be completed between 47.3 and 73.3 days.
There is a 99.7% probability that the project will be completed between 40.8 and 79.8 days.
In practice these percentages can be used to indicate to the sponsor that, due to the uncertainty regarding the
estimates, there is a: