Professional Documents
Culture Documents
Roll #: 113
Class: BBA 6th
Section: C
Subject: Business Law
Submitted to: Sir Qasim
PERT Estimation Technique
PERT (Program Evaluation Review Technique) is an estimation technique which was first
developed and applied by United States Defence establishment for their Ballistic Missile
development program. It was one of their most ambitious programs. Completion of this in time,
ahead of the other nations was critical for them. Such missile development program was filled
with huge amount of uncertainty, as it required large number supplier agencies working on new
technology development. This method of estimation which helped them build-in all the
uncertainties in their estimates and helped them to complete this program ahead of their expected
schedule.
PERT uses a three point estimation approach for a task. Any task filled with uncertainties can
have a wide range of estimate in which the task actually will get completed. Uncertainties
Optimistic estimate – Estimate when all favourable things will happen (all opportunities
happen
For example, if we think about a task which involves travelling in a crowded city from a specific
location in the city to the airport. Actual time taken will depend upon the traffic condition on the
road.
This may take optimistically 30 minutes, pessimistically 90 minutes and most likely 60 minutes.
So the range in which the travel time will fall is 30 minutes to 90 minutes.
E (Mean PERT Average) = (O+4ML+P)/6 (by giving more weightage to most likely
estimate)
Actual time taken to travel will be anything within this range with the most likely duration as 60
minutes. PERT allows applying statistical concepts to study the probabilities of completing the
Assuming that the mean is exactly in the middle, and assuming the actual estimates will follow a
normal distribution within the extreme range of optimistic and pessimistic estimates, we can
predict the following probabilities of completing the task in certain range of time as below:
Mean +/- 1 Standard Deviation range – Probability is 68.4%
Conclusion
PERT estimation technique will be a practical approach for estimating when the tasks on hand
are filled with uncertainties, where the tasks may take up different estimates depending upon
certain conditions. Actual estimate is dependent on certain variables. PERT allows preparing a
more practical estimate by factoring the 3 point estimates into one as explained above.
Limitations of PERT
these estimates. If team members who are finding these estimates are less
Managing the critical path is difficult in PERT because it might change before
Updating, amending, and maintaining the PERT diagram can be time and cost
consuming.
Now, let us look at an example on PERT and Standard Deviation.
EXample
Your team members tell you that an activity you are working on is most likely to be
completed in 20 days. However, the worst case, it might take 30 days, and if all
Solution
We need the Optimistic Time, Pessimistic Time, and Most Likely Time for the activity to
The question says it is most likely that the task can be completed in 20 days, hence:
It also says that in the worst case it may take 30 days, hence: Pessimistic Time = 30
days
Finally, it says that if all conditions are favorable, it will take 15 days to complete the
Now,
PERT is a network diagramming technique that is used for large projects where
uncertainties are high and time is the main constraint. This tool helps project managers
to develop a sound schedule when there is little information on activity duration. In this
diagram, nodes are milestones instead of an activity. The success of PERT depends on
the experience of the professionals who have developed it. It is the job of the project
manager to remove the biases from the estimation as this can affect your PERT
schedule.