Assignment 1-Summer A
Assignment 1-Summer A
Question 1
Get the total time and the critical path for the attached network.
N
2
M S
2 3
G H K
2 1 3
F V L
2 4
3
A B C D E
1 2 4 4 2
U T
3
1
W Y
2
1 Z X
4 6
Question 2
Get the total time and the critical path for the following project.