Professional Documents
Culture Documents
Activities involved:
U
Activities
T
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Time (Days)
Activities Duration Start Finish
P 3 0 3
Q 2 3 5
R 4 5 9
S 2 9 11
T 3 11 14
U 4 14 18
V 2 18 20
W 1 20 21
X 3 21 24
Y 4 24 28
U
Activities
T
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Time (Days)
A project having 10 activities are related as below:
U
Activities
T
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Time (Days)
Activities Duration Start Finish
P 3 0 3
Q 2 0 2
R 4 2 6
S 2 3 5
T 3 5 8
U 4 5 9
V 2 9 11
W 1 11 12
X 3 11 14
Y 4 12 16
U
Activities
T
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Time (Days)
A project having 7 activities are related as below:
• B must precede D, B 3
Activities D
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Time in Days
Activities Duration Start Finish
A 2 0 2
B 3 2 4
C 2 2 5
D 4 5 9
E 5 5 10
F 3 10 13
G 4 10 14
Activities D
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Time in Days
Activities Duration Dates
A 2 07-Sep
B 3 09-Sep
C 2 09-Sep
D 4 12-Sep
E 5 12-Sep
F 3 17-Sep
G 4 17-Sep
Activities D
06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep
Calendar dates
White washing
Sanitary fitting
Electrical fitting
Superstructure
Foundation
0 1 2 3 4 5 6 7 8 9 10
Activities Duration Dates
A 2 07-Sep
B 3 09-Sep
C 2 09-Sep
D 4 12-Sep
E 5 12-Sep
F 3 17-Sep
G 4 17-Sep
Activities D
06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep
Calendar dates
SHORTCOMINGS OF BAR CHARTS
AND REMEDIAL MEASURES
Lack of Degree of Details
Sanitary fitting
Superstructure
Foundation
0 1 2 3 4 5 6 7 8 9 10
Time (weeks)
For example, consider the construction of a two
room house, the activities involved are shown in
the bar-chart in figure 1. The activity
Superstructure is shown by the single bar.
However, activity has the following sub parts for
its completion:
Sanitary fitting
Superstructure
Foundation
0 1 2 3 4 5 6 7 8 9 10
Time (weeks)
2. Review of Project Progress
Sanitary fitting
Superstructure
Foundation
0 1 2 3 4 5 6 7 8 9 10
Time (weeks)
Sometimes, different colours are filled in the bars
to show various 'control informations', as indicated
below:
Electrical fitting
Flooring
Plasterig
0 2 4 6 8 10 12 14
4. Time Uncertainties
?
?