Professional Documents
Culture Documents
Node Nodes
Activity
i j
Duration
start/from/i end/to/j
i and j
X Y
Y
3. Activities Y and Z are controlled by activity X. Neither of activities Y and Z can start
unless activity X is completed.
W Y
Z
X
5. Activity D is controlled by activities A and C. However, activity B is controlled by
activity A only.
A B
Dummy
activity
C D
U Y
Dummy
Dummy
W Z
7. Activity D is controlled by A, B and C. However, activity E is controlled by B and C.
Activity F is controlled by C only.
D
A
Dummy
B E
Dummy
C F
Dummy
Dummy
B E
9. Activity X is controlled by D and A; activity Y is controlled by A, B and C, while activity
Z is controlled by D only.
D D
Dummy
Dummy
A Y
C
Draw a network diagram for the project having 9 activities, with the following inter-
relationships:
NUMBERING TH
HE EVENTS
S
1. There is a sinngle initial event in a nnetwork diaagram. Thiss initial evennt will havee arrows
cooming out of
o it and non ne entering it. Number this initial event
e as 1.
2. N
Neglect all the
t arrows emerging oout of the initial even
nt numberedd 1. Doing so will
appparently prrovide one or
o more new
w initial eveents.
3. N
Number thesse apparently producedd new initiall events as 2,
2 3, 4 etc.
4. A
Again neglecct all emerg
ging arrow s from thesse numbereed events; th
this will creeate few
m
more initial events.
e
5. Foollow step 3.
3
6. Continue this operation until the last event, which l. emerging arrows, is numbered.
Skip Numbering
As a rule, a tail event must have a lower number than the head event. In bigger networks,
where extensive modifications frequently required to be made, re-numbering can be avoided
by numbering the events in the multiple of 10, i.e., numbering the events as 10 (initial), 20,
30, 40 etc. If an event is added later, it can be assigned a number (such as 31, say) which lies
between the number of immediate predecessor event and immediate successor event. This
process of numbering is known as skip numbering. Alternatively, skip numbering can also be
achieved by leaving out successive number such as (8, 9), (18, 19), (28, 29) etc. from the
lumbering of initial network. These left out numbers can later be assigned to newly added
events arising out of the modification of the initial network.