You are on page 1of 21

ORIGINAL RESEARCH

published: 03 September 2021


doi: 10.3389/fbuil.2021.713976

Using Real-Time Tracking of Materials


and Labor for Kit-Based Logistics
Management in Construction
Jianyu Zhao *, Yuan Zheng, Olli Seppänen, Müge Tetik and Antti Peltokorpi
Department of Civil Engineering, Aalto University, Espoo, Finland

Improved productivity and the elimination of waste are key goals for lean methods in
construction production control. One such lean method is a kit-based logistics
management in which task-based materials are delivered just-in-time and aligned with
assembly operations on-site. Digital platforms could enable a situational awareness of
work and material flows, potentially increasing the benefit and applicability of kitting. The
aim of the current research is to utilize a real-time indoor tracking of material and labor flows
to evaluate an assembly kit–based management of construction projects. We propose a
linked data framework to connect labor, material, and scheduling information to integrate
heterogenous data. The contribution of the study is threefold: first, a feasible method is
developed to enable real-time detection of work and material flows inside the building for
Edited by:
Samad Sepasgozar,
logistics management purposes. Second, several key performance indicators for effective
University of New South Wales, evaluation of kit-based production flow in construction are provided, which allows
Australia
management to tackle root causes of problems and to enhance timely and productive
Reviewed by:
logistic solutions. Thirdly, by applying the linked data method, the study introduces a novel
Laura Florez-Perez,
University College London, approach to integrate heterogenous data from both indoor tracking and schedules.
United Kingdom
Longhui Liao, Keywords: real-time tracking, construction management, linked data framework, material and labor tracking, data
Shenzhen University, China integration, kitting logistics solutions

*Correspondence:
Jianyu Zhao INTRODUCTION
jianyu.zhao@aalto.fi
Construction sites are frequently thought of as chaotic environments in which waste occurs as a
Specialty section: consequence of complex on-site management. As a result, sites suffer from productivity loss and
This article was submitted to waste related to crews’ waiting times, rework, unnecessary movement, material handling, and unused
Construction Management, inventories in workspaces and of materials (Sacks et al., 2010). This complexity has motivated the
a section of the journal development of several production control approaches in construction (Zhao et al., 2019). Lean
Frontiers in Built Environment construction principles are often applied to enhance workflows and eliminate waste by focusing on
Received: 24 May 2021 workflow variability to improve overall project performance (Thomas et al., 2002). The variability of
Accepted: 20 August 2021 flow is a key root cause of waste (Seppänen et al., 2010), and therefore measuring and addressing
Published: 03 September 2021
variability is important to eliminate waste and enhance productivity. In this regard, field material
Citation: management has become a crucial management process (Grau et al., 2009) to address the variability
Zhao J, Zheng Y, Seppänen O, Tetik M of material flows, to minimize waste, and to ultimately improve project performance.
and Peltokorpi A (2021) Using Real-
In the context of material flows, the construction process includes numerous wasteful activities
Time Tracking of Materials and Labor
for Kit-Based Logistics Management
that result from material mishandling on-site. For example, Teizer et al. (2020) monitored shell and
in Construction. interior construction and indicated the notable wasteful activities, including 1) unnecessary handling
Front. Built Environ. 7:713976. of material (10%), 2) searching for the right resources (6%), and 3) waiting to use the resource (3%),
doi: 10.3389/fbuil.2021.713976 all of which caused wasted effort related to material mishandling. Misplaced materials cause waste

Frontiers in Built Environment | www.frontiersin.org 1 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

such as rework and delays in tasks (Ju et al., 2012), both of which linked data approach to integrate the positional data of workers
hinder labor performance. The spaces used to store materials can and materials with scheduling data.
also potentially block workflows (Arbulu and Ballard, 2004) and Based on the above background, our aim is to improve the
affect production progress. Site managers and engineers thus management of kit-based practice by implementing a passive
must improve material handling and production flows by indoor tracking solution to automatically detect the presence
utilizing materials at the right time and in the right location. of multiple workers as well as material kits delivered directly
A kitting logistics solution synchronizes material deliveries to various work locations. We then evaluate the interactions
with workers’ daily tasks into work location levels (Tetik et al., of the material kit and labor flows. Previous research has
2020) and could play a key part in stabilizing production flows. indicated substantial periods of time when workers are absent
Assembly kits, which are carriers that contain material parts for from work locations (Zhao et al., 2019), so we consider an
different tasks (Hanson and Medbo, 2012), are transported investigation of how the kitting solution influences the
directly to work locations so the materials can be quickly presence of workers to be an interesting line of research.
utilized or installed by workers in the right places without New insights could also be gained relevant to the evaluation
being stored on-site (Tommelein and Li, 1999). Still, kitting of material management practice (e.g., the kitting solution)
practices face the challenges of monitoring in time and and enhancement potentials by tracking both labor and
efficiently for the direct involvement of workers who use the material kits at the same time. Finally, a linked data
material batches in work locations. For example, previous framework is proposed to unite external data streams (e.g.,
methods for evaluating the impacts of kitting practices were scheduling information) to ensure data model
based on manual observations and videos (Tetik et al., 2020), interoperability and to evaluate the compliance of workers
which makes evaluating the solution both labor intensive and with material kits against the schedule. A broader image of
time consuming. Kitting logistics practice requires smooth construction resource interrelations thus can be established
information flows among different operations: a situation that for future application development.
also leads to the potential for automation (Zheng et al., 2020).
The use of automated tracking solutions for material
management could address these challenges and enhance TECHNICAL BACKGROUND
construction productivity and workflow by providing site
managers with easy-to-use metrics to evaluate the process of In this section, the technical background is reviewed from
flows. In building projects, automated material monitoring could previous studies related to tracking technologies that have
help workers know the locations of materials. In this way, been applied in construction for labor and material
searching times for materials are eliminated, productivity is monitoring, linked data, and Semantic Web technologies.
improved, and material handling efficiency is enhanced Tracking technologies can be divided into vision- and radio-
(Gurmu, 2019). based tracking methods. Table 1 summarizes the previous
Despite the expected benefits for site management from tracking applications used in the construction industry and
localization technologies (Grau et al., 2009), little research has presents conclusions from research related to our empirical
been conducted on tracking systems that cover both materials study on tracking solutions for material and labor flows in
and workers to support lean principles for enhancing material construction.
management and related workflows. Although the collection of
tracking data based on labor and material could improve Vision-Based Tracking in Construction
construction material and workflow management, such data is Several vision-based methods have been proposed and
still isolated from the scheduling information of planned on-site implemented for monitoring site occurrences involving labor,
operations. Such fragmentation leads to difficulties for various material, and equipment. The methods are generally easy to
stakeholders when evaluating and comparing the actual labor and deploy and are non-intrusive (Cai and Cai, 2020), although
material flow situation with the planned conditions based on an achieving smooth and continuous tracking that is satisfactory
integrated database. The worker and material positioning data for labor and material flows could be a complex undertaking. For
thus should be combined with the scheduling information in instance, recent research (Asadi et al., 2019) examined the
order to investigate the schedule compliance of labor and material possibility of using Building Information Modeling (BIM)
interactions. coordinate system from camera poses of image frames, which
The linked data approach is a set of design principles within enabled localization and mapping items between image frames
Semantic Web technologies for publishing data in a structured and BIM views. The research demonstrated the effectiveness of
format (Bizer and Schultz, 2009). Such an approach can structure real-time registration of images with BIMs, which could
heterogenous data with interlinks to provide formalized and potentially enhance visibility of tracking process for resources
structured data integration. The linked data approach also such as labor or materials in the BIM platform. However, the
provides a machine-readable format for computers to method heavily depends on camera pose estimation and the
understand the meaning of the data so they can produce interior structure of the buildings such as curved walls or
meaningful query results. While construction industry arches may be prone to higher error of analysis. Those
researchers have investigated these capabilities of the linked limitations may complicate the generalizability of applying this
data approach (Pauwels et al., 2015), they have yet to use the method as the use of a secondary positional sensor such as inertial

Frontiers in Built Environment | www.frontiersin.org 2 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

TABLE 1 | Previous research and conclusions related to our study.

Research Tracking solution Main results Conclusions directing our


study

Angah and Chen (2020): Tracking multiple Vision-based technology: video The authors tested and illustrated a The tracking solution enables multiple
construction workers through deep learning cameras multiple human tracking framework human monitoring but can encounter
and the gradient based method with re- which enables automatic detection, heavy interference for issues such as
matching based on multi-object tracking matching and re-matchig scale variations, appearance similarity,
accuracy occlusions, posture variations, abrupt
movement etc., thus hindering the
tracking and detecting of labor and
material flows indoors
Cai et al. (2019): Two-step long short-term Vision-based technology: The authors presented a working group The method allows for identifying
memory method for identifying construction construction video cameras identification method followed by activity construction activities through positional
activities through positional and attentional recognition based on both positional and and attentional cues so that the
cues attentional cues, to recognize complex interaction details of multiple entities
interactions from videos captured by videos could be recognized,
but the framework relies on positional and
attentional cues computed based on
manually annotated states of individual
entities. Furthermore, the method was
only tested outdoor construction
projects, so the indoor environment is yet
to be experimented
Kim et al. (2019): Remote proximity Vision-based technology: The authors proposed a UAV visual The method is useful for enabling
monitoring between mobile construction unmanned aerial vehicle (UAV)- monitoring solution that automatically automatic measurement of actual
resources using camera-mounted UAVs assisted visual monitoring measures proximities (actual distance distances among construction entities
method from 2D images captured from a UAV) which makes it possible for improving
accuracy of interpreting the actual
interactive activities of labor and materials
in our case. However, the framework
underwent difficulties to obtain clear state
of an object due to obstruction of noises
such as sands which may cause false-
positive results. Furthermore, the
feasibility of implementation UAV into
indoor environment can be also
challenging
Guven and Ergen (2021): Tracking major Radio-based technology: RFID The authors presented an automated The tracking method can determine
resources for automated progress progress monitoring system that utilized construction progress by fusing sensor
monitoring of construction activities: RFID technology to track a masonry task data collected from multiple resources.
masonry work case activity for multiple resources in The overall progress reached 95%
construction accuracy which potentially contributed to
estimating labor and material interactions
onsite. However, the method was only
applied on masonry task, so the accuracy
of other tasks is yet to be tested.
Furthermore, The RFID sensors were
installed in tower crane to enable floor-
level tracking detail, but at this stage the
floor information of where the masonry
materials were delivery was entered
manually which would impact the whole
automated progress monitoring
Ryu et al. (2019): Automated action Radio-based technology: The study allows for automatic The tracking approach is good for
recognition using an accelerometer- accelerometer-embedded construction action recognition using a capturing workers’ action in construction
embedded wristband-type activity tracker wristband-type activity tracker single wrist-worn sensor so that the sites, which has potential for detecting
characteristics of workers’ actions can ongoing activities, but the method relies
be suggested on predetermined and labeled action
classification so the method may work
well on standardized and repeated
actions but not the non-repetitive ones.
Furthermore, the study did not consider
material movement but only focused on
workers, so the interaction of labor and
materials’ movements were not possible
to detect
(Continued on following page)

Frontiers in Built Environment | www.frontiersin.org 3 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

TABLE 1 | (Continued) Previous research and conclusions related to our study.

Research Tracking solution Main results Conclusions directing our


study

Zhao et al. (2019): Real-time resource Radio-based technology: BLE The authors implemented a BLE tracking The tracking method allows for passive
tracking for analyzing value-adding time in system to detect and evaluate workers’ and automated monitoring of workers’
construction uninterrupted presence on-site at the presence on-site, which enables the
project level possibility of continuous tracking of labor
flows; the research did not consider
material tracking, however, so the
interaction of workers and materials in
work locations was unknown
Zhang et al. (2021). Wireless Radio-based technology: ZigBee The study demonstrates a proposed The combined networks of using both
Monitoring–Based Real-Time Analysis and and general packet radio service integration technology of real-time ZigBee and GPRS provided timely and
Early-Warning Safety System for Deep and (GPRS) analysis and safety early warning can reliable data support of detecting
Large Underground Caverns timely detect abnormalities from abnormalities of workers’ tracking
monitoring process and stepwise records. The method could be useful in
evaluation results our case by adding early-alert mechanism
to enable automatic operation
intervention possibilities from site
managers when the abnormalities of
labor and material movement show
notable. However, the method was only
applied in underground environment and
the scope of the study was focused on
construction safety therefore whether the
method could also enhance onsite
operation and productivity remains
unknown
Yang et al. (2020). Automated PPE-Tool Radio-based technology: The study developed an automated The method works efficiently checking
pair check system for construction safety Wireless Wi-Fi module personal protective equipment (PPE) paired workers and their tools and
using smart IoT based tool for pair checking of workers materials onsite, which has good
and their equipment using the internet of potentials to be expanded for checking
things (IoT) with Wi-Fi modules tagged effectiveness of workers using the tool or
on the PPE. materials. However, the method was only
tested in a lab experiment, so the
challenges revealed in the lab test (such
as heavy consumption of battery using
Wi-Fi module and obstruction of low
illumination) should also be assessed in
real construction projects for evaluation.

measuring unit (IMU) and ultrawide band (UWB) may often be Radio-Based Tracking in Construction
needed to address these issues (Asadi et al., 2019). Another category of sensor-based monitoring consists of radio-
Despite the possibility of identifying site activities and based tracking technologies, which are already being applied in
detecting task status from workers (Luo et al., 2018), the many construction projects. Such technologies are typically based
current state-of-the-art vision-based methods may not on radio signals that are sent and received among tags (such as
achieve our aim of tracking both material and labor due to beacons) and gateways (Cai and Cai, 2020; Dror et al., 2019).
challenges in long-term and robust monitoring of multiple Radio-based tracking technologies are less accurate compared
objectives (Cai and Cai, 2020). For our use case, each work with vision-based tracking technologies (over 1 m for radio-
location would have to have a camera to ensure the visibility frequency identification [RFID] and Bluetooth Low Energy [BLE]
of resources on-site for the entire tracking period; in technology), but they are reliable in tracked object detection and
addition, multiple tracked resources (e.g., workers and identification during the tracking period (Cai and Cai, 2020).
materials) might interfere in the view and occlude each Because of the capability of providing reliable information to
other within confined work locations such as apartments. exclude false detection (Cai and Cai, 2020), radio-based tracking
Given the requirement for extensive data sets while training technologies may be more suitable for analyzing the interactions
the system (e.g., Luo et al., 2018) and the demands for proper of multi-resource movements when the constant accuracy of
shooting angles from cameras (Zhang et al., 2018), these resource identity is required during the entire monitoring period.
complexities mean that vision-based tracking solutions Some common tracking methods include Zigbee (Zhang et al.,
may not be practical for analyzing the interactive 2021), accelerometer wristband (Ryu et al., 2019), Wi-Fi module
movement of labor and materials. (Yang et al., 2020), the aforementioned RFID (Guven and Ergen

Frontiers in Built Environment | www.frontiersin.org 4 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

2021) and BLE (Olivieri et al., 2017; Park et al., 2017; Zhao et al., data offers significant advantages to alleviate the problem of
2017). These methods all appear to eliminate the effort involved information heterogeneity. Using this approach, data is
in manual data collection in construction while being accurate machine-readable, explicit, and linked to other external data
and providing in-time data feedback through an automated sets and can in turn be linked to and from external data sets
process. For instance, the RFID solution enables tracking by (Bizer et al., 2011). The four basic uses of linked data include 1)
attaching tags that are active, semi-active, or passive and the use of Uniform Resource Identifiers (URIs) to name
having scanners or antennas read the tags (Ergen et al., 2007; resources; 2) the use of Hypertext Transfer Protocol (HTTP)
Li et al., 2020). URIs to provide access to resources via the internet; 3) the
The advantage of passive RFID technology is that those tags do not provision of extra information about resources using various
need a separate power supply and are small, inexpensive, and suitable standards, including the Resource Description Framework (RDF)
for nearly all kinds of materials (Teizer et al., 2020). This solution and RDF query languages such as SPARQL, when looking up
would be helpful for detecting material flows in different work URIs; and 4) the provision of links to related URIs to explore
locations in parallel with workers’ movements. Passive RFID tags more related factors.
cannot be used in large-scale environments, however (Wu et al., 2019), RDF is the critical technology involved in establishing the
and potential signal blocking under chaotic and dynamic indoor “web of data,” where data is encoded in the form of “subject,
construction conditions still causes challenges in the signal quality of predicate, object” triples (Bizer et al., 2011). These triples are
this tracking method (Teizer et al., 2020; Costin et al., 2012). In recent statements with resources modeled as subjects with their
study, RFID tracking methods have also been experimented into associated properties and the value or object of the properties.
integration of BIM. Chen et al. (2020) proposed a framework to RDF provides a graph structure in which users can look up any
integrate the use of detailed look-ahead plans when applying BIM and URI in an RDF graph over the web to retrieve additional
RFID technologies, aiming at enhancing supply chain visibility and information. Thus, each RDF triple is part of the global web
material flow process in pursuit of Industry 4.0. However, despite of of data, and each RDF triple can be used as a starting point to
the potentials to integrate the tracking method into BIM, the explore the data space.
framework has only been implemented on simulated projects, and Increasing implementations of linked data have recently
the benefits from the real-world projects have not yet been emerged in the construction domain. Construction
investigated. information and data are often characterized as fragmented,
Furthermore, Yang et al. (2020) developed an automatic since the construction information is usually acquired via
monitoring system connecting workers and their associated tools various information sources and from different stakeholders
for pair checking by using Wi-Fi networks on construction sites. The who work in various construction disciplines and use a variety
study demonstrated high potential of using radio-based technology to of tools, systems, and software. For example, Pauwels et al. (2015)
enable near real-time detection of interaction of workers and tools. reviewed various applications of linked data in the architecture,
Their research was conducted only as a lab test and was focused on engineering, and construction (AEC) domain and concluded that
construction safety. They did not consider production flows or linked data was used to improve information interoperability and
operations in their study. to link across domains to fuse construction information for
Compared to other radio-based tracking solutions, the BLE further information utilization. Curry et al. (2013) explored
tracking method has the following characteristics and advantages the use of the linked data approach to integrate cross-domain
for indoor monitoring of multiple resources in parallel: 1) the building data in order to serve a holistic database for the building
BLE tracking method involves minimal false negative alerts and lifecycle. Lee et al. (2016) proposed a linked data framework to
requires the least input of infrastructure and time for calibration share construction defect information to integrate the defect data
(Park et al., 2016); 2) the solution is cost efficient and lightweight from different silos to alleviate insufficient defect data sharing. To
for passive monitoring in previously tested construction projects our knowledge, however, no recent works have used the linked
(Zhao et al., 2019); 3) the solution supports multiple resource data approach to integrate indoor positioning and scheduling
tracking with reliable identity information, which is important in information to support the investigation of on-site material and
workers’ material handling. The BLE tracking method thus can be labor interactions.
a suitable approach for tracking both labor and material flows for
the purpose of improving material handling and evaluating a
specific material management solution on-site. To the best of our Possibilities for the Tracking of Kits and
knowledge, no reported studies to date have used the BLE Workers in Production Flow Improvement
tracking method within building projects’ indoor Material handling in construction is still frequently reviewed as
environments to investigate the interactions of construction primitive, and advanced on-site material management practice is
workers and materials. necessary for improvement (Caldas et al., 2006). Site material
management could substantially benefit from automated tracking
technology and automation in detection (Grau et al., 2009). For
Linked Data and Semantic Web example, the use of material tracking practice could enhance
Technologies worker productivity (Nasir et al., 2010) and minimize the time
Linked data is an approach in which the web is used to create links workers spend on searching for the right materials (Gurmu,
between data from different systems or sources. The use of linked 2019). In particular, material tracking may be used to evaluate

Frontiers in Built Environment | www.frontiersin.org 5 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

and improve logistics practice: a material kitting solution which tracking in work locations using a kit-based logistic solution. The
was proposed to enhance the time efficiency (Hanson and Medbo, underlying kitting solution, as part of the material management
2012). practice, can be assessed based on the “uninterrupted presence
Specifically, the kitting solution in logistics allows for more levels” of workers, as captured by the tracking system. A worker’s
efficient and prompt material deliveries directly to work uninterrupted presence level is an uninterrupted period that the
locations. With origins in manufacturing industries, the worker spends in the same work location before moving to
concept of kitting involves packing and delivering the another location. A threshold is set to define how much time
products necessary for an assembly task into one single workers need to stay at one work location before their jobs are
package to a designated workplace (Bozer and McGinnis, considered uninterrupted (Zhao et al., 2019). For system
1992). Because kits can be delivered close to the exact work implementation, we followed the process of a BLE-based real-
locations, the practice can enhance productivity by allowing for time tracking system from a previous study (Zhao et al., 2019),
more efficient material usage in work locations and reducing the including 1) setting up the real-time tracking system based on site
time spent looking for components required for various tasks floor plans, 2) evaluating the system accuracy by comparing the
(Tetik et al., 2020), thus contributing to overall work progress and system results to a researcher’s known movements (ground-truth
production stability. But the relationship between material data), 3) verifying the coverage of the system based on ground-
storage and project productivity has not been examined truth data, and 4) capturing and analyzing the uninterrupted
thoroughly in construction logistics (Seppänen and Peltokorpi, presence of workers and material kits.
2016). Kitting is usually used with other logistics practices such as Next, the real-time tracking system architecture and model are
logistics hubs and just-in-time (JIT) delivery. Logistics hubs can demonstrated. Then our case study is introduced in more detail.
be configured to support assembly and kitting activities (Hamzeh
et al., 2007). Tetik et al. (2020) showed, using four case studies, Real-Time Tracking System Infrastructure
that a kitting intervention could stabilize assembly work and Our current research uses the same BLE-based real-time tracking
increase workers’ productivity and workplace utilization. They system that Zhao et al. (2019); Zhao et al. (2021) used in their
measured work performance via schedule compliance, the share previous study. In the model, BLE beacons were used that could be
of value-adding time in work locations, and labor productivity by associated with construction workers who had previously agreed to
applying the camera-based video monitoring (for 44 days in total) be monitored. The beacons send their media access control (MAC)
and manual observation (for 25 days in total) methods of data address to the gateways (Raspberry Pi) periodically at an
collection. While their research did demonstrate the value of kits, approximately one second frequency; the gateways then transmit
their research method was resource intensive and may not be the information to the cloud. The information contains a unique
implemented scalably by practitioners who wish to improve their MAC address of each beacon assigned to a worker’s profile and a
logistics practices. The management of kitting still encounters time interval for the worker’s presence in the database. The data
potential challenges because no automated way currently exists to analyzer identifies the beacons’ locations from the magnitude of the
calculate key performance indicators (KPIs), which are used to received signal strength indicator (RSSI). To solve the potential
evaluate the success of the kitting method. Therefore, the benefits signal flickering problems (the gateways are close to each other, and
often remain anecdotal, which may hinder the implementation of the results that are detected flicker between locations (Zhao et al.,
such systems. 2019)), the system uses recent RSSI values; the oldest values are
In the current paper, we first explain the indoor positioning removed when new values are pushed in the data analyzer. The RSSI
system infrastructure and a case in which a kitting logistics value is averaged and the outlier values minimized to mitigate
solution was used; we then develop a linked data framework potential flickering interference. When a worker moves from one
to connect the typically heterogeneous information sources of location to another and is detected by a different gateway, a new time
labor, materials, and schedules. Next a novel method is proposed interval is automatically generated in the system. The cloud provides
to calculate the time-matching level of workers and materials in downloadable data for future analysis. The architecture of the indoor
work locations based on their detected uninterrupted presence. tracking application used in our case studies is illustrated in Figure 1
Finally, new KPIs are introduced to evaluate the kitting practice (Zhao et al., 2019).
for the improvement of site material management and work
progress in construction. Case Description
The case a renovation project was selected in Helsinki, Finland.
The renovation work was undertaken in a three-floor building
METHODS during June 2018. The case project team applied a kitting logistics
solution because of the potential to improve workplace utilization
We follow the design science research methodology in this study rates by minimizing the wasted efforts of material transportation
(Peffers et al., 2007) and will demonstrate our research method in from storage areas to the site (Tetik et al., 2020). We placed one
terms of system infrastructure, case description, time-matching gateway in each apartment, with nine total installed gateways
level calculations, and the proposed linked data framework. (eight gateways in eight apartments and one at the entry on the
The real-time tracking system that was used in previous ground floor). Eight workers (including carpenters, plumbers,
research (Zhao et al., 2019) was implemented in this case, but plasterers, and bricklayers) agreed to be monitored and were
we expanded our focus into the integration of labor and material given the beacons; each of the eight material kits was also attached

Frontiers in Built Environment | www.frontiersin.org 6 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

FIGURE 1 | The architecture of the tracking system applied in our case studies (adapted from Zhao et al., 2019).

with beacon tags for monitoring. Due to the different sizes of the detected by gateways that were near each other); and 3) non-match
apartments, the quantities of materials in the kits could be category 3 (the beacons that were not detected at all due to coverage
different, but the materials were the same for the tracked tasks problems.
in each apartment. Each material kit was assigned to each The system accuracy and coverage were evaluated by
apartment for the tasks shown in Table 2. As shown in the comparing the tracking results with ground-truth data (Zhao
table, each kit included the necessary material for the bathroom et al., 2019). We had a researcher simulate workers’ possible job
renovation in that specific apartment. The possibility of attaching routines on-site in both cases. The researcher self-recorded his
both material and labor data enabled us to monitor the movements to serve as the ground-truth data. Table 3 presents a
interactions of workers as they went about their on-site summary of the system accuracy and coverage results in this case.
material-related tasks. Compared to previous renovation project tracking in which the
Figure 2 shows a simplified floor plan, with gateways marked system reached 71% coverage and 55% accuracy via the same
in the jobsite. Table 2 shows a task schedule summary for tracked tracking method, with gateways installed at stairwells on each
workers and tasks. Each tracked task follows the same sequence floor (Zhao et al., 2019), our tracking data achieved sufficient
from apartment A3 to A4, A8, A7, A1, A2, A6, and A5. Each system accuracy without sacrificing coverage, mainly because we
successor apartment in the sequence for the same task is always placed gateways in each apartment near the bathroom area where
scheduled half a day later than the former apartment, skipping the material-related work was scheduled in this renovation
weekends. The scheduled worktime is from 7:00 to 11:00 in the project. This placement decreased the interference compared
morning for the first half day, and from 11:30 to 15:30 in the to the previously reported case, where gateways on adjacent
afternoon for the second half day. The tasks listed in the table only floors could interfere with each other and cause detection
covered work that was done in bathrooms. Workers from other inaccuracies.
trades (such as electricians and painters) were on the site during
the tracking period in the workflow, but we did not monitor Linked Data Framework
their tasks. The proposed framework is designed to provide automatic
identification of labor and material KPIs with limited human
System Coverage and Accuracy disturbance in order to support stakeholders in understanding the
To ensure the quality of the results, we needed to first test the situation of on-site operations (see Figure 3). The framework also
accuracy and coverage of the tracking system. The definition of connects the database of indoor positioning data with external data
“accuracy” and “coverage” from previous research (Zhao et al., sources such as schedules. Three tracks have been designed in this
2019) was followed: accuracy is defined as the proportion of how framework, including Data collecting, Linked data implementing, and
much time, detected by the system, is recorded in the correct location Data processing. The Data collecting is the initial track that obtains the
and at the correct time, while coverage is defined as the share of the indoor positioning tracking data of the labor and material kits, as
total time detected by any gateway of the system. For any incorrectly described in Real-Time Tracking System Infrastructure section—the
detected times recorded in the system, we classified these times into real-time tracking system infrastructure and project scheduling data.
three non-match categories (Zhao et al., 2019): 1) non-match category Following the data collecting track, the Linked data implementing
1 (the beacons detected by an incorrect gateway for a period of over a track triggers. The major objective of this track is to prepare, convert,
minute); 2) non-match category 2 (data flickering issue, the beacons and link the data collected from the indoor positioning system and

Frontiers in Built Environment | www.frontiersin.org 7 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

TABLE 2 | Task schedule summary for tracked workers and tasks.

Worker Tasks If using 05-31 05-31 06-01 06-01 06-04 06-04 06-05 06-05 06-06 06-06 06-07 06-07 06-08
type materials, 07:00 11:30 07:00 11:30 07:00 11:30 07:00 11:30 07:00 11:30 07:00 11:30 07:00
included
05-31 05-31 06-01 06-01 06-04 06-04 06-05 06-05 06-06 06-06 06-07 06-07 06-08
in the
11:00 15:30 11:00 15:30 11:00 15:30 11:00 15:30 11:00 15:30 11:00 15:30 11:00
kits?

1 1 Yes A3 A4 A8 A7 A1 A2 A6 A5
2 6 Yes A3 A4 A8 A7 A1 A2 A6 A5
2 7 Yes A3 A4 A8 A7 A1 A2 A6 A5
2 8 No A3 A4 A8 A7 A1 A2 A6 A5
3 9 Yes A3 A4 A8 A7 A1 A2 A6 A5
4 12 No A3 A4 A8 A7 A1 A2 A6
1 2 Yes A3 A4 A8
1 3 Yes A3 A4
06-08 06-08 06-11 06-11 06-12 06-12 06-13 06-13 06-14 06-14 06-15 06-15 06-18
07:00 11:30 07:00 11:30 07:00 11:30 07:00 11:30 07:00 11:30 07:00 11:30 07:00
06-08 06-08 06-11 06-11 06-12 06-12 06-13 06-13 06-14 06-14 06-15 06-15 06-18
11:00 15:30 11:00 15:30 11:00 15:30 11:00 15:30 11:00 15:30 11:00 15:30 11:00
3 9 Yes A5
4 12 No A6 A5
1 2 Yes A8 A7 A1 A2 A6 A5
1 3 Yes A4 A8 A7 A1 A2 A6 A5
1 4 Yes A3 A4 A8 A7 A1 A2
1 5 Yes A3 A4 A8 A7 A1 A2 A6 A5
4 13 Yes A3 A4 A8 A7 A1 A2 A6 A5
3 10 Yes A3 A4 A8 A7
4 14 Yes A3 A4
06-18 06-18 06-19 06-19 06-20 06-20 06-21 06-21 06-22 06-22 06-25 06-25 06-26
07:00 11:30 07:00 11:30 07:00 11:30 07:00 11:30 07:00 11:30 07:00 11:30 07:00
06-18 06-18 06-19 06-19 06-20 06-20 06-21 06-21 06-22 06-22 06-25 06-25 06-26
11:00 15:30 11:00 15:30 11:00 15:30 11:00 15:30 11:00 15:30 11:00 15:30 11:00
3 10 Yes A7 A1 A2 A6 A5
4 14 Yes A4 A8 A7 A1 A2 A6 A5
4 15 Yes A3 A4 A8 A7 A1 A2 A6 A5
3 11 Yes A3 A4 A8 A7 A1 A2 A6 A5
4 16 Yes A3 A4 A8 A7 A1 A2 A6 A5

WORKER TYPES: 1 (bricklayers), 2 (plasterers), 3 (plumbers), 4 (carpenters). TASKS: 1 (door wall masonry), 2 (rebar mesh), 3 (floor concreting and draining), 4 (surface priming), 5 (waterproofing
rolling), 6 (wall priming), 7 (plastering), 8 (cleaning), 9 (drainage), 10 (pipe attaching and connections), 11 (toilet installation and connection), 12 (layout), 13 (frame installation), 14
(suspended ceiling plating), 15 (shower wall fixing), 16 (applying silicone in walls).

FIGURE 2 | A simplified floor plan, with gateways marked on-site.

Frontiers in Built Environment | www.frontiersin.org 8 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

TABLE 3 | Summary of system accuracy and coverage (all times in minutes).

Total simulation Total matched Non-match category Non-match category Non-match category Accuracy (%) Coverage (%)
time on-site time 1 time 2 time 3 time

214.2 189.4 (88.4%) 14.6 (6.8%) 4 (1.9%) 6.2 (2.9%) 88.4 97.1

FIGURE 3 | Architecture of the linked data framework.

schedules, based on the linked data method, to create an integrated kitting solution has worked and whether the workers were able to
database that holds the comprehensive indoor positioning data and use materials from the kits to conduct their tasks in various work
scheduling data. In this track, as a first step, the indoor positioning locations. The workers’ time-matching levels and kits refer to the
data of the tracking labor and material kits collected from the indoor time period when workers’ detected presences overlap with the
positioning system and the project schedule is mapped in a certain kits’ detected presences.
ontology and schema for formalizing and creating the interlinks. The Workers and material kits at one work location can have the
data is then converted into RDF graphs and stored in the RDF graph following interactions: 1) both the material kit and workers are
store. The final track is the Data processing, in which the integrated in the work location; 2) the material kit is in the work location,
RDF graph is processed and queried to calculate the KPIs of workers’ but the worker is not; 3) the worker is in the work location, but
overlapping time levels and material kits based on the principles the material kit is not; and 4) neither the material kit nor the
introduced in the following part. worker is in the work location. Scenario (1) is the best scenario
when a worker is scheduled to perform the material-related
tasks at that location, while scenarios (3) and (4) could indicate
Calculation of Workers’ Time-Matching issues with the kitting solution because workers are working
Levels and Material Kits in One Apartment without the kit, or material kits have not been delivered as
Since kitting material logistic solutions require each material kit planned.
to be delivered directly to each work location (in this case, each The raw data was analyzed to estimate the overlapping time
apartment bathroom), workers’ time-matching levels and level of workers and material kits for each apartment using the
material kits can be used to indicate how well the underlying following steps.

Frontiers in Built Environment | www.frontiersin.org 9 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

1) The uninterrupted presence threshold represents the Figure 4 shows how the STMD and STMM calculations were
minimum time period that a worker needs to be present at carried out based on detected presences and scheduling
one site location without interruption gaps to be able to count information.
this presence as uninterrupted (Zhao et al., 2019). We set this In addition to calculating the time-matching level of
threshold for 10 min as the highest-tested value in Zhao et al.‘s workers and material kits, we were also interested in the
work (2019) because we wanted to focus on longer continuous following metrics related to the time and movements of
working periods rather than brief visits in a location. Because material kits to evaluate the performance of the logistics
we installed one gateway in each apartment in the building, we system: 1) delivery times of the kits to the first detected
were able to classify all detected uninterrupted worker apartment on-site; 2) removal times of the kits from the
presences by each work location (in this case, each last detected apartment on-site; 3) number of times each kit
apartment). The threshold was not applied on material kits moved between the delivery time and removal time. Those
because, due to their weight and immobility, their location is metrics contribute to understanding in more details of the
more fixed, and filtering out short visits is not required. material flows such as waiting time and the level of
2) For a single apartment, we aggregated all detected presences of unnecessary inventory. Although these metrics are not
the material kit assigned to that apartment. For example, in new, the novelty of the method lies in using the proposed
apartment 1, we searched for all detected presences of the lightweight monitoring system to obtain the time and
material kit assigned for apartment 1. location information automatically and passively to
3) T1  the uninterrupted presence of a worker during the same time analyze these metrics without time consuming data
when the material kit for that assigned apartment was present. collection efforts.
4) T2  the uninterrupted presence of a worker matched the time In summary, together with comparing the time-matching level
period of a material kit that was assigned to other apartments of workers and material kits based on their overlapping
but was present in the current apartment. uninterrupted presence, kit delivery times, and movements
5) T3  the uninterrupted presence of a worker that did not fall based on the analyses of automatically detected temporal and
into time periods of any material in that apartment (the spatial information by the real-time tracking system, we were able
uninterrupted presence of the worker thus  T1 + T2 + T3). to assess the soundness of the kitting solution in this case, such as
6) T4  the operational time of each worker, which was by examining how well the kitting material management practice
defined as the time from a worker’s first detected time worked in each work location.
of the day to the last detected time of the day (Zhao et al.,
2019).
7) The presence index (Zhao et al., 2019)  T1+T2+T3 T4 . Implementation of the Linked Data
8) The time-matching level of workers and materials in one Framework
apartment was then estimated by comparing T1, T2, T3, and Our aim was to establish and develop an automated process of
T4 and their ratios: data analysis modeling where the tracking data of cross-type
• TMD (time matching for designated)  T1+T2+T3 T1
, indicating resources such as materials and labors, together with workers’
the optimum scenario of a worker and the correct material schedules, could be linked and integrated into one proposed
kit in the apartment. framework. Based on the architecture discussed in the Method
• TMA (time matching for any)  T1+T2+T3 T1+T2
, indicating the section, we then implemented the linked data framework for the
presence of a worker together with any material kit in that case study (Figure 5).
apartment.
• NM (no material)  T1+T2+T3
T3
, indicating the share of time Ontology Selection and Mapping
when the worker was present in the location without any A standard data structure was used as the basis for formalizing
material kits. and integrating the indoor positioning data. In this research, we
9) Next, we followed the linked data framework, with the aim of used the extension of digital construction ontologies (Törmä and
connecting the indoor positioning data with the external Zheng, 2020), or DiCon, for the logistics structure (Zheng et al.,
scheduling information to enable further actual and as- 2020). DiCon is a set of ontologies that may be used to define the
planned comparisons of KPI calculations: basic terminologies and relations of the digitalized construction
process. DiCon is also used to model and represent the digitalized
information obtained from the implementation of information
STMD scheduled time matching for designated and communication technologies (ICTs) in the construction
 time when workers have the assigned material domain. Using DiCon, we used classes including “person,”
under their task schedules “batches,” “location,” “sensors,” and “events” and their
uninterrupted presences of workers interrelations to represent the indoor position data in this
case. In the DiCon logistics extension, the “material kit” is
STMMscheduled time matching for material defined to represent material kits, which are groups of
 time when the material kit is in the assigned apartment material batches. The mapping of the data to DiCon and
under task schedule logistics is shown in Figure 6. For the scheduling data, the
accumulative task schedule in that apartment information of every task and its assigned location and labor

Frontiers in Built Environment | www.frontiersin.org 10 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

FIGURE 4 | STMD and STMM calculation demonstration.

FIGURE 5 | Detailed process of linked data framework implementation.

can also be represented based on DiCon. Every record of the the gateway captures the signal from the beacon. Both beacons
indoor positioning system is considered to be an “event,” which is and gateways are considered to be sensors where beacons are
observed by a beacon and a gateway during a time interval when hosted by workers and material, which are known as the instance

Frontiers in Built Environment | www.frontiersin.org 11 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

FIGURE 6 | Mapping the indoor position data to DiCon.

of “person” and “material kit” classes in the DiCon logistics tracking period. The material kit was first detected at
extension. The gateways are hosted by apartment, which is a apartment A7 at 07:03 on June 1. The material kit was then
“location.” moved to apartment A2 at 17:04 on June 17 and subsequently
moved to apartment A1 at 11:04 on June 22. Finally, the kit was
Data Conversion and Storage moved to the entry area of the building at 08:20 on June 26.
In order to establish the linked data for further data processing, the Table 4 provides a summary of the moving times of each
data and information obtained from the indoor positioning system material kit with its delivery and removal times on-site, in
and project schedule must be converted from tabular format in a addition to the schedules of task start and end times in the
spreadsheet into RDF format based on the previous result of respective apartments. Because the presence of the material kit
ontology mapping. To achieve the conversion, in this case, a for apartment A3 was not found in the system due to the loss of
Python script was developed by utilizing an open source Python the beacon attached to the kit, we decided to exclude
library called RDFlib (2009) to handle the conversion process. apartment A3 from the analysis.
After the conversion, the RDF graphs were generated and Out of a total of seven material kits, six were delivered on-
stored in the Graph DB store. Graph DB is among the most site earlier than required (the first task scheduled in the
popular RDF stores for storing and managing semantic apartment), and six were removed from the site later than
information serialized in RDF format. In the Graph DB required (the last task scheduled in the apartment). On
environment, users can also conduct SPARQL queries to average, kits were moved 6.9 times between apartments.
process, search, and retrieve information from the database. The average number of move times for the cases where kits
After the implementation of the linked data framework, we were delivered earlier than required (apartments 1, 2, 5, 6, 7,
then conducted data analysis on material flows and time- and 8) was 6.6, lower than for the kit that was delivered later
matching levels of workers and kits, with the aim of than required (apartment 4), which was moved 8 times. In our
calculating the material-related metrics introduced in the case, the delays of material kits delivered later than the first
Method section. tasks scheduled led to more movement of kits between
apartments on average. It should be noted that if the kitting
solution had worked perfectly, no movements between
RESULTS apartments would have occurred.
For the task schedule in apartment A7, the material kit for
Material Flows apartment A7 was moved away from apartment A7 at 12:43 on
Figure 7 shows an example of one material kit (assigned for June 17, but the scheduled end time of the last task in that
apartment A7) that was moved inside the building during the apartment was at 11:30 on June 22. However, after the material kit

Frontiers in Built Environment | www.frontiersin.org 12 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

FIGURE 7 | Material flow of the material kit for apartment A7 inside the building.

TABLE 4 | Moved times between apartments for each material kit.

Material kit Moved times Kit delivery Kit removal Schedule for Schedule for
for each between apts. times when times when start time end time
apartment During tracking detected 1st detected last of 1st of last
time time task in task in
(apt. #) (apt. #)

A1 kit for apartment 1 5 26-05-2018 17:20 26-06-2018 11:57 04-06-2018 07:00 (1) 22-06-2018 15:30 (1)
A2 kit for apartment 2 8 28-05-2018 13:14 25-06-2018 07:30 04-06-2018 11:30 (2) 25-06-2018 11:30 (2)
A4 kit for apartment 4 8 31-05-2018 16:50 01-07-2018 19:14 31-05-2018 11:30 (4) 21-06-2018 11:00 (4)
A5 kit for apartment 5 7 30-05-2018 11:36 27-06-2018 12:47 05-06-2018 11:30 (5) 26-06-2018 11:30 (5)
A6 kit for apartment 6 5 31-05-2018 09:22 27-06-2018 19:10 05-06-2018 07:00 (6) 25-06-2018 15:30 (6)
A7 kit for apartment 7 3 01-06-2018 07:03 27-06-2018 10:55 01-06-2018 11:30 (7) 22-06-2018 11:30 (7)
A8 kit for apartment 8 12 31-05-2018 09:09 29-06-2018 10:01 01-06-2018 07:00 (8) 21-06-2018 15:30 (8)
Average 6.9

for A7 was moved away, the material kit for A4 was moved to apartment A7, while the material kits for A4 and A7 were
apartment A7 from June 18 to June 21, which covered the detected as being present during the same tracking period of
remaining time for tasks required in the apartment. June 1 to 21. Figure 8 also shows that the worker was mostly
The material kit for A7 was observed in apartment A1 present throughout the same time range as the material kit for A7
from June 22 to June 26, which covered the remaining time in that apartment, except for his or her presence from June 18 to
for tasks required in apartment A1 after the material kit for 21, when the material kit for A7 was undetected while the
A1 had already been moved away, at 12:28 on June 18. These material kit for A4 was present. Because the task of suspended
kit movements showed that the implementation of the kitting ceiling plating was scheduled in apartment A7 starting on the
process encountered problems during this project because afternoon of June 18, the worker could have taken the suspended
the originally assigned kit could not be used to complete ceiling plates from the material kit assigned for apartment A4
the work. instead.
Table 5 summarizes the TMD, TMA, and NM results for
carpenter one and how these values were calculated in apartment
Time-Matching Level of Labor and Materials A7. Because we set the threshold of an uninterrupted presence for
in the Apartment workers at 10 min, all time intervals from workers that are shorter
Next, we calculated how the material flow interacted with the than 10 min were omitted from the analysis. The 11.1% of NM
location information of workers in the apartment. Due to space time of the assigned worker (carpenter 1) with material presence
limitations, we have visualized the results of only one apartment represents time in which the worker was detected in the
(apartment A7), and we present the results of the whole data set in apartment without any material kits being around. A few
a later section. Figure 8 shows a visualization of the carpenter in possible reasons for this situation are as follows.

Frontiers in Built Environment | www.frontiersin.org 13 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

FIGURE 8 | Movement visualization of carpenter 1 with material kits in apartment A7.

TABLE 5 | TMD, TMA, and NM results for carpenter one in apartment seven. TABLE 6 | Summary of the time-matching levels in all apartments (all numbers in
minutes except percentages).
Metrics Calculation Results
Apartment T1 T2 T3 TMD (%) TMA (%) NM (%)
T4 2,794 min
T1 242 min 1 3,534 47 20 98.1 99.4 0.6
T2 58 min 2 2,225 383 236 78.2 91.7 8.3
T3 30 min 4 604 18 46 90.4 93.2 6.8
Presence index (T1+T2+T3)/T4 11.8% 5 283 81 126 57.8 74.3 25.7
TMD T1/(T1+T2+T3) 73.4% 6 620 117 231 64.0 76.1 23.9
TMA (T1+T2)/(T1+T2+T3) 88.9% 7 1,432 363 193 72.0 90.3 9.7
NM 1-TMA 11.1% 8 181 9 73 68.7 72.1 27.9
Sum 8,879 1,018 925 82.0 91.5 8.5
SD 1,140 148 83 13.3 10.0 10.0

1) The worker was waiting for the material.


2) The worker had to retrieve the material from other places (or
parts of other kits) and then returned to do the work.
Evaluation of the Time-Matching Level in all
3) Materials were delivered as supplemental orders and were not Tracked Locations and for Different
included in the original kits. Tracked Workers
4) The worker could have been with the material kit for To determine whether the tracking of material kits and labor
apartment A3, since the movement of that kit remained together would add more insightful information to the evaluation
unknown due to the loss of the beacon for that kit. of the kitting solution on-site, we then calculated and
5) The material kit was incorrectly detected (for example, summarized the metrics, grouped by location and workers (see
because of flickering between apartments). This impact was Tables 6 and 7).
minimal, however, because during manual investigation of the Overall, 8.5% of the total uninterrupted presence of all workers
time period between June 1 and 27, from the kit being (925 min) represented the time when the workers were present
delivered to the site until its removal, we noted that only either with the A3 kit or with no material kits in the same
4.33 min of flickering (detection in different apartments) apartment. In addition, 18% of the total uninterrupted presences
occurred. Although the exact activities of the worker (1,943 min) represented the time when the workers were present
during this time were unknown, the first three points could without material kits designated for the underlying apartments.
be regarded as an indication of problems in the kitting process. The standard deviation (SD) of all apartments (except apartment
In addition, we noted two time gaps in the material kit for 3) was 10%, so we noted some locations where the kitting process
apartment A7, between June 3 and 4 and between June 13 and worked better (i.e., with a low NM value, for example 0.6% in
14. During these times, the material kit for apartment A7 was apartment 1) and some locations where workers were not using
found in A3: from 11:06 on June 3 to 6:54 on June 4, and from the kits for a large portion of time (for example apartment 8,
15:34 on June 13 to 7:10 on June 14. with 27.9%).

Frontiers in Built Environment | www.frontiersin.org 14 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

TABLE 7 | Summary of the time-matching levels for each individual worker (all numbers in minutes except percentages).

Workers Operational T1 T2 T3 Presence TMD TMA NM


time index (%) (%) (%)
(%)

Bricklayer 1 10,375 1,111 381 125 15.6 68.7 92.3 7.7


Bricklayer 2 9,539 1,785 82 93 20.5 91.1 95.2 4.8
Carpenter 1 10,938 1,135 160 209 13.7 75.5 86.1 13.9
Carpenter 2 9,391 1,107 102 193 14.9 78.9 86.3 13.7
Plasterer 1 5,737 937 85 42 18.6 88.0 96.0 4.0
Plasterer 2 6,815 1,089 98 103 18.9 84.4 92.0 8.0
Plumber 1 6,117 723 34 112 14.2 83.2 87.1 12.9
Plumber 2 6,793 993 75 48 16.4 89.0 95.7 4.3
Sum/mean 65,705 8,879 1,018 925 16.5 82.0 91.5 8.5
SD 1,928 285 101 56 2.3 7.1 4.0 4.0

Next, the time-matching level based on individual workers The first query is used to identify the uninterrupted presence
throughout their operations in all work locations was evaluated of carpenter two in apartment 7 (T1 + T2 + T3) from the
(Table 7). processed database, in which the uninterrupted presence
For the individual workers, the SD values for NM were much threshold of 10 min had already been applied. The query
smaller than for the locations. The problems with kitting seemed could thus be directly conducted to find all the records of the
to occur mostly with carpenters, while other trades showed uninterrupted presence of carpenter 2. In this query, the variables
smaller NM values. The carpenters were scheduled to do the to be explored were “?duration.” In SPARQL, SELECT is a
non-material-related task (layout) first, and then to start using the reserved function for listing all the variable results of interest
materials in the kit; therefore they may have been in work that satisfy the conditions from the WHERE section. The query
locations before the kits had arrived, thus leaving larger NM follows the logic where a worker hosts a beacon first and then the
values compared to other crews. In addition, all workers were beacon and gateway observe the event, which contains the
detected to have periods in the presence of material kits other temporal information of the presence duration. In this case,
than those that were designated, on average 9.4% of the time [T2/ we specified apartment seven and carpenter 2 as an example.
(T1 + T2 + T3)]. The results in Table 7 show an estimate of how The second query is used to find the total overlapping time of a
well the kitting solution worked for each tracked worker. worker with an apartment-assigned material kit and to check if
the worker’s presence is in the designated apartments of all
scheduled activities of carpenter 2—in other words, to identify
Estimation of Compliance With the the T1 that fits the schedule. The query follows the logic of first
Schedule searching material kits and worker temporal overlaps at
Next, SPARQL queries were used to calculate how well the designated apartments and then comparing the identified
uninterrupted presences of workers and material kits matched overlapping time to the scheduled operation time in that
with the schedule. The proposed linked data framework was used location. The logic of identifying the overlap and comparing
to create an integrated RDF graph of the linked indoor positioning the overlapping time with the schedule is based on Allen’s interval
data and the scheduling information. This section presents an algebra (Allen, 1983).
example of using SPARQL queries based on semantic logics and We conducted the third query to find the duration of the
structured data to explore the worker and material kit interaction corresponding material kit localized in the assigned apartment
performance in compliance with the schedule. In the example, the that fit the schedule. Allen’s interval algebra (Allen, 1983) was
“time matching for designated” (TMD) indices were further also used in this query to find the overlap time of the scheduled
specified to investigate the compliance with the schedules. TMD activity and material presence in the target apartment.
was further addressed as the time-matching level of a worker’s The results of the three queries were then further processed
uninterrupted presence matching the material kit assigned to a based on the principles defined in the Method section. The
specific apartment in compliance with the schedule (“scheduled accumulated results from the first query represent the
time matching for designated” [STMD]). STMD was designed to uninterrupted presence of carpenter two in apartment 7 (T1 +
identify the time of labor-material matching in the schedule-assigned T2 + T3), which is 2,233.32 min. The accumulated results from
work locations, while STMM was designed to investigate the spatial- the second query represent the total time of the labor and the
temporal metric of the material kit in compliance with the schedule. designated material kit in compliance with the schedule, which is
Due to space limitations, the STMD of carpenter two in apartment 228 min. By dividing the uninterrupted presence accumulated
seven and the STMM of the A7 material kit were selected as a case to from the result of the first query, the STMD may be calculated as
illustrate the query process. The queries were conducted in the 10.21%. The accumulated results from the third query represent
Graph DB environment. The results of the queries show the the total time of the material kit in the assigned apartment that
capability to flexibly process and retrieve meaningful information matches the scheduled tasks in that location, which is
from organized indoor positioning data formed in RDF. 2,132.27 min. By dividing the total duration of the planned

Frontiers in Built Environment | www.frontiersin.org 15 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

tasks (7,200 min) accumulated from the schedule, the STMM of based on the uninterrupted presence of workers and kits in
the A7 material kit was calculated to be 29.61%. work locations that still enables the calculation of KPIs, which
As shown in the example, calculating the STMD and STMM is can be used to evaluate logistics performance.
possible by integrating the indoor positioning data and the Our case was an apartment renovation project where small
scheduling information. The results of the STMD and STMM locations (in this case apartment bathrooms) enclosed with walls
values are an enrichment of the material-related KPIs, which can were used for analysis. Due to the project type, the accuracy and
provide further information for site managers to evaluate how the coverage values were high. In earlier research, Bluetooth-based
underlying kitting solution has worked for a specific worker (e.g., systems showed lower accuracy and coverage values in projects
carpenter 2) or the kit (e.g., the A7 material kit) against his or her with large, open areas. Kitting as a logistics solution has often
schedule. The implementation of the linked data framework also been implemented first on project types with small work areas,
provides an alternative for identifying the desired time-matching because kitting is mainly used to solve issues related to a lack of
level of workers and material kits in construction operations with space (Corakci, 2008). Large open areas typically have better
a more automated and flexible procedure. possibilities to store materials, and thus the benefits of kitting may
To summarize the results, the following outcome based on the not be so large.
proposed methods and the real-time monitoring system was Generalizability to other project types should be explored in
achieved: 1) calculated kit moving times inside the building future research. The current method depends on apartment-specific
and analysis of the material kit flows from the delivery to the material kits delivered to each work location. This type of logistics
site until the removal of the kits. 2) investigated in detail the time- enables easy tracking because tracking beacons are required only for
matching level of labor and materials in apartments, providing each kit. Although the system could, in theory, be applied for other
insights and evaluation of the tested kitting solution. 3) estimated types of materials as well, each tracked material has associated costs
level of compliance with schedule by applying the proposed in time. A typical construction site contains an enormous amount of
linked data framework to connect other external available data materials, and tagging all materials is not always practical. We
sources. Next, the discussion was presented regarding the analyzed this kitting solution in particular because of its ability to
generalizability, reliability of the system, comparison to easily map materials to locations and tasks and the low number of
previous studies, contribution to knowledge, implication and tracked elements required. Previous researchers who have
limitation as follows. investigated materials on worksites, such as Grau et al. (2009),
have taken a similar approach by focusing on individual types of
materials, although the individual materials in the kits are also of
DISCUSSION interest. In future studies, the current method could be applied on
selected individual materials to determine if their movements differ
Generalizability of the Method and the from the movements of kits.
Reliability of the System The reliability of the system depends on the following factors:
Little research to date has focused on the combination of real- 1) the tracking accuracy and coverage. In our case, the accuracy
time tracking for labor and material in construction sites for the reached 88.4% and the coverage reached 97.1%, which indicated
purposes of addressing material mishandling and evaluating high overall tracking reliability of system. 2) system
kitting solutions. In a few previous empirical works, implementation and maintenance. The system depends on
researchers have analyzed material tracking data to support assurance of gateway connectivity, power availability, and on
better material handling and site-work performance, but the workers and material kits carrying beacons at all times. In our
generalizability of their methods has varied. For instance, Grau case the beacon for the A3 kit was unfortunately lost onsite, which
et al. (2009) developed localization algorithms based on a affected the monitoring of A3 apartment.
combination of RFID and Global Positioning System (GPS) In any case, based only on the movement of tracked material
technologies to capture the time spent on activities directly kits, knowing whether a specific material part in a kit has been
related to tracked steel material components and to analyze utilized is difficult. In the future, we aim to test the performance of
the impact of the tracking application on steel erection a kitting solution by focusing on the material utilization level. For
productivity. Because GPS is unsuitable for indoor instance, the tracking method could be supplemented by vision-
environments, however, the generalizability of this method is based technology, such as by integrating a camera monitoring
limited to the outdoors. Tetik et al. (2020) evaluated the and indoor positioning system in the work location. By
applicability of kitting by comparing four projects with and implementing both vision-based technology and indoor
without kitting solutions, with a focus on the impact of work positioning, we would not need to monitor the videos all the
performance and management requirements. While they showed time but could instead shift our focus to the time period when the
that kitting solutions could improve product flow and work KPIs (e.g., NM) are alerted during the kitting process.
performance, our focus is on the effectiveness of an applied
kitting solution by showing the variability of kit presences
associated with workers in multiple work locations. Their Comparison to Project-Level Presence
method can be used to capture logistics performance on a Indices of Previous Studies
more detailed level but is not scalable due to the manual The concept of project-level presence indices was first introduced
analysis required. Our approach presents a scalable solution by Zhao et al. (2019). Such indices indicate the percentage of

Frontiers in Built Environment | www.frontiersin.org 16 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

workers’ uninterrupted presences inside their daily accumulated between workers and material kits (TMA and NM). The
operation times at the project level. This setup means that smaller the NM (or larger the TMA) value, the lower time
project-level indices only show workers’ uninterrupted disparity of workers who lack any kits.
presence values and take all workers into account. By 2) Success of having a correct kit in a work location can be
differentiating work locations and non-work locations, project- analyzed from time-matching levels between workers and the
level indices require small amounts of context information but material kits assigned to the specific apartment (TMD). A
provide important indications such as estimates of the overall larger TMD value implies that the assigned material kit with
efficiency of the worksite based on the share of workers’ actual planned material contents was more successfully adopted in
presence levels throughout a project. practice. The difference between TMA and TMD (TMA-
Compared with project-level presence indices, in the current TMD) also suggests a time level where the kits assigned to
paper the concept was expanded further by dividing indices into other apartments were occupied in the apartment when the
categories based on the time-matching of material kits. These assigned kit was absent, thus indicating potential work that
material-related uninterrupted presence metrics include TMD, workers needed to use from other apartments’ materials for
TMA, and NM, which also require tracking data from the the underlying apartment. The TMA value may indicate
material kits for each work location. A project-level presence problems with the bill of materials used to assemble the kit
index is a metric of operations flow at the project level. Therefore, and will likely rise as a result of incorrect quantities or kinds of
the material-related uninterrupted presence uses the resource materials in the kits.
flows from both material and labor perspectives, which creates 3) Success of following the original work plan can be analyzed
opportunities to evaluate the current material management from time-matching levels between workers with material kits
practice (in this case, the kitting solution). For instance, in the under their original schedules (STMD and STMM). Larger
current case, the overall project-level presence index was 16.5%, STMD or STMM values imply that workers are spending time
which was lower than in previous studies with the same threshold with material kits in work locations following the original
value (Zhao et al., 2019). The index also indicates that 83.5% of plans. This information could be particularly valuable in
the time, the worker was either undetected inside the building or projects that use, for example, the takt production concept,
was detected at one location for less than 10 min. Additionally, in where the schedule is committed and followed (Frandson and
our case the tracked material kits were not always at the Tommelein, 2014).
designated location, and the workers were not always present 4) Unnecessary inventory can be calculated from the detected
with the correct kit in the apartment. delivery time of material kits compared with the time when
The current research extends the research conducted by Zhao the first task requires the material in that kit. The lower the
et al. (2019) by investigating also material flows which have not time gap between these two times, the less waiting or delays of
been addressed in their previous studies. Zhao et al. (2019) the material to be used will occur. Unnecessary inventory is
assessed an overall percentage of workers’ uninterrupted one waste type related to materials, and kitting practice is
presence level for all workers in the project during the typically planned to be JIT (Tetik et al., 2020; Tommelein and
tracking period. This kind of project-level indices cannot be Li, 1999).
used to understand root causes of problems to inform 5) Wasted time for moving of materials can be analyzed from the
improvement interventions. The project-level presence indices moving times of material kits between work locations. With
reflect on the productivity level of the entire project but do not more detected moving times of material kits, workers
include connections to task schedule or other site data sources. unavoidably waste more time transporting kits to the
The measurement of labor and material kit integrated required apartments. In an optimally working kitting
uninterrupted presence creates some new and deeper analysis process, only one movement of the kit to its location, and
opportunities. The efficiency of the logistic system can be then one movement out, should occur once all materials have
analyzed by looking at materials and labor together in been consumed.
connection with the schedule. For that purpose, our study
introduces new material-related metrics which can be used to In summary, we argue that a well-performing kitting solution
provide supplemental information on top of the project-level should have 1) high TMA and TMD values, 2) ideally little
uninterrupted presence indices. Therefore, the key motivation of difference between TMA and TMD values, and 3) no kit
this research was to broaden the knowledge of previous studies movements between work locations. If scheduling information
toward material management practices. is taken into consideration, then a good performance should also
Overall, presence indices, which also consider material flows, require high STMD and STMM values with the least possible time
provide a deeper understanding of production performance than gap between detected delivery times and task schedules required
those indices that rely only on the tracking systems of workers’ for the underlying material kits.
location. In addition to project-level presence indices, the several
metrics can be used to evaluate the kitting logistics solution from Contributions to Current Knowledge
the following perspectives. In the current paper, we contribute to tracking methods in
construction by developing and demonstrating a method to
1) Waiting or other non-value-adding time spent in work manage kit-based logistics management using an indoor real-
locations can be analyzed from time-matching levels time tracking system to monitor both material and worker flows.

Frontiers in Built Environment | www.frontiersin.org 17 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

More specifically, the tracking method is developed to integrate special attention to the task progress in apartment A8. Faulty
material kit and labor tracking for a kitting logistics solution in a amounts or kinds of materials for that apartment likely
scalable way by measuring the uninterrupted presences of both explained these issues.
labor and material kits. Second, for logistics providers, the automated detected
One of the specific contributions to the methods based on the timestamps of kit delivery and removal in/out from the
presence of materials and workers in work locations is that the work locations, and the value difference between TMA and
developed method does not require manual observation or TMD, can provide useful information about the correctness
watching through camera videos to understand the process. and punctuality of kit deliveries. If TMA is equal to TMD,
For example, using camera monitoring and manual then all assigned material kits have been correctly placed in
observations, Tetik et al. (2020) pointed out that the effects of the apartments, and no other material kits are needed for
random factors may be large due to a relatively small data set. Our replacement. Logistics providers can use the information of
method does not rely on manual analysis and thus is scalable to kit delivery and removal to estimate approximate kit usage
large data sets, which will help to avoid random factors. using cycle times in each work location. They can also
In addition to the methodological development, the contribution estimate the right quantity and correct size of kits to be
to construction management lies in the introduction and delivered to the assigned apartment. Based on real-time data
demonstration of several KPIs to evaluate the effectiveness of the logistics, providers can dynamically update kit delivery plans
kitting solution. When the kitting process works in an optimal way, it and executions to the site (Kalsaas et al., 2014).
fulfills the following requirements: 1) kits only go to the right Third, for task schedulers, the study will provide practical KPIs
apartment, 2) kits only move in once and out once, and 3) for evaluating and continuously improving their processes.
workers are present in the planned work location with the correct STMD can be used to evaluate the compliance levels of
kit. The results have shown that none of the requirements were met in workers with the assigned material kits in apartments, while
the project we tested, so the implemented kitting practice was far from STMM can be used to evaluate the share of time when the
optimal. Calculating these KPIs in real time could allow management material kit is placed elsewhere under the task schedule.
to find the root causes of problems and to continuously improve on In summary, our research has introduced these KPI metrics to
material logistic solutions. Such a system could be seen as a digital twin enable real-time monitoring for detecting problems in kitting
of the logistics process and could drive improvement in the way that practices in work locations. These metrics can potentially benefit
Sacks et al. (2020) proposed in their recent paper on digital twin logistics providers, site managers, and schedule planners. Lean
construction. interventions should be undertaken accordingly if the problems
In the current paper, the existing knowledge was also appear to be continuous, as indicated by the KPIs.
contributed on data linkages in construction projects by we The linked data method also provides the opportunity to align
investigating the labor-material interaction in compliance with heterogenous data sets from various domains or systems with the
operation schedules. By applying the linked data method, we indoor position tracking system. With linked data sets, more
introduced a novel approach to integrating heterogenous data applications can be used based on indoor positioning than just
from both positioning tracking and schedules. With our KPI identification. For example, by combining real-time indoor
introduction of the linked data approach, the cross-type positioning tracking with building information modeling (BIM),
resource data in construction becomes linked and machine- users can gain a prompt and direct visual-based awareness of the
readable, which provides easy utilization of semantics for KPI on-site work situation and thus can flexibly adjust and control the
calculations and the ability to conduct analyses without on-site work to improve productivity.
fragmentary raw data processing. The integrated data enables Overall, we have shown that waste is a problem with flows
the evaluation of the effectiveness of kitting solutions compared during value-adding activities on-site rather than being caused
to the plans, which cannot be achieved by individual data only by a single worker or by individual materials being
streams alone. misplaced. The use of presence information from both
workers and materials can offer simple KPIs that can act as
Managerial Implications proxies for waste indication—for instance, to evaluate how much
This work has several managerial implications for operations the presence of workers and material kits would be affected by JIT
management in construction based on the proposed tracking logistics (e.g., kitting practice) in different projects.
application framework. First, the proposed system and KPIs
can help site managers to understand how well the applied Limitations
kitting solution performs. For instance, the disparity from the The current research does have a few limitations. One of the main
optimal situation quantified by NM can be used to indicate limitations of this method may be described as identification issues of
the amount of time when workers are present without any materials and kits. Based on the real-time tracking system used in this
materials. Managers can use the method and KPIs when case, which showed satisfactory coverage (97.1%) and accuracy
reallocating working resources to those places where the (88.4%), we saw relatively good results from worker and material
kitting practice appears to have the most challenges. For timestamps to reduce resource flows on-site. We were unable to
example, our case apartment A8 was found to be the most identify the presence of specific materials in the kits, however, because
complex work location with the highest NM and kit-moving we only placed beacons to monitor the kits in our study. In future
times, which should urge the site managers in this case to pay studies, we propose to add features such as sending notices to workers

Frontiers in Built Environment | www.frontiersin.org 18 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

for simple confirmation of their current activities (such as waiting for occurred in work locations in which workers were without
materials, idle status, etc.) when the TMA degree appears to decrease kits on-site. The variability of these durations in different
during the day. In this way, sorting through all uninterrupted worker places should be noted for managing kitting solution
presences to search for time durations could be avoided, which hinders practices.
the effectiveness of the kitting solution. We would also be able to learn Compared to tracking for workers only, the information in
the actual reasons for better effectiveness from workers’ direct this work consists of the integration of labor and material
confirmations. tracking and the evaluation of current kitting logistic
Another limitation is that one beacon for the A3 kit was lost solutions based on overlapping times of workers and kits.
onsite, so the NM periods may have included times in which The current method works by revealing the observed
workers were actually with the A3 kit, thus making the actual NM problems of kitting practices in real time, thus providing
smaller. In this case, some indication of the effectiveness of the lean intervention opportunities for material-labor-related
underlying kitting practice could still be obtained by examining tasks on-site. Users can also evaluate the effectiveness of
the value of TMD and checking on a worker’s status with the the kitting practice in work locations based on the metrics
correct material kits in an apartment (i.e., the designated kits). For introduced in this paper. We aim to establish a linked data
future study, beacons will be tagged with the material kits all the model that could be used to connect heterogeneous
time during the tracking periods. information of cross-type resources (such as labor and
In this research, Linked data method was implemented to materials) and their schedules from external sources in
integrate the heterogeneous indoor positioning and the operation construction so that an automated data analysis for
schedule information. Such integration combines data sources proposed KPIs (such as STMD and STMM) could be
from different systems, and further enables the calculation of the executed smoothly for site managers’ decision-making in
KPIs with schedule compliance (STMD and STMA) that cannot the future.
be achieved with solo data streams based on previous methods.
However, in this research only these two data sources were
obtained, which means that only STMD and STMA can be DATA AVAILABILITY STATEMENT
calculated. If more types of data sources could be acquired,
more potential KPIs could be also calculated. For example, if The raw data supporting the conclusions of this article can be
the BIM model of the project could also be obtained, it is possible made available by the authors upon request.
to use the BIM quantity takeoff to calculate the workload of each
task in the schedule, and further to calculate the work efficiency of
each task. In the future research, the goal is to collect AUTHOR CONTRIBUTIONS
comprehensive digitalized data from one construction project
and integrate all digital data sources and develop more accurate Conceptualization, JZ, YZ, OS, and AP; Methodology, JZ and YZ;
KPIs to represent the construction productivity. Data Collection, JZ; Data Analysis, JZ and YZ; Writing—original
draft, JZ; Writing—review and editing, JZ, YZ, OS, MT, and AP;
Funding acquisition, OS.
CONCLUSION
In this paper, we have illustrated how our proposed real-time FUNDING
tracking system and linked data framework were applied in
an indoor bathroom renovation construction project for the This work was supported by the Intelligent Construction Site
automated detection and analysis of time-matching levels of (iCONS) research project (Grant No. 2819/31/2016) and the
material kits and workers based on their uninterrupted Digitalizing Construction Workflows (DiCtion) research
presence. New KPIs were developed that can be measured project (Grant No. 2758/31/2017) funded by the Business
in real time and offer opportunities to improve material and Finland, Aalto University, and a consortium of companies. In
labor flows for kitting logistics solutions based on the addition, the research was partially supported by the Building
proposed metrics. We have learned that notable durations 2030 consortium of Aalto University and 21 companies.

Asadi, K., Ramshankar, H., Noghabaei, M., and Han, K. (2019). Real-time Image
REFERENCES Localization and Registration with BIM Using Perspective Alignment for
Indoor Monitoring of Construction. J. Comput. Civ. Eng. 33 (5), 04019031.
Allen, J. F. (1983). Maintaining Knowledge about Temporal Intervals. Commun. doi:10.1061/(ASCE)CP.1943-5487.0000847
ACM 26, 832–843. doi:10.1145/182.358434 Bizer, C., Heath, T., and Berners-Lee, T. (2009). Linked Data - the Story So Far. Int.
Angah, O., and Chen, A. Y. (2020). Tracking Multiple Construction Workers J. Sem. Web Inform. Sys. 5 (3), 1–22. doi:10.4018/jswis.2009081901
through Deep Learning and the Gradient Based Method with Re-matching Bizer, C., and Schultz, A. (2009). The Berlin SPARQL Benchmark. Int. J. Sem. Web
Based on Multi-Object Tracking Accuracy. Automation in Construction 119, Inf. Syst. 5 (2), 1–24. doi:10.4018/jswis.2009040101
103308. doi:10.1016/j.autcon.2020.103308 Bozer, Y. A., and McGinnis, L. F. (1992). Kitting versus Line Stocking: a Conceptual
Arbulu, R., and Ballard, G. (2004). “Lean Supply Systems in Construction,” in Proc. Framework and a Descriptive Model. Int. J. Prod. Econ. 28 (1), 1–19.
12th Ann. Conf. Int. Group Lean Const. (Copenhagen, Denmark: IGLC-12). doi:10.1016/0925-5273(92)90109-k

Frontiers in Built Environment | www.frontiersin.org 19 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

Cai, J., and Cai, H. (2020). Robust Hybrid Approach of Vision-Based Tracking and Li, C. T., Cheng, J. C. P., and Chen, K. (2020). Top 10 Technologies for Indoor
Radio-Based Identification and Localization for 3D Tracking of Multiple Positioning on Construction Sites. Automation in Construction 118, 103309.
Construction Workers. J. Comput. Civ. Eng. 34 (4), 04020021. doi:10.1061/ doi:10.1016/j.autcon.2020.103309
(asce)cp.1943-5487.0000901 Luo, X., Li, H., Cao, D., Yu, Y., Yang, X., and Huang, T. (2018). Towards Efficient
Cai, J., Zhang, Y., and Cai, H. (2019). Two-step Long Short-Term Memory Method and Objective Work Sampling: Recognizing Workers’ Activities in Site
for Identifying Construction Activities through Positional and Attentional Surveillance Videos with Two-Stream Convolutional Networks. Automation
Cues. Automation in Construction 106, 102886. doi:10.1016/ in Construction 94, 360–370. doi:10.1016/j.autcon.2018.07.011
j.autcon.2019.102886 Nasir, H., Haas, C. T., Young, D. A., Razavi, S. N., Caldas, C., and Goodrum, P.
Caldas, C. H., Torrent, D. G., and Haas, C. T. (2006). Using Global Positioning (2010). An Implementation Model for Automated Construction Materials
System to Improve Materials-Locating Processes on Industrial Projects. Tracking and Locating. Can. J. Civ. Eng. 37 (4), 588–599. doi:10.1139/l09-178
J. Constr. Eng. Manage. 132 (7), 741–749. doi:10.1061/(asce)0733- Olivieri, H., Seppänen, O., and Peltokorpi, A. (2017). “Real-time Tracking of
9364(2006)132:7(741) Production Control: Requirements and Solutions,” in Proc. 25th Ann. Conf.
Chen, Q., Adey, B. T., Haas, C., and Hall, D. M. (2020). Using Look-Ahead Plans to Int. Group Lean Const. (Heraklion, Greece: IGLC-25), 671–678. doi:10.24928/
Improve Material Flow Processes on Construction Projects when Using BIM 2017/0177
and RFID Technologies. Ci 20, 471–508. doi:10.1108/CI-11-2019-0133 Park, J., Kim, K., and Cho, Y. K. (2017). Framework of Automated Construction-
Corakci, M. A. (2008). An Evaluation of Kitting Systems in Lean Production. Borås, Safety Monitoring Using Cloud-Enabled BIM and BLE mobile Tracking
Sweden: Master’s thesis, University College of Borås School of Engineering. Sensors. J. Const. Eng. Man. 143 (2), 5016019. doi:10.1061/(ASCE)CO.1943-
Costin, A., Pradhananga, N., and Teizer, J. (2012). Leveraging Passive RFID 7862.0001223
Technology for Construction Resource Field Mobility and Status Park, J., Marks, E., Cho, Y. K., and Suryanto, W. (2016). Performance Test of
Monitoring in a High-Rise Renovation Project. Automation in Construction Wireless Technologies for Personnel and Equipment Proximity Sensing in
24, 1–15. doi:10.1016/j.autcon.2012.02.015 Work Zones. J. Const. Eng. Man. 142 (1), 4015049. doi:10.1061/(ASCE)
Curry, E., O’Donnell, J., Corry, E., Hasan, S., Keane, M., and O’Riain, S. (2013). CO.1943-7862.0001031
Linking Building Data in the Cloud: Integrating Cross-Domain Building Data Pauwels, P., Törmä, S., Beetz, J., Weise, M., and Liebich, T. (2015). Linked Data in
Using Linked Data. Adv. Eng. Inform. 27 (2), 206–219. doi:10.1016/ Architecture and Construction. Automation in Construction 57, 175–177.
j.aei.2012.10.003 doi:10.1016/j.autcon.2015.06.007
Dror, E., Zhao, J., Sacks, R., and Seppänen, O. (2019). “Indoor Tracking of Peffers, K., Tuunanen, T., Rothenberger, M. A., and Chatterjee, S. (2007). A Design
Construction Workers Using BLE: mobile Beacons and Fixed Gateways vs. Science Research Methodology for Information Systems Research. J. Manag.
Fixed Beacons and mobile Gateways,” in Proc. 27th Ann. Conf. Int. Group Lean Inf. Syst. 24 (3), 45–77. doi:10.2753/MIS0742-1222240302
Const. (Dublin, Ireland: IGLC-27). doi:10.24928/2019/0154 RDFlib (2009). Documentation. Retrieved from: https://rdflib.readthedocs.io/en/
Ergen, E., Akinci, B., East, B., and Kirby, J. (2007). Tracking Components and stable/.
Maintenance History within a Facility Utilizing Radio Frequency Identification Ryu, J., Seo, J., Jebelli, H., and Lee, S. (2019). Automated Action Recognition Using
Technology. J. Comput. Civ. Eng. 21 (1), 11–20. doi:10.1061/(asce)0887- an Accelerometer-Embedded Wristband-type Activity Tracker. J. Constr. Eng.
3801(2007)21:1(11) Manage. 145 (1), 04018114. doi:10.1061/(ASCE)CO.1943-7862.0001579
Frandson, A., and Tommelein, I. D. (2014). Development of a Takt-Time Plan: a Sacks, R., Brilakis, I., Pikas, E., Xie, H. S., and Girolami, M. (2020). Construction
Case Study. Const. Res. Cong. 2014, 1646–1655. doi:10.1061/ with Digital Twin Information Systems. Data-cent. Eng. 1, 1. doi:10.1017/
9780784413517.168 dce.2020.16
Grau, D., Caldas, C. H., Haas, C. T., Goodrum, P. M., and Gong, J. (2009). Sacks, R., Radosavljevic, M., and Barak, R. (2010). Requirements for Building
Assessing the Impact of Materials Tracking Technologies on Construction Information Modeling Based Lean Production Management Systems for
Craft Productivity. Automation in Construction 18 (7), 903–911. doi:10.1016/ Construction. Automation in Construction 19 (5), 641–655. doi:10.1016/
j.autcon.2009.04.001 j.autcon.2010.02.010
Gurmu, A. T. (2019). Tools for Measuring Construction Materials Management Seppänen, O., Ballard, G., and Pesonen, S. (2010). The Combination of Last Planner
Practices and Predicting Labor Productivity in Multistory Building Projects. System and Location-Based Management System. Lean Const. J. 2010, 43–54.
J. Constr. Eng. Manage. 145 (2), 04018139. doi:10.1061/(asce)co.1943- Seppänen, O., and Peltokorpi, A. (2016). “A New Model for Construction Material
7862.0001611 Logistics: from Local Optimization of Logistics towards Global Optimization of
Guven, G., and Ergen, E. (2021). Tracking Major Resources for Automated On-Site Production System,” in 24th Ann. Conf. Int. Group Lean Const.
Progress Monitoring of Construction Activities: Masonry Work Case. (Boston, MA, USA: IGLC-24), 73–82.
Construction Innovation ahead-of-print, 1471–4175. doi:10.1108/CI-05-2020- Teizer, J., Neve, H., Li, H., Wandahl, S., König, J., Ochner, B., et al. (2020).
0081 Construction Resource Efficiency Improvement by Long Range Wide Area
Hamzeh, F. R., Tommelein, I. D., Ballard, G., and Kaminsky, P. (2007). “Logistics Network Tracking and Monitoring. Automation in Construction 116, 103245.
Centers to Support Project-Based Production in the Construction Industry,” in doi:10.1016/j.autcon.2020.103245
Proc. 15th Ann. Conf. Int. Group Lean Const. (East Lansing, MI, USA: IGLC- Tetik, M., Peltokorpi, A., Seppänen, O., Leväniemi, M., and Holmström, J. (2020).
15), 181–191. Kitting Logistics Solution for Improving On-Site Work Performance in
Hanson, R., and Medbo, L. (2012). Kitting and Time Efficiency in Manual Construction Projects. J. Const. Eng. Man. 147 (1), 05020020. doi:10.1061/
Assembly. Int. J. Prod. Res. 50 (4), 1115–1125. doi:10.1080/ (ASCE)CO.1943-7862.0001921
00207543.2011.555786 Thomas, H. R., Horman, M. J., de Souza, U. E. L., and Zavřski, I. (2002). Reducing
Ju, Y., Kim, C., and Kim, H. (2012). RFID and CCTV-Based Material Delivery Variability to Improve Performance as a Lean Construction Principle. J. Constr. Eng.
Monitoring for cable-stayed Bridge Construction. J. Comput. Civ. Eng. 26 (2), Manage. 128 (2), 144–154. doi:10.1061/(ASCE)0733-9364(2002)128:2(144)
183–190. doi:10.1061/(asce)cp.1943-5487.0000134 Tommelein, I. D., and Li, A. (1999). “Just-in-time concrete Delivery: Mapping
Kalsaas, B. T., Gundersen, M., Berge, T. O., Koskela, L., and Saurin, T. A. (2014). Alternatives for Vertical Supply Chain Integration,” in Proc. 7th Ann. Conf. Int.
“To Measure Workflow and Waste: a Concept for Continuous Improvement,” Group Lean Const. (Berkeley, CA, USA: IGLC-7), 97–108.
in 22nd Ann. Conf. Int. Group Lean Const. (Oslo, Norway: IGLC-22), 835–846. Törmä, S., and Zheng, Y. (2020). Digital Construction Ontologies. Retrieved from:
Kim, D., Liu, M., Lee, S., and Kamat, V. R. (2019). Remote Proximity Monitoring https://w3id.org/digitalconstruction (Accessed November 15, 2020).
between mobile Construction Resources Using Camera-Mounted UAVs. Wu, C., Wang, X., Chen, M., and Kim, M. J. (2019). Differential Received Signal
Automation in Construction 99, 168–182. doi:10.1016/j.autcon.2018.12.014 Strength Based RFID Positioning for Construction Equipment Tracking. Adv.
Lee, D.-Y., Chi, H.-l., Wang, J., Wang, X., and Park, C.-S. (2016). A Linked Data Eng. Inform. 42, 100960. doi:10.1016/j.aei.2019.100960
System Framework for Sharing Construction Defect Information Using Yang, X., Yu, Y., Shirowzhan, S., sepasgozar, S., and Li, H. (2020). Automated PPE-
Ontologies and BIM Environments. Automation in Construction 68, Tool Pair Check System for Construction Safety Using Smart IoT. J. Building
102–113. doi:10.1016/j.autcon.2016.05.003 Eng. 32, 101721. doi:10.1016/j.jobe.2020.101721

Frontiers in Built Environment | www.frontiersin.org 20 September 2021 | Volume 7 | Article 713976


Zhao et al. Labor-Material Tracking in Kitting

Zhang, B., Zhu, Z., Hammad, A., and Aly, W. (2018). Automatic Matching of Industry,” in 37th Int. Symp. Autom. Rob. Const. (Kitakyushu, Japan:
Construction Onsite Resources under Camera Views. Automation in ISARC 2020), 1278–1285. doi:10.22260/ISARC2020/0175
Construction 91, 206–215. doi:10.1016/j.autcon.2018.03.011
Zhang, S., Shang, C., Fang, X., He, S., Yu, L., Wang, C., et al. (2021). Wireless Conflict of Interest: The authors declare that the research was conducted in the
Monitoring-Based Real-Time Analysis and Early-Warning Safety System for absence of any commercial or financial relationships that could be construed as a
Deep and Large Underground Caverns. J. Perform. Constr. Facil. 35 (2), potential conflict of interest.
04020147. doi:10.1061/(ASCE)CF.1943-5509.0001534
Zhao, J., Olivieri, H., Seppänen, O., Peltokorpi, A., Badihi, B., and Lundstrom, P. Publisher’s Note: All claims expressed in this article are solely those of the authors
(2017). “Data Analysis on Applying Real Time Tracking in Production Control and do not necessarily represent those of their affiliated organizations, or those of
of Construction,” in 2017 IEEE Int. Conf. Ind. Eng. And Eng. Man. (Banff, AB, the publisher, the editors and the reviewers. Any product that may be evaluated in
Canada: IEEM), 573–577. doi:10.1109/IEEM.2017.8289956 this article, or claim that may be made by its manufacturer, is not guaranteed or
Zhao, J., Seppänen, O., Peltokorpi, A., Badihi, B., and Olivieri, H. (2019). Real- endorsed by the publisher.
time Resource Tracking for Analyzing Value-Adding Time in
Construction. Automation in Construction 104, 52–65. doi:10.1016/ Copyright © 2021 Zhao, Zheng, Seppänen, Tetik and Peltokorpi. This is an open-
j.autcon.2019.04.003 access article distributed under the terms of the Creative Commons Attribution
Zhao, J., Pikas, E., Seppänen, O., and Peltokorpi, A. (2021). Using Real-Time License (CC BY). The use, distribution or reproduction in other forums is permitted,
Indoor Resource Positioning to Track the Progress of Tasks in Construction provided the original author(s) and the copyright owner(s) are credited and that the
Sites. Front. Built Environ 7, 661166. doi:10.3389/fbuil.2021.661166 original publication in this journal is cited, in accordance with accepted academic
Zheng, Y., Tetik, M., Törmä, S., Peltokorpi, A., and Seppänen, O. (2020). “A Shared practice. No use, distribution or reproduction is permitted which does not comply
Ontology for Logistics Information Management in the Construction with these terms.

Frontiers in Built Environment | www.frontiersin.org 21 September 2021 | Volume 7 | Article 713976

You might also like