ID Task Name Duration Work Predecessors Resource Names Total Slack Cost Fixed Cost

1 PROJECT 59.82 days 3,395.34 ... Core team 0 days €91,075.... €0.00
2 1 - Initial planning 5.56 days 120 hrs Alfredo[90%],António,Susana[80%] 2.44 days €0.00 €0.00
3 2 - Accreditation 3.89 days 56 hrs 2 Lívio,Pedro[80%] 23.56 days €1,543.11 €0.00
4 3 - Marketing plan 12.47 days 160 hrs 2 António,Susana[80%] 4.64 days €0.00 €0.00
5 4 - Sponsorship 13.33 days 192 hrs 2 Lucinda[80%],Marco 1.33 days €4,224.00 €0.00
6 5 - Financial planning 7 days 128 hrs 4,5 António,Félix,João 0 days €2,346.67 €0.00
7 6 - Venue plan 9.63 days 208 hrs 6,3 Alfredo[90%],Susana[80%],Teodoro 4.41 days €1,078.51 €0.00
8 7 - Logistics 23.13 days 480 hrs 6 Félix,Guilherme,Marco,Paulo 0 days €14,481.... €0.00
9 8 - Protocol preparation 14 days 336 hrs 6 Alexandre,João,Ana 12.38 days €10,528.... €0.00
10 9 - Communication plan 5.17 days 120 hrs 5 Alfredo[90%],Teodoro,Marco 21.49 days €1,489.66 €0.00
11 10 - TV Broadcasting 5.56 days 80 hrs 7,10 Susana[80%],António 5.57 days €0.00 €0.00
12 11 - Risk & Contingency plan
21 days 176 hrs 2 Pedro[80%],Lívio 2.56 days €4,928.00 €0.00
13 12 - Medical Service 5.63 days 144 hrs 6 Susana[80%],Alfredo[90%],Lucinda[80%],Lucas[70%]
14.04 days €1,359.00 €0.00
Deployment
14 13 - Transport 14.19 days 352 hrs 12 Lucinda[80%],Lívio,Pedro[80%],Lucas[70%] 3.78 days €8,516.13 €0.00
15 14 - Equipment 2.78 days 40 hrs 8,13,14 António,Susana[80%] 0 days €0.00 €0.00
Deployment
16 15 - Service Test 3.1 days 72 hrs 9,11,15 Alfredo[90%],António,Guilherme 0 days €645.54 €0.00
17 16 - Documentation 15.13 days 176 hrs 3 Alfredo[90%],Guilherme 26.79 days €2,408.42 €0.00
18 17 - Official Approval 2 days 76.8 hrs 16,17 Alexandre,Ana,Félix,Teodoro,Horácio[80%] 0 days €2,019.20 €0.00