0.5
NVA but cannot be eliminated
0.5
Value Added Activity 5
Value Added Activity 5
Patient can keep the sample on Pneumatic
Automate 0.5
conveyor for transporting it to cold storage
Eliminate
Eliminate
27
27
Single time gunning
Time Consumed
Sl. No. Activity
(Minutes)
1 Entry & Parking of Torpedo ladle in Gunning Yard 5
2 Scheduled Electrical Maintenance Job 45
Mouth Cleaning by Gradall Machine & Torpedo De-
3 slagging 32
Removal of slag at bottom of torpedo by Gradall
4A m/c 13
Opening machine top cover & feeding with
4B monolithic powder 27
5 Gunning on one side 15
6 Settling down time for gunning material 11
7 gunning activity on another side 5
8 pipe removal and valve closing 3
Type of Waste