You are on page 1of 17

By Mohammad Shahidehpour

and Mohammad E. Khodayar

IIT logo courtesy of the Illinois Institute of Technology


Cutting Campus
Energy Costs with
Hierarchical Control
The economical and reliable operation
of a microgrid.

ith the introduction of the smart quency and voltage support, active and reactive power con-

W
grid, there is an intense interest in the inte- trol, and better energy management through storage tech-
gration of intelligent and flexible microgrids nologies. The proximity of power generation to microgrid
in large-scale power systems. Microgrids consumptions could result in improved power quality,
would be operated locally in grid-connected lower power losses, better voltage stability, and higher reli-
and island modes and can provide black start operation, fre- ability (fewer customer outages) by engaging fewer compo-
nents and eliminating additional transmission services.
Distributed energy resources (DERs), which include distrib-
uted generation (DG), distributed storage, and adjustable
Digital Object Identifier 10.1109/MELE.2013.2273994
Date of publication: 23 October 2013 load, are a key component in microgrid operations.

40 I EEE E l e c t r i f i c a t i on M a gaz ine / september 2013 2325-5987/13/$31.00©2013IEEE


Microgrids could be clustered at distribution levels to Avenue on the east, 29th/30th Street on the north, and the
enhance the economics and the reliability of small DGs Metra Rock Island train line on the west. Starting with the
such as microturbines and wind-generation turbines as campus substations, IIT owns, manages, and operates its
well as DGs with power electronic (PE) interfaces such as underground electricity distribution system. A cross-tie
photovoltaic (PV) arrays and fuel cells. PE interfaces are fast, feeder between the substations allows for the seamless
enabling full control of transients by introducing virtual operation of the microgrid in the case of a utility grid fail-
inertia implemented through control loops known as ure in the shared feeder or one of the individual feeders in
droops. The implementation of droops would enable adjust- the North or the South Substation. The on-site generation
ments in frequency and voltage, which are in proportion to can also feed the northern part of the campus through the
real and reactive power at converter terminals. Microgrids cross-tie between the North and the South Substations.
use small generators with low or no i­nertia, which are In the decade preceding the implementation of the IIT
mostly equipped with PE interfaces in resistive networks, microgrid, the university experienced several outages
whereas the utility grid includes large synchronous within the campus infrastructure and the utility feeders,
machines with high inertias and an inductive network. which resulted in partial or complete loss of loads in
The microgrid control architectures are offered in grid- buildings and research facilities. Several campus buildings
connected and island modes. Microgrids use two control lost power, including laboratories, resulting in the loss of
architectures: multiagent system control and hierarchical experimental data and subjects. The substantial annual
control. The multiagent control system provides genera- loss of revenue as a result of the outages included the
tion unit autonomy, reduces large data manipulation, and replacement costs of damaged equipment due to
increases the control system reliability; however, the ­undervoltage or ­unbalanced voltages (campus facilities as
implementation would require a more complicated con- well as laboratories), the personnel and administrative
trol infrastructure, which is not recommended for indus- costs of restoring and sustaining research and educational
trial applications. The hierarchical control of microgrids experiments, and the cost and aggravation associated
includes primary-, secondary-, and tertiary-level opera- with disrupted academic classes and laboratories and any
tions. The primary control would share the load among other major campus events such as open houses and con-
DER units using droops while eliminating circulating cur- ferences that were interrupted by the outages.
rents. The secondary control would eliminate steady-state The IIT microgrid, funded mostly by a grant from the
errors imposed by primary control. The tertiary control U.S. Department of Energy, empowers the campus con-
would ensure the economical and secure operation of the sumers with the objective of establishing a microgrid that
microgrid and manage the microgrid’s energy imports/ is economically viable, environmentally friendly, fuel effi-
exports with the utility grid. The hierarchical control of cient, robust, and resilient with a self-healing capability.
microgrids would minimize operation costs and increase The IIT microgrid enhances its operation reliability by
the microgrid reliability and enhance the dynamic perfor- applying a real-time reconfiguration of power distribution
mance of a highly nonlinear system through various con- assets, real-time islanding of critical loads, and real-time
trol strategies. The hierarchical control of islanded optimization of power supply resources.
microgrids would use existing DERs for regulating the sys-
tem frequency in different time spans. In addition, using Objectives for Establishing a Microgrid
microgrids would reduce communication requirements The IIT microgrid is powered by a master controller, which
among local DER units. offers the opportunity to eliminate costly outages and
In this article, we discuss microgrid objectives and power disturbances, supply the hourly campus load pro-
present options for microgrid operations and their mon- file, reduce daily peak loads, and mitigate greenhouse gas
itoring and control in the context of a functional system production. The distribution system topology consists of
at the Illinois Institute of Technology (IIT) in Chicago. several loops, which provide redundant electricity supply
The microgrid represents a multitier hierarchical con- to the end consumers. The IIT microgrid would specifically:
trol of self-sustaining energy infrastructure with island- xx demonstrate the higher reliability introduced by the
ing and resynchronization, self-healing, and demand microgrid system at IIT
response capabilities. The intelligent high-reliability dis- xx demonstrate the economics of microgrid operations
tribution system (HRDS) at IIT is equipped with phasor xx allow for a decrease of 50% of the grid electricity load
measurement units (PMUs) for real-time monitoring, xx create a permanent 20% decrease in the peak load
nondispatchable renewable energy production, as well from the 2007 level
as conventional and dispatchable energy resources. xx defer a planned substation through load reduction
xx offer a distributed system design that can be repli-
Status of a Typical Distribution Network cated in urban communities.
at a University Campus The criteria for achieving these objectives are short-term
IIT is located approximately 2.5 mi south of downtown reliability and economical operation. Figure 1 shows the
Chicago, bounded by 35th Street on the south, Michigan microgrid elements, functions, and control tasks a ­ ssociated

IEEE Elec trific ation Magazine / s ep t emb er 201 3 41


with each criterion. To achieve the optimal economics, ­Figure 3 shows the full-scale model of the natural-gas tur-
microgrids apply coordination with the utility grid and eco- bine generator located at the IIT campus.
nomical demand response in island mode. The short-term
reliability at load points would consider microgrid islanding Solar PV Generation
and resynchronization and apply emergency demand A total of 140 kW of solar PV cells are installed on three
response and self-healing in case of outages. building rooftops, including a 20-kW solar canopy (shown
in Figure 4) installed at the electric vehicle charging station
Campus Microgrid Components to supply portions of the IIT campus load. The solar PV
In this section, the components of the IIT microgrid, includ- units are not dispatchable and use the maximum power
ing DERs, HRDS switches, meters and PMUs, and building point tracking (MPPT) control system shown in Figure 5 to
controllers, are introduced. DER units include ­dispatchable maximize the solar power output for a given insolation. A
units such as natural-gas turbine generator and battery solar PV cell is a controlled-current source with a nonlinear
storage units, and nondispatchable units such as solar PV ­current–voltage relationship corresponding to a given inso-
and wind turbine units. The storage unit includes a flow lation and temperature. Generally, as the solar PV cell volt-
battery and several lead-acid batteries. Building controllers age increases, its output current will decrease. To achieve
would provide control and monitoring functions for build- the highest efficiency and capture maximum solar energy,
ing loads on campus. Figure 2 depicts the seven-loop a solar PV array voltage-control mechanism is developed
­configuration established at IIT in which three loops are for a given insolation. Here, the inverter output voltage Vo
connected to the North Substation and four loops are con- of solar PV units is determined by the microgrid. The dc/ac
nected to the South Substation. The components of the IIT inverter uses an angle control to stabilize the dc bus voltage
microgrid are described in the remainder of this section. Vdc based on the fixed Vo and also used a magnitude con-
trol to regulate the reactive power output at a reference
Natural-Gas Turbine Synchronous Generation value (typically zero). Based on the stabilized Vdc , the dc/dc
The IIT microgrid is equipped with an 8-MW natural-gas- converter adopts MPPT control to regulate the solar PV
fired power plant with two 4-MW Rolls Royce gas turbines. array voltage VPV and reach the maximum real power out-
The natural-gas turbine consists of five sections, including put. The objective of solar PV generation control is to with-
air intake, compressor, combustor, turbine, and exhaust. draw maximum real power without injecting any reactive
The air sucked into the inlet is compressed by the com- power to the microgrid.
pressor and mixed with the fuel (natural gas) to form an
air–fuel mixture. The mixture is burned in the combustor Wind Turbine Unit
to form a high-pressure air, which drives the turbine. The An 8-kW wind turbine unit is installed on the north side of
synchronous generator installed on the turbine shaft will the campus in the Stuart soccer field, connected to Loop 1, as
convert the mechanical energy into electrical energy. shown in Figure 6. The wind turbine unit on the IIT campus

IIT Microgrid (Optimal and Reliable Operation)

Economical Operation Short-Term Reliability

Tertiary
Control Unit Islanding
Economical Commitment and Emergency Primary
Self-
Demand and Resynchronization Demand Secondary Control
Economical Healing
Response Response Control
Dispatch

Microgrid Components
Meters Coupling
Wind PV Gas Building HRDS Gas
and Switch
Turbine Arrays Turbines Controllers Switches Turbines
PMUs at PCC Set Point Values
Control Commands
Battery Battery Monitoring Signals Battery
Storage Storage Storage

Figure 1. The objectives and functions for the control and operation of the IIT microgrid.

42 I E E E E l e c t ri f i c a t i on M a gaz ine / september 2013


Microgrid of the IIT Campus
ED Glancy Field McCormick Student Village

Cu
n
PMU

TX
TRI

nin
Law
AEP

g
Parking
Flower
Farr IPS

East
Lewis

ha
Gunsaulus Gas Generator

m
Graduate
Charging Station

PKS

Chapel
Solar PV

North
South
PKP
SPE
DTD
Loop 4

ASP

Carmen
Bailey Loop 2 MTCC
Keating (Gymnasium) MC Parking Parking
KH

Commons
Parking
Parking
Parking
Parking Parking
Downtown State Street
Perlstein
E1 PH

AM


TS

Siegel

Alumni
Crown

LS

SB
Engineering 1 WH SH
CR
TN
TC

Stuart
Life Science
Loop 5
IIT Tower

Stuart Field Wishnick


Loop 7

Life Science Research


Institute of Gas Tech.

HH GL

AAR 3
Loop 1
Loop 3

Hermann Galvin Library Incubator

Parking
Parking South Substation IITRI
Chemistry
Wind Turbine AAR 2 VanderCook North Substation CO-GEN Power Plant
Machinery

Main IITRI Metals Loop 6

Fisk Substation Pershing Substation


(12.47 kV) (12.47 kV)

IEEE Elec trific ation Magazine / s ep t emb er 201 3


Figure 2. An IIT Microgrid based on a looped distribution system.

43
May 2013. Here, the wind turbine unit would spin when the
wind speed is higher than 10 mi/h (4.47 m/s).

Battery Storage
The IIT microgrid is equipped with a 500-kWh battery
storage system (including ten 50-kWh battery cells)
with 250-kW power capacity, which is connected to
Loop 1. ­Figure  9 shows a stack of the flow battery and
the battery inverter, which can regulate the real and
reactive power output.

HRDS Switches
The HRDS at IIT uses underground closed-loop fault-
clearing Vista switchgear with SEL-351 directional over-
Figure 3. The full-scale model of the natural-gas turbine at IIT.
current protection relays. The fault isolation takes place in
a quarter of a cycle by automatic breakers. The communi-
cation via fiber-optic cables facilitates the coordination
between Vista switches. ­Figure 10 shows the underground
installation of a HRDS switch at IIT. In HRDS, at least two
simultaneous failures in the cable segments feeding a
building from both paths will lead to a ­complete outage in
the building. As the chances of two coincident failures is
far less than single failures in cables feeding, the interrup-
tion indices of the buildings are improved significantly by
the installation of HRDS. ­Figure 11 shows a loop configura-
tion in distribution system at IIT. Here, in Loop 1, any cable
Figure 4. The solar panel in IIT’s charging station.
failure between Vista switches 1C and 1D will be cleared,
and the Stuart and Life Sciences Buildings fed by the
uses a Viryd wind turbine unit. The wind turbine features switches will not face any interruptions.
continuous ­variable transmission (CVT) technology, which
provides automatic and continuous variable ratio change Meters and PMUs
that maintains stable rotor speed for the generator as wind The IIT microgrid is equipped with building meters and
speed changes. This would enable the generator to main- PMUs, which report building electricity consumptions to
tain high efficiency at all wind speeds. The CVT can also the master controller. The master controller will receive an
precisely slow the rotor in high wind speed, curtailing the energy consumption update every 15 min. The load data
excess wind power. Figure 7 shows the structure of the recorded on 17 July 2012 at the McCormick Tribune Campus
CVT-based wind turbine unit. The role of the variable gear Center (MTCC) at the IIT microgrid are shown in ­Figure 12.
ratio is to regulate the power output close to the rated value Approximately 30% of building consumptions at IIT are
when the wind speed is within the acceptable range. The shiftable loads, which can be served when the electricity
cut-in and cut-off wind speeds for this turbine are 4.5 and price is lower. The IIT microgrid is equipped with 12 PMUs
25 m/s, respectively, and the turbine has an 8-m diameter that monitor and record the real and reactive generation
and 50-m2 sweep area. Figure 8 shows the hourly power and consumption in real time and provide the information
output and the wind speed for the wind turbine unit on 20 on instantaneous voltage and current of DER units (includ-
ing the magnitude and phase angle)
at a sampling rate of one signal per
cycle to the master controller.
Angle Magnitude ­Figure  13 shows a PMU installed at
Control Control
MPPT the North Substation. Figure 14
ang mag
VPV, IPV Qout shows the real and reactive power of
Vdc PWM
critical loads and DER units, which
are calculated by master controller
Microgrid

ac Filter
based on the instantaneous values.
Vo
Capacitor
Building Controllers
Building controllers facilitate the
Figure 5. The equivalent circuit and power output characteristics of a solar PV cell. building consumption manage-

44 I E E E E l e c t ri f i c a t i on M a gaz ine / september 2013


ment in the IIT microgrid. The reduc- follow set points determined by
tion in building consumption is their controllers, can interact with
accomplished by defining several other DER units using a grid-forming
operating modes representing con- interactive c ­ ontrol scheme. DER
sumption levels in each building. units with load-sharing capability,
Once the operation mode for each which would collaborate in setting
building is set by the master control- their output real and reactive power
ler, the building controller will send a dispatch according to the microgrid
signal to the sub-building controllers frequency and voltage, are an exam-
to set the requested load level associ- ple of gird-forming interactive con-
ated with the selected mode and trolled DER units. Dispatchable units
feed back the confirmation signal to can also use grid-forming noninter-
the master controller to acknowledge active control to maintain a fixed
the mode change. Figure 15 shows set-point for microgrid voltage and
the buildings equipped with building frequency. This control scheme can
controllers in Loop 1, in which the be used in dispatchable units with
blue squares represent command sufficient real and reactive power
signals from the master controller, capacity (such as microturbines) to
and the green squares represent maintain nominal microgrid voltage
acknowledgment signals originating and ­frequency.
from the building controllers. The The grid-following control is used
building controllers are also able to when the DER unit is not required to
Figure 6. The wind turbine unit at IIT.
monitor and control the energy flow directly control the microgrid voltage
within the buildings, including hot and/or frequency. In this control
and cold water flow, heating and cooling loads, and scheme, the real and reactive power output of the DER is
­monitoring the temperature of different spaces within maintained within permissible limits, and the voltage and
the building. frequency is regulated by other DER units in the microgrid.
Similar to the grid-forming control scheme, DER units
Microgrid Control using a grid-following control scheme can either collabo-
Figure 11 shows the DER units (including DG and rate with other DER units in the microgrid or operate
rechargeable storage) implemented
in the IIT microgrid. The IIT
microgrid integrates DG units, Input Disk Output Disk
which are classified into conven-

Microgrid
tional DGs and PE coupled DGs. Wind
Table 1 shows that the DER control
schemes are categorized into grid-
Induction
following and grid-forming control. Turbine CVT Generator
In grid-forming control, DER
units maintain the microgrid volt-
age and frequency, while in the Figure 7. A CVT-based wind turbine unit with a fixed-speed induction generator.
grid-following control, the units
maintain their individual real and
reactive power dispatch. In other Wind Generation Power Output (kW)
words, DER units with grid-forming 8 Wind Speed (mi/h) 25
7
control would act as the swing bus 20
Wind Speed (mi/h)

6
Dispatch (kW)

in microgrids and should have ade-


5 15
quate real, reactive, and reserve
4
power capacity and fast response 10
3
to control microgrid voltage and 2
frequency. The DER unit using this 5
1
control scheme can either collabo- - -
rate with other microgrid units
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23

(interactive control) or operate Time (h)


autonomously (noninteractive con-
trol). Dispatchable DER units, which Figure 8. The wind power generation on 20 May 2013 at IIT.

IEEE Elec trific ation Magazine / s ep t emb er 201 3 45


autonomously. Nondispatchable units control scheme on the natural-gas
in a microgrid (such as solar PV units turbine and the battery storage units
with MPPTs or wind turbine units) would enable the microgrid to
often apply a noninteractive control, ­operate in both island and grid-­
which maximizes their output power. connected modes.
Dispatchable units apply a grid-follow- The proper monitoring and control
ing interactive control in which the real of DERs at the IIT microgrid would
and reactive power output is deter- satisfy the following objectives:
mined by the respective set points. This x load sharing among DERs
control scheme can be applied to PV x voltage and frequency regulation
units equipped with storage in in island mode
microgrids, where the output real and x islanding and resynchronization
reactive power is regulated irrespective to the utility grid
of the control strategy for microgrid x optimal generation and consump-
voltage and frequency. tion at IIT microgrid
Depending on the microgrid operat- x real-time monitoring of the distri-
ing mode, a proper DER control scheme, bution system ­components.
shown in Table 1, is used. An interac- Functionally, three control levels
Figure 9. A battery storage unit and
tive grid-forming control can be used inverter. (shown in Figure 1) are applied to
either in island or grid-connected the IIT microgrid:
mode. In island mode, DERs apply this control scheme to 1) primary control, which is based on droop control for
share the load, while in the grid-­connected mode, DERs sharing the microgrid load among DER units
apply this control scheme to regulate the power exchange 2) secondary control, which performs corrective action
between the microgrid and the utility grid. The noninter- to mitigate steady-state errors introduced by droop
active grid-forming control can be used only in island control
mode, as the frequency and voltage will be set by DER 3) tertiary control, which procures the optimal dispatch of
units in the island mode. In the grid-connected mode, if DER units in the microgrid and manages the power flow
the utility frequency or voltage deviates from the DER set between the microgrid and the utility grid for optimizing
point, the DER real or reactive power may reach its physi- the grid-connected and island operation schemes.
cal limit once its controller apply the set point voltage or The control levels at the IIT microgrid are discussed next.
frequency. The DER unit with grid-following control fol-
lows the microgrid voltage and frequency, which is set by Tertiary Control
the utility grid in grid-­connected mode and other DER Tertiary control is the upper most level of the control
units in island mode. system in ­Figure 1; it ensures the optimal operation of
Table 1 shows that the natural-gas turbine and the bat- the microgrid by determining the set points of genera-
tery storage at IIT are using interactive grid-forming control tion and load entities at the IIT microgrid. The master
and the wind turbine and PV units are using noninterac- controller, which is regarded as the most important
tive grid-following control. The interactive grid-forming control element of the IIT microgrid, is responsible for
applying the tertiary control. The master controller uses
the data supplied by the supervisory control and data
acquisition (SCADA), which enables the real-time moni-
toring and control of microgrid elements including
HRDS controllers, on-site generation, storage, and indi-
vidual building controllers and meters. The master con-
troller signals, which are relayed through SCADA, will
adjust building loads and the generation dispatch for
economical operation.
Figure 16 shows a hierarchical operation within the
­tertiary control that would provide generation and
load management at normal and emergency condi-
tions. The hierarchical tertiary control includes the fol-
lowing components.
xx The master controller determines the optimal and
reliable operation of the microgrid through optimal
Figure 10. The installation of an underground HRDS switch. generation dispatch and load signals. The generation

46 I E E E E l e c t ri f i c a t i on M a gaz ine / september 2013


Utility Grid

12.47 kV

PCC
North South
Substation Substation
4.16 kV 4.16 kV

VanderCook
Engineering 1
Vista lE

Vista lA

=
Gas-Turbine
S

= Synchronous
= Machinery Generators
Loop 1

Loop 2

Loop 3

Loop 7
CTA 1

S
PV =
Vista lD

Vista lB

=
Life Sciences =
S

=
S

= Vista lC
CTA 2 =
Battery = PV
S

=
Stuart =
= PV
Wind

PV

Figure 11. The DER units and HRDS in the IIT microgrid.

dispatch signals are sent to dispatchable DER units on master controller indicate the status of DER and distribution
campus, and the load signals are sent to the building components, while the master controller signals provide set
controllers. points for DER units and building controllers. Building con-
xxThe building controllers are responsible for setting the trollers will communicate with sub-building controllers
building loads according to the dispatch signal through a ZigBee wireless control and monitoring system to
received from the master controller. achieve a device-level rapid load management.
xxThe sub-building controllers
­preform device-level load man-
380
agement by controlling the opera-
360
tion status of devices located in 340
Dispatch (kW)

buildings. 320
The hierarchical tertiary control 300
approach would receive the informa- 280
tion from loads and power supply 260
entities on campus as well as the 240
information on the status of campus 220
distribution network and procure the 200
12:14:33 a.m.
12:59:33 a.m.
1:44:33 a.m.
2:29:33 a.m.
3:14:33 a.m.
3:59:33 a.m.
4:44:33 a.m.
5:29:33 a.m.
6:14:33 a.m.
6:59:33 a.m.
7:44:33 a.m.
8:29:33 a.m.
9:14:33 a.m.
9:59:33 a.m.
10:44:33 a.m.
11:29:33 a.m.
12:14:33 p.m.
12:59:33 p.m.
1:44:33 p.m.
2:29:33 p.m.
3:14:33 p.m.
3:59:33 p.m.
4:44:33 p.m.
5:29:33 p.m.
6:14:33 p.m.
6:59:33 p.m.
7:44:33 p.m.
8:29:33 p.m.
9:14:33 p.m.
9:59:33 p.m.
10:44:33 p.m.
11:29:33 p.m.

optimal solution via an hourly unit


­commitment and real-time economi-
cal dispatch for serving the campus
load in the normal operation mode
Time
and contingencies. In ­Figure  16, the
monitoring signals provided to the Figure 12. The MTCC load on 17 July 2012.

IEEE Elec trific ation Magazine / s ep t emb er 201 3 47


there is a sudden decrease in demand in microgrid, the
frequency and voltage increases. Once the frequency or
voltage increases, the operating point may slide from A to B
with primary control to decrease the generation dispatch
and match the generation with demand. As the frequency
or voltage is above the rated value, the secondary control is
used to lower the operating point from B to C, where the
­frequency or voltage is restored to the rated values. As shown
in Figure 17, only the frequency or voltage is restored in sec-
ondary control, while the real or reactive power dispatch is
not changed. Thus, with secondary control, dispatchable
DER units would maintain the frequency and voltage at the
rated value while adjusting their dispatch according to the
tertiary control signal to serve the microgrid load. The sec-
ondary control is a centralized and performed by master
controller. The master controller will set the microgrid volt-
age and frequency and send the set points to primary
­control at DER level. Restoration, load sharing, and manage-
ment can be performed in secondary control.

Primary Control
The primary control, shown in Figure 1, is the lowest level
of control in the IIT microgrid. The primary control is
mainly used for load sharing among controllable and dis-
Figure 13. The PMU at the North Substation. patchable fast-response DER units, which have adequate
capacity to serve the microgrid load. The most widely used
primary control strategy is droop control, which is shown
Secondary Control in Figure 18. DER units equipped with droop control, which
Secondary control in Figure 1 is the middle level control at are connected in parallel, would not need to communicate
the IIT microgrid. Secondary control is used to eliminate with each other to perform load sharing; instead, individu-
frequency and voltage deviations caused by lower control al dispatch levels are calculated based on predefined droop
level (primary control). As illustrated in the Figure 17, once characteristics and microgrid frequency and voltage. In

PMU Information

Date 5/30/2013 Time 3:01:51 PM


ID No Building Name P (kW) Q (kVAr) Frequency Power Factor
1 Engineering 1 590.18 832.45 60.0150 0.5784

2 Life Sciences 302.70 289.27 60.0150 0.7230


3 Stuart Building 442.60 210.45 60.0180 0.9031
4 Gunsaulus 46.28 33.48 60.0150 0.8102

5 MTCC 335.25 234.14 60.0160 0.8198


6 Hermann Hall 447.39 18.12 60.0150 0.9992
7 Wishnick Hall 426.30 200.09 60.0150 0.9052

8 Siegel Hall 138.09 260.82 60.0170 0.4679


9 North Substation 7017.33 165.26 60.0160 0.9997
10 IIT Tower 628.78 312.70 60.0120 0.8954

11 IIT Tower (20th Floor) 1238.62 537.08 60.0160 0.9175

12 Power Plant 0.00 0.00 59.9600 0.0000

Figure 14. Real and reactive power based on PMUs on DER units.

48 I E E E E l e c t ri f i c a t i on M a gaz ine / september 2013


Curtailment Points Will Keep the Fans Off
Engineering Building Life Science Building Stuart Building

E1.AH01.CURT ME1SYS ME1RET LS.AH02.CURT LS2SYS SB.AH01.CURT SB.AH01.SYS


Curtailment Descriptor Descriptor Curtailment Descriptor Curtailment SF South End
NONE Priority Priority NONE Priority NONE NONE
OFF Value N/A Units Value N/A Units OFF Value N/A Units OFF ON

E1.AH02.CURT ME2SYS ME2RET Point: MEIRETLS.AH02.CURT LS3SYS SB.AH02.CURT SB.AH02.SYS


Curtailment Descriptor Descriptor Desc.: Curtailment
Descriptor Descriptor Curtailment NORTH END
NONE Priority Priority Status: StatusNONE Priority NONE NONE
OFF Value N/A Units Value N/A Units Pri: OFF
Priority Value N/A Units OFF ON
Value: Value
E1.AH03.CURT ME3SYS Ex–State: StateLS.AH03.CURT LS4SYS SB.AH03.CURT SB.AH03.SYS
Curtailment Descriptor Total: Total Curtailment Descriptor Curtailment Basement
NONE Priority NONE Priority NONE NONE
OFF Value N/A Units OFF Value N/A Units OFF ON

E1.AH04.CURT ME4SYS LS.AH06.CURT LS6SYS


Curtailment Descriptor Curtailment Descriptor
NONE Priority NONE Priority
OFF Value N/A Units OFF Value N/A Units

E1.AH05.CURT ME5SYS LS.AH07.CURT LS7SYS


Curtailment Descriptor Curtailment Descriptor
NONE Priority NONE Priority
OFF Value N/A Units OFF Value N/A Units

LS.AH08.CURT LS8SYS
Curtailment Descriptor
NONE Priority
OFF Value N/A Units

Figure 15. The building controllers showing the status of controllable loads in three buildings in Loop 1 at IIT.

Figure 18, the DER dispatch P is at its rated value Prated at the turbine and exciter, respectively, to regulate the real
the rated frequency frated , which are determined by the and reactive power output and maintain the microgrid
master controller through tertiary control level. As the fre- frequency and voltage at the rated values. At steady state,
quency increases, there will be a slight decrease in power if the generator dispatch is deviated from the rated value
dispatch to compensate the frequency deviation. Similarly, through primary droop control, the secondary control will
as the microgrid voltage increases, the injected reactive generate a nonzero adjustment signal shown in (1) to
power decreases to compensate the voltage drop. In ­Figure restore the frequency or voltage back to the rated value.
18(a) and (b), m p and m q , respectively, represent the slopes Thus, the natural-gas turbine synchronous generator
of the f - P and v - Q curves. The DER units at the IIT would serve the campus load while maintaining the
microgrid, which are equipped with primary and sec- microgrid frequency and voltage at the rated value.
ondary control, are the natural-gas turbine synchro-
nous generator and the battery storage unit. ~ 2nd = m p $ ^P - Prated h

V2nd = m q $ ^Q - Q rated h. (1)
Natural-Gas Turbine Synchronous Generator
Figure 19 shows the control diagram for the natural-gas Battery Storage Unit
turbine synchronous generator. Here, ~ , ~ rated , V , and The control structure of the battery storage system is
Vrated are the measured speed, rated speed, measured volt- shown in Figure 20, where the battery storage is connect-
age, and rated voltage of the synchronous generator, ed to the microgrid through a bidirectional dc/ac inverter,
respectively; P, Prated , Q , and Q rated are the measured real an ac filter, and a transformer. Here, the output real and
power, rated real power, measured reactive power, and reactive power denoted by P and Q is calculated by
rated reactive power of the generator, respectively; ~ 2nd measuring the terminal voltage and current Vo and I o .
and V2nd are the adjustment signals used for secondary The measured real and reactive power are used in the
control. As shown in Figure 19, the natural-gas turbine primary droop control to provide a reference voltage sig-
and exciter provide the input mechanical torque TM and nal V *o . The voltage loop is used to stabilize the inverter
excitation to the generator. The primary and secondary terminal voltage using the reference voltage signal and
control modules for ~ - P and v - Q generate signals to to ensure that the DER output impedance is inductive at

IEEE Elec trific ation Magazine / s ep t emb er 201 3 49


pulsewidth modulation (PWM) ratio, which would trigger
Table 1. The Classification of DER Controls
dc/ac inverter switches. If the microgrid frequency fMG or
and Units at the IIT Microgrid.
the microgrid ­voltage VMG deviates from the rated value,
Grid-Following Grid-Forming
Control Control the secondary control module will generate secondary
control signals f2nd or V2nd to restore the rated frequency
Noninteractive Power injection Voltage and or voltage. The inverter power output is limited between
control (wind turbine, frequency control
−250 and 250 kW as enforced by primary control module.
solar PV)
In Figure 20, the battery storage system would maintain
Interactive Real and reactive Load sharing
control power dispatch (battery storage, the rated frequency and voltage of microgrid in case of
control natural-gas turbine) any disturbances in the island mode. Moreover, the bat-
tery storage system would perform the following func-
tions:
rated frequency, which is an important factor in imple- xxcontain abrupt load changes in island mode
menting f - P droop control. The current loop is used to xxhelp mitigate frequency deviations in island mode
obtain a fast response in a wide frequency band. The x participate in frequency regulation when the
biloop block output (voltage and current loops) is the microgrid operates in grid-connected mode
x charge and discharge
periodically for the eco-
nomical operation of the
IIT microgrid.

Solar (PV) Wind DAS


Economical and
Thermal Generation Reliable Operation
of the Microgrid
Generation Control System
The hierarchical tertiary
control is used to ensure
the economical and reliable
operation of the microgrid.
In ­Figure 1, the economical
operation pertains to unit
Building Control System commitment and econom-
ical dispatch as well as eco-
Master Sub-Building
nomical demand response
Controller ZigBee Control
System in grid-connected and
island modes. Also, the
short-term reliability of
microgrid is satisfied
Distribution System Control through islanding and
resynchronization, emer-
gency demand response,
and self-healing. In this
section, the economical
and reliable operations of
microgrid performed by the
hierarchical tertiary control
are discussed.

Economical Operation
Storage Control The cost of economical
System
operation includes the cost
of utility grid energy trans-
Battery Storage actions (in both directions),
Charging Station cost of microgrid energy
supply, and load curtail-
ment costs (value of lost
Figure 16. Architecture of master controller at IIT. load.) Microgrid outages

50 I E E E E l e c t ri f i c a t i on M a gaz ine / september 2013


could result in a loss of revenue estimated at US$80/kWh
(value of lost load), which covers the replacement cost of f/V
damaged equipment, and personnel and administrative
Pri
B m
cost of restoring and sustaining research and education at Co ary
Secondary ntro
IIT. Once the real-time price exceeds 6–8 cents/kWh (mar- l
Control
ginal cost of microgrid generation), the campus load is sup- A
plied by the local microgrid generation. The master control-
C
ler uses a security-constrained unit commitment to calcu- Rated
late the day-ahead optimal operation of microgrid. The
optimal hourly solution includes the dispatch of the No Change
microgrid generation and renewable energy resources, in Dispatch
P/Q
exchanges with the utility grid, charge/discharge schedule
of the battery storage unit, and adjustments to set points of
Figure 17. The secondary control in DER units.
building loads.
To perform the tertiary control, the master ­controller
procures the day-ahead forecasts for building loads and and 24.5 cents/kWh at hours 16 and 17, respectively. The
renewable energy resources. The forecasted price of elec- cost of supplying the campus energy on this day was
tricity is procured by ComEd. The forecasted values are US$15,524.
calculated based on the historical data and forecasted The real-time optimization is based on real-time infor-
weather data using nonlinear regression methods. The mation, such as the price of electricity, campus load,
integration of renewable energy generation in microgrids renewable energy generation, and the topology of the
will reduce carbon footprints while decreasing the cost of campus microgrid including the state of Vista switches
supplying the campus load. The drawback of integrating and cables. The master controller will perform the campus
renewable technologies is the variability of their genera- energy management by procuring the optimal 15-min
tion portfolio. To overcome this challenge in the microgrid, economical demand response and the dispatch and com-
several approaches are used including the coordination of mitment of campus generation.
dispatch with the utility grid and hourly demand
response. The economical operation of microgrid is imple- Economical Demand Response
mented by two master controller functions, which are The master controller will adjust shiftable building load
discussed below. schedules to calculate optimal generation schedules.
Shiftable loads can often be served at delayed hours with-
Unit Commitment and Economical Dispatch out jeopardizing the convenience of campus residents.
To ensure the economical operation of the microgrid, the Moreover, the tertiary control will schedule the charging/­
master controller performs unit commitment and eco- discharging sequence of battery storage to optimize the
nomical dispatch in island and grid-connected modes to supply of campus load with respect to the utility price of
procure the o­ ptimal generation scheduling of DER units as electricity. In island mode, the microgrid load is supplied
well as the utility grid dispatch. In grid-connected mode, by dispatchable DER units, which respond according to
the microgrid load is compensated by adjusting the power their droop characteristics using primary and secondary
generation exchange with the utility grid. Here, the prima- control scheme. The tertiary control would also set the
ry and secondary controls of DER units will not respond to optimal operating point of dispatchable DER units. The
disturbances, as the microgrid voltage and frequency are nondispatchable DER units including solar PV and wind
set by the utility grid. Figure 21 shows the day-ahead turbine units will not respond to deviations in real and
hourly control signals provided by the master controller reactive campus loads. In Figure 22, the master controller
for supplying the campus load on 17 July 2012. On this would apply demand response through tertiary control
day, the campus reached its annual
peak load of 11.263 MW at hour 15.
The master controller dispatched f V
the microgrid generation once the ∆f = mp . ∆P ∆V = mq . ∆Q
electricity price was higher than 6 (f1, P1) (V1, Q1)
cents/kWh. In Figure 21, the battery (frated, Prated) (Vrated, Qrated)
∆f mp ∆V m
storage was charged when the elec- q
∆P ∆Q
tricity price was lowered to 2.8 and
2.7 cents/kWh at hours 4 and 5, Q
P
respectively. In addition, the battery (a) (b)
storage was discharged as the price of
the electricity was increased to 22.4 Figure 18. The (a) frequency and (b) voltage droop characteristics of a DER unit.

IEEE Elec trific ation Magazine / s ep t emb er 201 3 51


P
P-ω TM
(ωrated) + + Primary Gas Sync.
Turbine Gen.
+ ω −
2nd
P-ω V
Secondary ω Exciter
Q

Q-V
V2nd Secondary
Vrated +
Prated +

Q-V
Tertiary Qrated Primary
Control

Figure 19. The natural-gas turbine synchronous generator control module.

signals when the price of electricity is high, which would was recorded by ComEd. Here, the campus load is reduced
lower the cost of supplying the campus load. Here, the by 60% through curtailing building loads, shifting campus
building load is shifted from peak hours 16–18 to off-peak loads, and dispatching the natural-gas turbine at IIT.
hours 4–6. The set points shown in Figure 22 are sent to
DER units and building controllers to set the campus load Short-Term Reliability
and generation. The local microgrid generation is also The IIT microgrid connects to the utility grid through
used to supply the peak demand at the utility grid. four 12.47-kV feeders located at the North and South
Accordingly, the daily energy cost of the microgrid is Substations. The IIT microgrid can operate in both grid-
reduced from US$15,524 to US$13,715. Figure 23 shows the connected and island (autonomous) modes. In the grid-­
economical load reduction at IIT on 19 August 2010, which connected mode, the microgrid frequency and voltage

Inverter
ac Filter

Microgrid

PWM

Ic Vo Vo Io
Primary
∗ Control
Current Voltage Vo P, Q Power
Loop Loop Calculation
Biloop

Prated, Qrated f2nd, V2nd

Secondary
Control
Tertiary
fMG, VMG
Control

Figure 20. The control structure of the battery storage system.

52 I E E E E l e c t ri f i c a t i on M a gaz ine / september 2013


are regulated by the utility grid. In
island mode, the n­ atural-gas turbine 13,000 30

Electricity Price (cents/kWh)


and battery storage would maintain 11,000 25
the microgrid frequency and voltage, 9,000

Power (kW)
20
while solar PV and wind turbine units 7,000
serve portions of the campus load. 15
5,000
The short-term microgrid reliability is 10
3,000
enhanced by implementing three
1,000 5
major functions at IIT: islanding and
resynchronization, emergency −1,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0
demand response, and self-healing, Time (h)
which are discussed in this section. Utility Grid Supply Total Demand
Battery Supply Price of Electricity
Microgrid Supply
Islanding and Resynchronization
The microgrid may increase its load
point reliability indices by setting up Figure 21. The day-ahead storage, microgrid, and utility grid supply on 17 July 2012.
its operation in island mode. Gener-
ally, there are two major reasons for
setting up a microgrid in island mode: 1) poor power nization signals to the campus DER units through sec-
quality at the utility grid, such as frequency or voltage ondary control for mitigating any possible transients.
deviations, and 2) major faults at the utility grid. PMUs The following criteria are to be satisfied for transition
and voltage/current meters at the point of common cou- from island to grid-connected mode:
pling (PCC) would report the utility grid malfunction to 1) The voltage magnitude difference at the PCC would be
the master controller, which will initiate the islanding small.
process at the tertiary control level. The master controller 2) The frequency difference would be small to match the
will monitor building meters for supplying the local gen- voltage phase angles at the switching instance.
eration dispatch. At islanding, the master controller may 3) The voltage angle with the lower frequency should lag
reduce the campus load through emergency demand behind that of the higher frequency. Figure 25 shows
response to match the load with the local generation dis- the voltage angle difference between the microgrid and
patch. The load reduction may entail shifting building the utility grid at resynchronization instance. Assuming
loads and reducing curtailable building loads. Matching that the microgrid frequency is slightly smaller than
the load with generation at islanding will reduce tran- that of the utility grid if VMG leads Vgrid , then the power
sients and ensure a feasible microgrid operation consid- flow will be from the microgrid to the utility grid and in
ering the ramping limits of DER unit g ­ eneration. the reverse direction at steady state. The flow from the
Figure 24 shows the campus load restoration in island microgrid to the utility grid at resynchronization may
mode at the Engineering 1 and Stuart Buildings located result in the overloading of the microgrid DER units.
in Loop 1 on 19 July 2012. The load restoration started at The IIT microgrid resynchronization process is present-
6:19 a.m. on both buildings and was fully restored at 6:29 ed as follows. At first, the master controller will send the
a.m. Figure 24(b) shows the inrush
current of a switched-on transform-
er located in the Stuart Building. In 13,000 30
Electricity Price (cents/kWh)

island mode, any abrupt changes in 11,000 25


the local microgrid load are served 9,000
Power (kW)

20
by the battery storage through pri-
7,000
mary and secondary controls. Once 15
5,000
the normal operation at the utility 10
3,000
grid is restored, the microgrid will be
1,000 5
resynchronized with the utility grid.
In island mode, the microgrid could −1,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0
be operated at a frequency and a Time (h)
voltage magnitude that are different
than those of the utility grid, which Utility Grid Supply
Total Demand
could cause transients during the Utility Grid Supply with Building Controllers
resynchronization process and dam- Price of Electricity
age the substation equipment. The
master controller will send synchro- Figure 22. The day-ahead economical demand response by building controllers on 17 July 2012.

IEEE Elec trific ation Magazine / s ep t emb er 201 3 53


able levels in island mode or to sup-
ply the utility grid partially in grid-
10,000 100
connected mode in case of an
9,000 90
80 emergency. In either case, the IIT
8,000
7,000 70 microgrid will perform emergency
6,000 60 demand response. In island mode,
(kW)

(°F)
5,000 50
40 the emergency demand response will
4,000
3,000 IIT Load 30 match the load with the generation
2,000 Temperature 20 (e.g., dispatch the battery storage or
1,000 10
curtail building loads), while in grid-
0 0
0:00 4:00 8:00 12:00 16:00 20:00 24:00 connected mode, the microgrid
Time (h) would curtail loads as required. The
master controller will communicate
Figure 23. The load reduction test at the IIT microgrid on 19 August 2010. with building controllers to curtail or
shift loads and monitor the updated
frequency adjustment signal to the natural-gas turbine and load level through building meters.
the battery storage unit to adjust the microgrid frequency Once the campus load is reduced, DER units on campus
to less than nominal frequency (59.9 Hz). The secondary will be redispatched through primary and secondary con-
control will maintain a lower microgrid frequency than that trols to maintain the nominal voltage and frequency. After
of the utility grid before resynchronization. When the the completion of emergency demand response, the ter-
microgrid voltage angle lags behind that of the utility grid tiary control provided by master controller will procure
slightly (fewer than 10), the PCC switch will be closed, and the steady-state optimal generation dispatch of dispatch-
the IIT microgrid will be resynchronized with the utility. able DER units.

Emergency Demand Response Self-Healing


The objective of emergency demand response is to main- Self-healing relies on robust HRDS protection and switching
tain the microgrid voltage and frequency within accept- schemes as well as on-campus storage to supply the load

Current Magnitude Curve (E1-500K-TR#1-IA)


250

200
Current (A)

150

100

50

0
0 20 40 60 80 100 120 140 160 180
6:18 a.m. Time (s) 6:21 a.m.
(a)

Current Magnitude Curve (SB-PWR-1000K-IA) Inrush Current Magnitude Curve (SB-PWR-1000K-IA)


35 200
30 180
160
25
140
Current (A)

Current (A)

20 120
15 100
80
10
60
5
40
0 20
0 20 40 60 80 100 120 140 160 180 0 50 100 150 200 250 300
6:19 a.m. Time (s) 6:22 a.m. 6:28 a.m. Time (s) 6:33 a.m.
(b)

Figure 24. The load restoration at the (a) Engineering 1 and (b) Stuart Buildings in Loop 1 in island mode on 19 July 2012.

54 I E E E E l e c t ri f i c a t i on M a gaz ine / september 2013


during campus conting encies and maintain the o ­p t i m a l
(e.g., component outages). The integra-
The microgrid ­dispatch of DER units. The func-
tion of HRDS provides a looped distri- represents a tions are performed by the
bution network by integrating Vista ­m aster controller, DER units,
switches to automatically detect and multitier hierarchical building controllers, and meters,
isolate microgrid faults while main- which can achieve economical
taining the service to buildings through
control of self- and reliable operations of a
redundant distribution paths. More- sustaining energy microgrid. The effect of HRDS
over, the integration of battery storage switches in reducing the tran-
will serve critical campus loads in case infrastructure with sients that occur during distri-
of generation deficiency or distribution bution network faults and com-
cable contingencies. The interruption
islanding and ponent failures in microgrids is
indices are calculated in for load points resynchronization, discussed. Transients occur
on Loop 3 with and without Vista when switching a microgrid
switches, which show that the integra- self-healing, and between island and grid-con-
tion of HRDS will result in a dramatic
reduction in load interruption indices.
demand response nected modes, and options such
as emergency demand response,
Rapid fault ­detection and clearance will capabilities. load restoration, and DER unit
result in fewer transients in distribu- response are considered in this
tion systems. article to maintain steady-state
Figure 26 shows two induction operations in microgrids.
motors in non-HRDS and HRDS systems. The response of
motor 1, located close to the Vista switch 1, to a nearby Acknowledgment
cable fault is shown in Figure 27. As shown in this figure, This project was funded in part by the U.S. Department of
HRDS has cleared the fault in 0.1 s, which has retained the Energy Grant DE-FC26-08NT02875.
normal motor speed quickly. In Figure 26(a), without the
HRDS system, the cable fault would lead to a dramatic drop
in the motor 1 speed as the fault clearing time is longer and
the fault clearance would lead to the loss of load down- VMG
s V grid
stream, i.e., motor 2. Lead
V MG

Conclusions Vgrid
This article discusses the hierarchical control of
VM
microgrids and the role of primary, secondary, and ter- G Lags
Vg
rid
tiary ­controls in enhancing the microgrid reliability VMG
and economics and introduced the control applica-
tions to a functional microgrid at IIT. The IIT microgrid Figure 25. The voltages at the microgrid and the utility grid.
is analyzed as a test bed, and the functions for imple-
menting microgrid objectives are
discussed. The functions include
unit commitment and economi- Motor 1 Motor 2
cal dispatch, economical demand
response, islanding and resyn- Generator
chronization, emergency demand
response, and self-healing. The
MV Breaker
master controller applies tertiary
(a)
and secondary control to ensure
Motor 1 Motor 2
the economical and reliable oper-
ation of the microgrid. Primary
control is applied at the DER unit Generator
level to respond to disturbances
i n a s h o r t t i m e, w h i l e t h e Vista Switch 1 Vista Switch 2
­s econdary and tertiary control
signals eliminate errors intro- (b)
duced by primary control to regu-
late the voltage and frequency Figure 26. Distribution networks (a) with and (b) without HRDS switches.

IEEE Elec trific ation Magazine / s ep t emb er 201 3 55


J. A. P. Lopes, C. L. Moreira, and A. G. Madureira, “Defin-
1.05 ing control strategies for microgrids islanded operation,”
1 IEEE Trans. Power Syst., vol. 21, no. 2, pp. 916–924, 2006.
0.95 J. F. Kelly, M. Meiners, and G. Rouse. (2007, Oct.). IIT Per-
0.9 fect Power Prototype, Final Report. Endurant Energy.
Speed (p.u)

0.85 [Online]. Available: www.galvinpower.org


0.8 Y. Fu, M. Shahidehpour, and Z. Li, “Security constrained
0.75 unit commitment with ac constraints,” IEEE Trans. Power
0.7 Without HRDS Syst., vol. 20, no. 3, pp. 1538–1550, Aug. 2005.
0.65 With HRDS A. Mehrizi-Sani and R. Iravani, “Potential function based
0.6 control of a microgrid in islanded and grid-connected
0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0
Time (s) modes,” IEEE Trans. Power Syst., vol. 25, no. 4, pp. 1883–1891,
Nov. 2010.
Figure 27. The speed of induction motor 1 exposed to a cable fault A. Flueck and Z. Li, “Destination: perfection,” IEEE
in Figure 26. Power Energy Mag., vol. 6, no. 6, pp. 36–47, Nov. 2008.
ComEd residential real-time pricing. [Online]. Available:
For Further Reading https://rrtp.comed.com
M. Shahidehpour and J. F. Clair, “A functional microgrid for R. H. Lasseter and P. Piagi, “Control and design of
enhancing reliability, sustainability, and energy efficiency,” microgrid components,” Final Report, Power Systems Engi-
Electricity J., vol. 25, no. 8, pp. 21–28, Oct. 2012. neering Research Center (PSERC), PSERC Publication 06–03,
N. D. Hatziargyriou, A. Dimeas, and A. Tsikalakis, “Cen- Jan. 2006.
tralized and decentralized control of microgrids,” Int. J. Guide for Design, Operation, and Integration of Distrib-
Distributed Energy Resources, vol. 1, no. 3, pp. 197–212, July– uted Resource Island Systems with Electric Power Sys-
Sept. 2005. tems, IEEE 1547.4, 2011.
J. M. Guerrero, M. Chandorkar, T. Lee, and P. C. Loh, M. E. Khodayar, M. Barati, and M. Shahidehpour, “Inte-
“ Advanced control architectures for intelligent gration of high reliability distribution system in microgrid
microgrids—Part I: Decentralized and hierarchical operation,” IEEE Trans. Smart Grid, vol. 3, no. 4, pp. 1977–
­control,” IEEE Trans. Ind. Electron., vol. 60, no. 4, pp. 1254– 2006, Dec. 2012.
1262, Apr. 2013.
J. Rocabert, A. Luna, F. Blaabjerg, and P. Rodríguez, Biographies
“Control of power converters in acmicrogrids,” IEEE Trans. Mohammad Shahidehpour (ms@iit.edu) is the Bodine
Power Electron., vol. 27, no. 11, pp. 4734–4749, Nov. 2012. chair professor and director of the Robert W. Galvin Center
A. Bidram and A. Davoudi, “Hierarchical structure of for ­Electricity Innovation at the Illinois Institute of Tech-
microgrids control system,” IEEE Trans. Smart Grid, vol. 3, nology. He received an honorary doctorate in 2009 from
no. 4, pp. 1963–1976, Dec. 2012. the Polytechnic University of Bucharest in Romania. He is
J. M. Guerrero, J. C. Vasquez, J. Matas, L. G. de Vicuna, and a research professor at King Abdulaziz University in Jed-
M. Castilla, “Hierarchical control of droop-controlled ac and dah, Saudi Arabia; North China Electric Power University
dc microgrids—A general approach toward standardization,” in Beijing; and Sharif University in Tehran. He is an IEEE
IEEE Trans. Ind. Electron., vol. 58, no. 1, pp. 158–172, Jan. 2011. Distinguished Lecturer, chair of the 2012 IEEE Innovative
F. Katiraei and M. R. Iravani, “Power management strat- Smart Grid Technologies Conference, chair of the 2012
egies for a micro-grid with multiple distributed generation Great Lakes Symposium on Smart Grid and the New Ener-
units,” IEEE Trans. Power Syst., vol. 21, no. 4, pp. 1821–1831, gy Economy, and editor-in-chief of IEEE Transactions on
Nov. 2006. Smart Grid. He was the recipient of the 2012 IEEE Power &
North American Electric Reliability Corporation. (2011, Energy Society Outstanding Power Engineering Educator
Jan.). Balancing and frequency control. [Online]. Available: Award. He is a Fellow of the IEEE.
http://www.nerc.com/docs/oc/rs/NERC%20Balancing%20 Mohammad E. Khodayar (mkhodayar@smu.edu)
and%20Frequency%20Control%20040520111.pdf received his B.S. and M.S. degrees in electrical engineering
M. Shahidehpour (2012, Oct.). A world-class university- from Amirkabir University of Technology (Tehran Poly-
industry consortium for wind energy research, education, technic) and Sharif University of Technology, respectively.
and workforce development. [Online]. Available: http:// He received his Ph.D. degree in 2012 in electrical engineer-
www.iitmicrogrid.net/windconsortium.aspx ing and was a visiting faculty member in 2013 at the
F. Katiraei, R. Iravani, N. Hatziargyriou, and A. Dimeas, ­Robert W. Galvin Center for Electricity Innovation at the
“Microgrids management,” IEEE Power Energy Mag., vol. 6, Illinois Institute of Technology. He is an assistant professor
no. 3, pp. 54–65, May–June 2008. in the Electrical and Computer Engineering Department at
R. H. Lasseter, “MicroGrids,” in Proc. IEEE Power Engi- Southern Methodist University in Dallas, Texas. He is a
neering Society Winter Meeting, 2002, pp. 305–308. Member of the IEEE. 

56 I E E E E l e c t ri f i c a t i on M a gaz ine / september 2013

You might also like