DAILY ACTIVITY REPORT

ABOU SULTAN PROJECT - CHP


28/04/2012

Serial Dredger Mawany 7 Dredger Mawany 11

Preparing Hyd. Pitons for sending to 3rd


Ongoing for removing valves and piping system for inspection and
1 party workshop for maintenance and test
clean activity
operation

Preparing Hyd. Pitons for sending to 3rd party workshop for


2 maintenance and test operation

Start working in Maine Engine Hatch & ventilation


Cover by inspection and repair with requesting items for maintenance
3 activity

4 Finish repair and maintenance for Some valves & pumps and store it till
installation activity and operation test

Start working in cleaning and preparation of cutting drive stave bearing


5
& trenion pin

Dredger 7 Maine Engine


Hatch Cover & Ventilation

Dredger 7 Maine Pipe & Valve