DAILY ACTIVITY REPORT

20 April, 2021 ABOU SULTAN PROJECT - CHP

Regarding the status of the Dredgers (Rust, Stuck),


Some of the mentioned activities require longer time than usual for dismantling and removing

Serial Dredger Mawany 7 Dredger Mawany 11

Inspection ladder drum and open gearbox


1 clutch then assembly ( finish and start install in Install tumble sheaves in dredger
dredger)

2 Continuous cleaning bilge Filling up by weld bulk head pipe

3 Continuous cleaning coolers

4 Start repair sea chest valve

5 Start gauging coupling cutter shaft to dismantle

Start remove compression head ( all bolts stuck


6
, start heating and weld nut on the top of bolt)

1|Page
DAILY ACTIVITY REPORT
20 April, 2021 ABOU SULTAN PROJECT - CHP

Items which purchasing for Mawany 7

‫كمية‬ ‫بيان‬ ‫م‬


‫متر‬5.3 Soft packing 6mm 1
1 ‫سم‬53‫فيلرمقاس‬ 2
1 ‫ك‬13 ‫جركن صابون سائل‬ 5
13 ‫اسطوانة تقطيع حديد‬ 4
2 ‫فرش سنفرة‬ 3