Impellors 5 0 3 2
Impellors 5 0 2 2 1
Order HRE10128
Bal
Item Description Order Qty Order Delivery to cust
1HD PUMP
Bearing Housing 4 4
Volute casing 6 6
Shafts 10 0 10
Gland follower 4 4
Open Impellors 10 0 10
2HD PUMP
Bearing Housing 4 4
Volute casing 6 6
Shafts 5 0 5
Gland follower 4 4
Open Impellors 10 0 5 5
3HD PUMP
Bearing Housing 5 5
Volute casing 6 4 2
Shafts 5 0 5
Gland follower 4 4
Open Impellors 10 0 10
Wear plates 6 0 6
Bal
Item Description - HRE10130 Order Qty Order Delivery to cust
80mm STGVA Impellor 5
Bal
Item Description - HRE10129 Order Qty Order Delivery to cust
GWEBI PROJECT
CRANE
LEYLAND DAF
MIMOSA PIPES
GENERATOR
MR MUKUMBI VEHICLE
RUSTLER
CUPOLA DISCHARGE
STAFF BUS
RUFARO TOYOTA
MR SIBANDA ISUZU
M/shop
M/c at Metal component To Collect Friday 22nd Jan
M/shop
Complete for invoicing customer alerted for collection.
M/shop
Casting sent back to the foundry for rework. Casting seem to have a casting defect/design problem which
needs to be attended to. Rectifying the pattern.
1 in machineshop. Rest returned to foundry after machining could not be drilled. Casting issues
Machining in progress
Castings seem to have a casting defect/design problem which needs to be attended to. Rework may be
required. Fettling
M/shop status
M/shop status
Machining now in progress .Two Completed to be taken for testing by client before doing the rest. (VM)
Gearbox to be sent for repairs on broken gears. Machine working with one hoist.
Parts sent out for repair awaiting payment to collect and assemble.
Contracted a team to complete the job. They quoted USD500. The understanding is if we buy aal the
required parts the machine should run by this weekend. Will monitor progress in the next 2 days and
see if we can get value for money.
Multiple defects to be repaired and VID inspection done. Parts being ordered in batches to control cash flow
Had a problem with pump for testing. We have since repaired the pump and are testing the pipes
They should be ready by 4/2/2021
8 completed and ready for delivery. The two which came recently have been stripped and awaiting quotes
for the supply of spare parts. To be completed by 9/2/2021