As per Nilesh only 5 nos Valve repairing done, expected despatch by 3rd July. For rest of the 7 nos
valve procurement action to be start.
PO to be release by Dhaval & material to be routed through Indure factory, Material ready to
despatch. Expected despatch from Indure factory 15th July.
SCM to release PO