SUBJECT : DAILY ACTIVITIES REPORT


Respectfully submitted herewith is the Daily Activities Report covering the period from 0700H 07 to 0700H 08
of December 2022. For your information and ready reference.

I. INCIDENT:

1. At around 1305H dated 07 December 2022, the Orient Square building have experienced unusual movement
of the building, which lasted for about just few seconds only. And no reading on the seismic accelerograph
device located at 6th floor Engineering Office. That according to the record from PHIVOLCS ( Philippine
Institute of Volcanology and Seismology ), the recorded intensity was intensity II at Pasig City. So, most of the
tenants have not felt the Earthquake. But some tenants voluntarily evacuated from their respective units using
fire exit going to ground floor and to the evacuation area in front of the building at Don Francisco Ortigas, Jr.
Road side. Assisted by Orient Square Emergency Response Team, Headed by the Incident Commander, Ms.
Sherdy C. Grabanzor. That the elevators were temporarily parked at ground floor for safety. Also, the parking
Entrance & Exit and the back door Entrance/Exit at Ruby Road side was temporarily closed. That the voluntary
evacuation started at around 1322H. Then after the last man Sg. Jay Satago, cleared the area from 37 th floor going
down and arrived at ground floor at around 1347H. After 3 minutes, at around 1350H the Incident Commander,
Ms. Grabanzor, announced that those who evacuated can go back to their respective units or Offices. That no
report of anyone got hurt due to this incident. Also, no damage of building equipment & facilities, and building
structure.

Page 1 of 10
II. SIGNIFICANT EVENT:

1. At around 0850H to 1715H dated 07 December 2022, two (2) personnel of Twincom/Globe, Mr. JD Dalisaymo
and Mr. Jomar Pelagio, conducted taking pictures of antenna, service unit component at 25 th floor unit-2503,
Iljin Wall Tech, Inc., 30th floor unit-3001 Golden Suntec Solutions, Inc., and at 35 th floor Blast Asia, Inc.,
monitored by Roving guard, Jay Satago.

2. At around 0850H
to 1000H dated 07 December 2022, Engineering Technicians, Mr. Nick Dela Cruz, and Mr. Chris Villadiego,
conducted dismantling of Transfer pump motor no. 2, at basement 6 cistern tank room, due to unusual noise on
motor pump during operation. Monitored by Basement 6 Roving guard, Roberto Mamaril.

3. At around 1205H to 1328H dated 07 December 2022, DPI-PAG. & PMG. Officers, Engr. Condrad V. Roque,
Engr. Vince Yap, Engr. Mark L. Alulod, Engr. Jaydick R. Leope, with TOSCAI-PMO, Ms. Sherdy C. Grabanzor,
Engr. Josenily J. Nautan, Jr., Engr. Marven Oropel, & Colliers Senior Manager, Mr. Dennis Marquez, had a
meeting at 6th floor Engineering Office with Kone Modernization Project Manager, Mr. Charles Reyes, regarding
neutral tapping. Also, the group, conducted inspection inside the Substation room at 6 th floor. Monitored by
Roving guard, Jay Satago.

Page 2 of 10
4. Continuation: At around 2012H dated 07 December 2022, to 0045H 08 December 2022, four (4) personnel of
Kone Installation Team, Mr. Rudy Paralejas, Mr. Jeffrey Arada, Mr. Honieval Olabre, and Mr. Redencio
Timblaco, conducted installation of plastic green mesh screen in between highrise elevator no. 2 & 3, from 37 th
floor to ground floor inside the tunnel. Assisted by three (3) personnel of Kone Modernization Team, Mr.
Gregorio Cruz, Mr. Godofredo Lining, and Mr. Ryan Dacuno. Monitored by Roving guard, Felipe Layan.

5. At around 2030H to 2050H dated 07 December 2022, Engineering Technicians, Mr. Dennis Bernal and Mr.
Daniel De Vera, conducted checking and functionality testing of the Earthquake device at ground floor electrical
room, 18th floor and 37th floor . And the result is normal. The device is functioning. Monitored by Security
Officer, Carlo Belleza.

III. ELEVATOR MONITORING:


Elevator No. Operational Parked Remarks
Service elevator 0600H-0400H 0400H-0600H Normal
LRE no. 1 0600H-0600H Normal

Page 3 of 10
LRE no. 2 0600H-0600H Normal
LRE no. 3 0600H-2000H 2000H-0600H Normal
MRE no. 1 0600H-0600H Normal
MRE no. 2 0600H-0600H Normal
MRE no. 3 0600H-1600H 1600H-0600H Normal
HRE no. 1 0600H-0000H 0000H-0600H Normal
0600H-2000H/
HRE no. 2 2000H-0000H Normal
0000H-0600H
HRE no. 3 Not operational since November 29, 2022.
Shuttle elev. 1 0600H-0600H Normal
Shuttle elev. 2 0600H-0600H Normal

IV. MAINTENANCE OPERATION:


a. Utilities Reading
Company Present Reading Previous Reading Difference Multiplier Consumption
MERALCO 53199 53187 12 1,750 21,000 kwh
Main Water Meter 976439 976267 172 1 172 m³

b. Equipment Standard
Units Equipment Present Reading Previous Reading
LVSG 1 (Power Running Consumption) 35214976 35205980
LVSG 2 (Power Running Consumption) 34674420 34668184
LVSG 3 (Power Running Consumption) 27802570 27795524
Gen set Fuel Day Tank 2,463 Liters
B-5 Fuel Tank Storage 1 19,511 Liters
B-5 Fuel Tank Storage 2 19,284 Liters
B-5 Fuel Tank Storage 3 19, 957 Liters
TRANSFORMER- 1 Reading Remark
Liquid Temperature Gauge 47
Vacuum Pressure Gauge 0
Oil Level 26
TRANSFORMER- 2
Liquid Temperature Gauge 45
Vacuum Pressure Gauge 0
Oil Level 27
TRANSFORMER- 3
Liquid Temperature Gauge 45
Vacuum Pressure Gauge 0
Oil Level 25
CISTERN TANK B-6
Tank no. 1 78%
Tank no. 2 78%
TRANSFER TANK 20th floor
Tank no. 1 62%
Tank no. 2 62%
DOMESTIC TANK 39th floor
Tank no. 1 72%
Tank no. 2 72%
FIRE TANK 39th floor
Tank no. 1 94%
Tank no. 2 94%
Tank no. 3 94%

V. FIT-OUT/ TENANT CONTRACTOR:


COMPANY SCOPE OF WORK LOCATION MANPOWER TIME IN/OUT
Clean Patrol General cleaning U1901-02 2 0656H-1106H
Hauling office equipment and
35th floor & 23rd
Blast Asia ( In-House ) furniture for transfer from 35th 4 0805H-2340H
floor unit-2306
floor to 23rd floor unit-2306
Taking photo of antenna and
Twincom/Globe 25th floor U2501 2 0830H-1735H
service unit component

Page 4 of 10
Clean Patrol General cleaning U3701/38th floor 4 1440H-1920H
The Law Office of Flores
Delivery and assemble of cabinet U2507 2 1740H-2117H
and Ofrin (In-House)
Pull-out of chairs for storage and 35th floor & 23rd
Blast Asia ( In-House ) 4 1834H-0700H
arrangement of office equipment floor unit-2306
AD Pineda Removal of tiles U1103 2 1922H-2152H

VI. TRADE/ BUILDING CONTRACTOR:


COMPANY SCOPE OF WORK LOCATION MANPOWER TIME IN/OUT
Hyper Kem STP operator Basement 1 STP room 1 0824H-2013H
Hyper Kem STP operator Basement 1 STP room 1 2011H-0845H
U1601, U1602, U1603-04,
U1606, U1607-08, U1801-
Airetech, Inc. Aircon maintenance 2 0655H-1610H
05, U1806-08, & 6th floor
Eng’g. Office
U1601, U1602, U1603-04,
U1606, U1607-08, U1801-
Airetech, Inc. Aircon maintenance 1 1315H-2205H
05, U1806-08, 6th floor
Eng’g. Office
Installation of plastic green
KONE Installation 37th floor to ground floor
mesh screen between HRE 4 1908H-0446H
Team inside the tunnel
no. 2 & 3
KONE Assist Kone Installation
37th to ground floor 3 1911H-0434H
Modernization Team & Monitoring

VII. INCOMING DELIVERIES:


FROM TO ITEMS / PARTICULARS TIME IN/OUT
Foodsphere/ CDO GN Power Ltd. Co. U1905-06 186 CDO products 0718H-0738H
2 unit Laptop, 4 units
Progressive Ideas The New APEC Dev’t. Corp. U1603-04 0812H-0823H
printer
Aqua 2000 Grand Nourriture International, Inc. U1602 4 bottles drinking water 0925H-0930H
ADB Water Refilling Unlimited Packing and Design U1206-07 9 bottles drinking water 0954H-1000H
Fuji film Boskalis Philippines, Inc. U3701/38th floor 1 pc toner 1000H-1011H
6 Gallons step off, 9
Thoroclean The Orient Square Admin. Office - 6th
gallons degreaser, 8 1020H-1037H
Marketing floor
gallons floor finish
DHL ACW Distribution (Phil’s.), Inc. U2301-02 1 box darktrace 1045H-1123H
Andaman Medical RESWERKES PHILS., INC. U1001 1 xmas gift 1055H-1108H
Gentech Industrial Boskalis Philippines, Inc. U3701/38th floor 1 pc binocular 1120H-1133H
Aqua Kiera Fusion BPO Services Phils., Inc. U601-02 25 bottles drinking water 1153H-1255H
FEDEX/2GO Exclusive Networks PH, Inc. U1505-06 1 box documents 1226H-1233H
Biz Asia Trading The New APEC Dev’t. Corp. U1603-04 1 unit stand fan 1258H-1320H
Integrated Computer BSI Group Philippines, Inc. U2408 1 unit printer 1300H-1309H
San Sui Tech
Kusum Healthcare Private Ltd. U2405-06 1 unit Macbook apple 1322H-1416H
Solutions
Hans Paper Corp. Philkoei International Inc. U1701-03 30 reams paperline 1400H-1412H
Stance Ergonomics Global Staff Connection, Inc. U2106 17 pcs. office chair 1416H-1627H
Water Genesis PH Global U2901 10 bottles drinking water 1420H-1452H
Aqua Roa Quantel Global Phil’s., Corp. U2401-02 6 bottles drinking water 1446H-1500H
H2O Life Source CCZ Information Technology U2104 5 bottles drinking water 1637H-1646H

VIII. PULL-OUT:
FROM BY ITEMS / PARTICULARS TIME IN/OUT
RESWERKES PHILS., INC. U1001 Esteban Q. Panis, Jr. 38 bags medical supplies 0852H
UC Biosciences U1904 Benedict Belarmino 3 bags medical test kits 0930H
EMAPTA Versatile Services, Inc. 2nd floor Geraldine Seria 1 unit Laptop with bag 1134H
EMAPTA Versatile Services, Inc. 2nd floor Loida Gentallan 3 units Laptop with bag 1416H
RESWERKES PHILS., INC. U1001 Cathy Dal 3 bags medical supplies 1417H
Seven Seven Global Services, Inc. 27th floor John Cris Simon 1 set Laptop 1457H
Unlimited Packing and Design U1206-07 Jeffrey Lasaten 40 folders 201 files 1548H

IX. OVERNIGHT VEHICLE MONITORING:


NO. COMPANY TYPE OF VEHICLE COLOR PLATE NO. SLOT PARKING

Page 5 of 10
NO. LEVEL
1. SMEC Philippines, Inc. T. Hilux Gray NFJ-7309 109 B-1
2. Blast Asia, Inc. Hy. Accent Silver WOU-233 121 B-1
3. Enfrausa Solutions, Inc. T. Altis Gold XST-559 122U B-1
4. PHILKOEI International, Inc. T. Hi-Ace White NEP-9674 123 B-1
5. PHILKOEI International, Inc. T. Innova Brown NCJ-6843 207 B-2
6. Ascenders Business Services T. Altis Gray XTE-796 213 B-2
7. SMEC Philippines, Inc. T. Innova Gray NCE-3997 215 B-2
8. Seven Seven Global Services, Inc. T. Innova White NFY-4446 224 B-2
9. Seven Seven Global Services, Inc. T. Innova Silver NEW-9200 225 B-2
10. Leverage Systems Technologies, Inc. M. L300 White UKE-413 226 B-2
11. The New APEC Development Corp. T. Vios Black NGO-7472 229 B-2
12. BSB Group, Inc. T. Vios Red XSJ-786 230 B-2
13. M.V.G.S. Law Office T. Innova Brown NCQ-8366 235 B-2
14. M.V.G.S. Law Office Mazda 2 Gray TQU-578 302 B-3
15. Syiaco Realty Corp. S. Forester Gray NET-3326 308 B-3
16. BSI Group Philippines, Inc. T. Rush Red CAL-5565 338 B-3
17. Exist Software Labs., Inc. S. Forester Gray ABF-5040 339 B-3
18. Optimum Source, Inc. T. Hiace Gray FDM-7498 402 B-4
19. Kusum Healthcare Private Ltd. T. Wigo Orange NFH-5477 405 B-4
20. Syiaco Realty Corp. F. Territory Black NID-2885 409 B-4
21. TAPServices Traviz White NES-5589 411 B-4
22. Syiaco Realty Corp. T. Corolla Blue WME-885 413 B-4
23. Enfrausa Solutions, Inc. Wuling Black U5J-839 421 B-4
24. Tin Ting Chan T. Alphard White NAI-2958 426 B-4
25. Syiaco Realty Corp. T. Innova Brown NDG-5259 440 B-4
26. Exist Software Labs., Inc. M. Benz Gray NBU-5098 441 B-4
27. ZZC Information Technology Carnival Black NGG-9101 447 B-4
28. Hypens Pharma Phils., Inc. T. Wigo Blue NCE-8415 503 B-5
29. Furukawa Sangyo Kaisha Phils., Inc. T. Rush Red DAQ-4825 507 B-5
30. Optimum Source, Inc. K. Rio White AAX-8855 510 B-5
31. Enfrausa Solutions, Inc. Hy. Starex Black NQT-205 513 B-5
32. Optimum Source, Inc. M. L300 White NBY-1275 515 B-5
33. Sensomed Philippines, Inc. M. L300 Silver WPI-123 522 B-5
34. Tan & Concepcion Law firm N. Urvan Silver NAG-3300 525 B-5
35. COGNITIF, Inc. Hy. Sonata White UIV-278 528 B-5
36. Quantel Global Phils. Corp. APV Black UGQ-636 531 B-5
37. Aiqon Unicorp. H. City Black NAK-6935 532 B-5
38. Aiqon Unicorp. H. Mobilo Black NDX-1368 533 B-5
39. TUV SUD PSB Philippines, Inc. T. Innova Silver NCY-9234 601 B-6
40. TUV SUD PSB Philippines, Inc. T. Vios Silver NCJ-3685 604 B-6
41. Seven Seven Global Services, Inc. N. Almera Gray NCT-8999 607 B-6
42. QUANTEL Philippines, Inc. T. Innova Silver TLI-864 609 B-6
43. SMEC Philippines, Inc. T. Fortuner Gray SMC-10 612 B-6
44. RESWERKES PHILS., INC. S. Celerio Gray NAK-7953 617 B-6
45. Seven Seven Global Services, Inc. Hy. Starex Gray UEQ-104 631 B-6

X. VISITORS:
LOW RISE HIGH RISE
TOTAL VISITORS : 153 TOTAL VISITORS : 72
Note: List of visitors slip available in housekeeping dept. upon request

XI. TOSCAI BUILDING ADMIN.


NAME DESIGNATION TIME IN/OUT
1. Ms. Sherdy C. Grabanzor Property Manager 0620H-1643H
2. Ms. Annaliza V. Velasco Admin. Assistant 0801H-1643H
3. Ms. Maylyn C. Mijares Bookkeeper 0738H-1643H

XII. TOSCAI BUILDING ENGINEERING.


NAME DESIGNATION TIME IN/OUT
1. Engr. Josenily G. Nautan, Jr. Building Engineer 0745H-1714H
2. Engr. Marven Oropel From Colliers Head Office 0747H-1714H
3. Paulino J. Montanes Senior Technician On leave
4. Aurelio E. Ventura Technician Day Off

Page 6 of 10
5. Dennis D. Bernal Technician 1352H-2204H
6. Mark David S. Morris BMS Technician 0546H-1521H
7. Michael P. Manalo BMS Technician 0907H-2332H
8. Daniel M. De Vera Technician 1334H-2337H
9. Nick M. Dela Cruz Technician 0600H-1541H
10. Henry M. Estacio Technician 2132H-0600H
11. Rolex L. Seroje Technician 2159H-0602H
12. Cris C. Villa Diego Technician 0502H-1542H

XIII. BUILDING HOUSEKEEPING AND RECEPTIONIST.


1. FIRST SHIFT
NAME DESIGNATION TIME IN/OUT
1. Edith M. Lazo Supervisor 0656H-1607H
2. Cyrene R. Ablat Housekeeping 0543H-1606H
3. Cristine Joy E. Lorido Housekeeping 0731H-1702H
4. Lilia B. Mente Housekeeping 0554H-1530H
5. Marivic Y. Perez Housekeeping 0537H-1531H
6. Cristina S. Pilango Housekeeping 0528H-1505H
7. Juliet T. Romero Receptionist 0655H-1711H
8. Maria Kristy Ticman Receptionist 0621H-1610H
9. Lenny A. Villanueva Receptionist 0850H-1803H
10. Jerome M. Calimotan Housekeeping 0502H-1606H
11. Philip A. Catarungan Housekeeping 0550H-1606H
12. John Cedric S. Chavez Housekeeping 0858H-1703H
13. Arsenio M. Franco Housekeeping 0754H-1703H
14. Jerald N. Ira Housekeeping 0520H-1512H
15. Jomarlon T. Lacambra Housekeeping 0457H-1606H
16. Rolly C. Ortaliza Housekeeping 0536H-1603H

2. SECOND SHIFT:
NAME DESIGNATION TIME IN/OUT
1. Archie C. Batino Housekeeping 1336H-2301H
2. Arnold J. Santos Housekeeping 1254H-2301H

3. NIGHT SHIFT:
NAME DESIGNATION TIME IN/OUT
1. Roberto A. Rubio Housekeeping 2245H-0803H

4. TENANTS GUARDS:
TOUR OF
NAME COMPANY/TENANT COMPANY/AGENCY
DUTY
1. Sg. Lingatong East West unibank U101-A 0720H-1800H E-Power Security Agency
2. Sg. Correa East West unibank U101-A 0850H-1838H E-Power Security Agency
3. Sg. Calma Fusion BPO Services Phils., Inc. U601 0600H-1800H 168 Security Agency
4. Sg. Ollagangi Fusion BPO Services Phils., Inc. U601 1800H-0600H 168 Security Agency
5. Sg. Arzaga Fusion BPO Services Phils., Inc. U601 1800H-0600H 168 Security Agency
6. Sg. Reyes Ascenders Business Services U1801-05 0800H-2000H First Delta Security Agency
7. Sg. Sibulo Seven Seven Global Services U2004-05 0600H-1800H Commanders Security Agency
8. Sg. Vila Seven Seven Global Services 27th flr. 0600H-1800H Commanders Security Agency
9. Sg. Del Rosario Seven Seven Global Services 27th flr. 1800H-0600H Commanders Security Agency

XIV. BUILDING SECURITY FORCE:


1st Shift
NAME POST DURATION
0700H-
1. Eugenio A. Carbonel Detachment Commander
1900H
0700H-
2. Jay A. Satago Highrise Area Roving 21st floor to Helipad
1900H
0700H-
3. Romeo M. Espinoza Lowrise Area Roving Ground floor to 20th floor
1900H
0700H-
4. Leonardo A. Berongoy Ground floor Center Lobby
1900H
5. Johnny O. Perez Don Francisco Ortigas, Jr., Entrance/Exit Lobby 0700H-1900H
6. Marlon O. Ildefonso Ruby Road side Entrance/Exit Lobby 0700H-1900H
7. Ryan V. Vidal Entrance Ramp - Ruby Road side 0700H-1900H
Page 7 of 10
8. Edmar P. Balendres Exit Ramp – Ruby Road side 0700H-1500H
9. Ace P. Policarpio Service Elevator Operator 0700H-1900H
0700H-
10. Redentor S. Tenoria Basement-1 Access Control
1900H
11. Emer U. Aguilar Basement 2 Roving/ Assist to Entrance ramp 0700H-1900H
12. Roberto T. Mamaril Basement-6 Roving/Assist to Basement 1 0700H-1900H

2nd Shift
NAME POST DURATION
1. Christopher G. Santing Exit Ramp – Ruby Road side 1500H-2300H

NIGHT SHIFT
NAME POST DURATION
1. Carlo M. Belleza Assistant Detachment Commander 1900H-0700H
2. Felipe S. Layan, Jr. Highrise Area Roving 21st floor to Helipad 1900H-0700H
3. Gilbert B. Manalo Lowrise Area Roving Ground floor to 20th floor 1900H-0700H
4. Christopher N. Romino Ground floor Center Lobby 1900H-0700H
5. Arnaldo S. Reano Don Francisco Ortigas, Jr., Entrance/Exit Lobby 1900H-0700H
6. Michael T. Samson Entrance Ramp - Ruby Road side 1900H-0700H
7. Gerry R. Gutierrez Basement-1 Access Control 1900H-0700H

NAME OTHER DURATION


1. Joseph T. Endico Day Off
2. Darwin B. Oliva Day Off

Parking Attendant
NAME POST DURATION
1. Mariano Saculo Parking Attendant 0600H-1500H
2. Glenn Salas Parking Attendant 1000H-1900H

XV. BUSTED LAMP:

1. Two (2) pcs. Halogen (Ground floor canopy area, F. Ortigas, Jr. Road side).
2. Three (3) pcs. Halogen (Ground floor canopy area, Ruby Road side).

XVI. INFORMATION:

1. Metro Waste collected 47 plastic bags of garbage at around 2052H dated 07 December 2022, monitored
by Sg. Christopher G. Santing (Exit ramp guard).

Prepared by:

SSG. CARLO M. BELLEZA


Asst. Det. Commander

Noted by:

SGS. EUGENIO A. CARBONEL


Detachment Commander

Cc : DPI-PAG.
Admin.
Eng’g.
Det. file

Page 8 of 10

You might also like