2.3. In which of the following organizations is the project manager MOST likely to be part-time?
A. Weak matrix
B. Strong matrix
C. Functional
D. Projectized
2.4. A project manager is trying to complete a software development project, but cannot get
enough attention for the project. Resources are focused on completing process-related
work and the project manager has little authority to properly assign resources. What form
of organization must the project manager be working in?
A. Functional
B. Matrix
C. Expediter
D. Coordinator
Kördere Sokak Çavdar Apt. No: 6/3, Kızıltoprak 34724 İstanbul Tel: 0
216 4491633 Faks: 0 216 4492848 e-posta : mentor@mentor.com.tr
www.mentor.com.tr
2.5. In a projectized organization the project team:
2.6. A project team member is talking to another team member and complaining that so many
people are asking him to do things. If he works in a functional organization, who has the
power to give direction to the team member?
A. All employees report to one manager and have a clear chain of command.
B. All employees report to two or more managers, but project team members show
loyalty to functional managers.
C. The organization is focused on projects and project work
D. Teams are collocated.
2.9. An organization where the project manager is in charge of the projects and has primary
responsibility for the resource is:
A. Functional
B. Projectized
C. Matrix
D. Hierarchial
Mentor Proje Yönetimi
________________________________________________________________________
Kördere Sokak Çavdar Apt. No: 6/3, Kızıltoprak 34724 İstanbul Tel: 0
216 4491633 Faks: 0 216 4492848 e-posta : mentor@mentor.com.tr
www.mentor.com.tr