1.1.You have been asked to take charge of project planning for a new project but you have
very little experience in managing projects. What will be the BEST source of help for you?
A. Your education
B. Your on-the-job training
C. Historical information
D. Your functional manager
1.2.You have been promoted to Manager, Continuous Process Improvement. Your new position:
1.4.You are the project manager for Fun Days Vacation Resorts. Your new project assignment is
to head up the Fun Days resort opening in Austin, Texas. You are estimating the duration of
the project plan activities, devising the project schedule and monitoring and controlling
deviations from the schedule. Which of the Project Management Knowledge Areas are you
working in?
1.7.You are a project manager working on gathering requirements end establishing estimates for
the project. Which process group are you in?
A. Planning
B. Executing
C. Initiating
D. Monitoring and Controlling
A. Company processes
B. The company culture
C. Historical WBSs
D. Project scope statement
1.9.The system that supports all aspects of the project management processes from initiating
through closing is:
A. Information technology.
B. The information distribution system.
C. The project management information system.
D. The work authorization system
A. Planning
B. Executing
C. Monitoring and controlling
D. Closing
1.11. The monitoring & controlling process group includes all of the following project
management processes EXCEPT:
A. Conduct Procurements
B. Report Performance
C. Validate Scope
D. Control Procurements
1.12. Evaluating overall project performance on a regular basis to ensure that it meets
expectations takes place in which process group of project management?
A. Planning
B. Executing
C. Monitoring and controlling
D. Closing