Professional Documents
Culture Documents
Special Specifications
18.1 Introduction
The use of special specifications should be minimized. Efforts should first be made to use
a standard specification. However, the use of a special specification is appropriate when
introducing new products or techniques. More detailed information on specification
procedure, item number prefixes and item number serialization is presented in Chapter 21
of the Highway Design Manual.
Once the decision to use a special specification has been made, the first step should be
to check if a suitable specification has been written for another project. The Design Quality
Assurance Bureau produces Addenda Catalogs listing the titles of thousands of special
specifications from Department projects. Separate catalogs are produced for metric and
common unit specifications. From these listings it may be possible to find an appropriate
special specification or at least something that can be used as a basis to create a new
special specification. The specification should be read to make sure it meets the project
needs. If it does, request that the Special Specification Coordinator have the specification
coded for use in the project. The request should include:
18 - 1 4/2005
NYSDOT Bridge Manual
If no specification is available that covers the situation, then it is necessary to write a new
specification either by modifying an existing specification or starting from scratch.
Special specifications should mirror the standard specifications as much as possible. All
special specifications contain the same six elements, either by inclusion or by reference.
These elements are:
C Title - This should be a short description of the main portion of the work; it may
be four lines long.
C Description - This is a more detailed statement of the work involved.
C Materials - Material requirements should reference readily available standards,
such as:
These less desirable call outs may require justification, See Chapter 21 of the
Highway Design Manual for more information. To prevent delays during
construction and prevent misinterpretation, the designer should communicate
their intent for the ‘or equal’ to the group designated. In Technical Services,
coordination with the Materials or Geotechnical Engineering staff is appropriate
as construction and specification questions are directed to them by their regional
counterparts. In most cases, Materials or Geotechnical Engineers are already
involved, if not, their involvement should be sought by the designer.
18 - 2 4/2005
Section 18 - Special Specifications
C Basis of Payment - In addition to stating what is included in the bid price, this
section should state what is excluded from the cost (e.g., "The unit price bid shall
include the cost of all labor, materials and equipment necessary to complete the
work, except excavation will be paid under separate item(s)"). Progress
payment schedules should be included as appropriate.
18 - 3 4/2005
NYSDOT Bridge Manual
All the provisions of Section 603 pertaining to Round Corrugated Steel Pipe shall
apply and in addition the Contractor shall plug each end of the pipe with standard
galvanized steel end plugs.
The cost of furnishing and installing the end plugs shall be included in the price
bid for this item.
Page 1 of 1
February 4, 1997
C Pay item and the five main section titles should be in Universal 11 point Bold
Underlined type.
18 - 4 4/2005
Section 18 - Special Specifications
A more complex specification including all six elements would appear as:
DESCRIPTION
This work shall consist of furnishing and erecting Fascia Precast Concrete Beams as shown
on the Contract Plans and in accordance with these specifications.
MATERIALS
The Fascia Precast Concrete Beams shall meet the requirements of the P.C.C.M. Bolts, nuts,
washers and plates used for anchoring the Fascia Precast Concrete Beams shall meet the
requirements of ASTM F568M, A563M, F463M and A709M GRADE 250 respectively and
shall be galvanized in accordance to Section 719-01.
CONSTRUCTION DETAILS
The requirements of the P.C.C.M. shall apply in their entirety. In lieu of the precast beam
shown on the Contract Plans, the Contractor shall have the option of submitting his own
design to the D.C.E.S. for approval. In submitting such a design, the Principal-Controlling
Dimensions shall not be altered. The Contractor may also provide extra prestressing steel
in the beam shown on the Contract Plans for handling and transporting.
METHOD OF MEASUREMENT
The Contractor will be paid the Lump Sum price bid for the "Fascia Precast Concrete Beams".
BASIS OF PAYMENT
The Lump Sum bid price shall include the cost of labor, materials and equipment necessary
to complete the work.
18 - 5 4/2005