Estimate I Beam

The document provides a bill of materials and estimate for a proposed warehouse office project. It includes 7 items with descriptions and quantities of materials needed, as well as unit costs and totals. The main materials are for earthworks, concrete works, reinforcement, masonry works, forms and scaffolding, plumbing works, and electrical works. The total estimate includes materials and labor costs for each item.

Uploaded by

Edward Cardenas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
781 views6 pages

Estimate I Beam

The document provides a bill of materials and estimate for a proposed warehouse office project. It includes 7 items with descriptions and quantities of materials needed, as well as unit costs and totals. The main materials are for earthworks, concrete works, reinforcement, masonry works, forms and scaffolding, plumbing works, and electrical works. The total estimate includes materials and labor costs for each item.

Uploaded by

Edward Cardenas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

BILL OF MATERIALS AND ESTIMATE

PROJECT TITLE: PROPOSED WAREHOUSE OFFICE


LOCATION :TUGUEGARAO CTY, CAGAYAN
OWNER :
,

ITEM DESCRIPTION QTY UNIT UNIT COST AMOUNT


1 MOBILIZATION
Demolition 1 sq. m

2 EARTH WORKS
Excavation 21.6 sq.m ₱ 400.00 ₱ 8,640.00
Back Fill cu.m ₱ 400.00 ₱ -
Soil Poisoning lot
MATERIAL COST ₱ -
LABOR COST ₱ 8,640.00

3 CONCRETE WORKS
GROUND
Column Footing
Portland Cement 32.00 bags ₱ 240.00 ₱ 7,680.00
Fine Aggregates 1.80 cu.m ₱ 550.00 ₱ 990.00
CRS Aggregates 3.50 cu.m ₱ 600.00 ₱ 2,100.00
Column
Portland Cement 31.00 bags ₱ 240.00 ₱ 7,440.00
Fine Aggregates 1.80 cu.m ₱ 550.00 ₱ 990.00
CRS Aggregates 3.50 cu.m ₱ 600.00 ₱ 2,100.00
Tie Beam
Portland Cement 18.00 bags ₱ 240.00 ₱ 4,320.00
Fine Aggregates 1.20 cu.m ₱ 550.00 ₱ 660.00
CRS Aggregates 1.80 cu.m ₱ 600.00 ₱ 1,080.00
Stair
Portland Cement 23.00 bags ₱ 240.00 ₱ 5,520.00
Fine Aggregates 1.60 cu.m ₱ 550.00 ₱ 880.00
CRS Aggregates 2.70 cu.m ₱ 600.00 ₱ 1,620.00

SECOND FLOOR
Slab
Portland Cement 174.00 bags ₱ 240.00 ₱ 41,760.00
Fine Aggregates 9.70 cu.m ₱ 550.00 ₱ 5,335.00
CRS Aggregates 19.30 cu.m ₱ 600.00 ₱ 11,580.00
Roof Beam
Portland Cement 24.00 bags ₱ 240.00 ₱ 5,760.00
Fine Aggregates 1.20 cu.m ₱ 550.00 ₱ 660.00
CRS Aggregates 2.40 cu.m ₱ 600.00 ₱ 1,440.00

MATERIAL COST ₱ 101,915.00


LABOR COST ₱ 61,149.00

4 REINFORCEMENT
GROUND
Column Footing
16mm Ø RSB x 6m 24.00 pcs ₱ 410.00 ₱ 9,840.00
Tie Wire #16 4.60 kgs ₱ 70.00 ₱ 322.00
Column
16mm Ø RSB x 6m 72.00 pcs ₱ 410.00 ₱ 29,520.00
10mm Ø RSB x 6m 124.00 pcs ₱ 142.00 ₱ 17,608.00
Tie Wire #16 21.00 kgs ₱ 70.00 ₱ 1,470.00
Tie Beam
12mm Ø RSB x 6m 24.00 pcs ₱ 410.00 ₱ 9,840.00
10mm Ø RSB x 6m 60.00 pcs ₱ 142.00 ₱ 8,520.00
Tie Wire #16 9.00 kgs ₱ 70.00 ₱ 630.00
Beam
I-Beam 6.00 pcs ₱ 12,000.00 ₱ 72,000.00
Welding Rod 8.00 kgs ₱ 70.00 ₱ 560.00
Stair
12mm Ø RSB x 6m 32.00 pcs ₱ 410.00 ₱ 13,120.00
10mm Ø RSB x 6m 48.00 pcs ₱ 142.00 ₱ 6,816.00
Tie Wire #16 4.00 kgs ₱ 70.00 ₱ 280.00
SECOND FLOOR
Slab
10mm Ø RSB x 6m 224.00 pcs ₱ 142.00 ₱ 31,808.00
Tie Wire #16 64.00 kgs ₱ 70.00 ₱ 4,480.00
Roof Beam
16mm Ø RSB x 6m 24.00 pcs ₱ 410.00 ₱ 9,840.00
12mm Ø RSB x 6m 60.00 pcs ₱ 410.00 ₱ 24,600.00
Tie Wire #16 9.00 kgs ₱ 70.00 ₱ 630.00

MATERIAL COST ₱ 241,884.00


LABOR COST ₱ 145,130.40

5 MASONRY WORKS
CHB 4" - Second Floor 4266.00 pcs ₱ 13.00 ₱ 55,458.00
Portland Cement(Mortar and 359.00 bags ₱ 240.00 ₱ 86,160.00
Screened Sand (Mortar) 14.30 cu.m ₱ 500.00 ₱ 7,150.00
Fine Sand (Plastering) 10.50 cu.m ₱ 500.00 ₱ 5,250.00
10mm x 6.00m Rsb 233.00 pcs ₱ 142.00 ₱ 33,086.00
Tie Wire 15.30 kgs ₱ 80.00 ₱ 1,224.00
MATERIAL COST ₱ 188,328.00
LABOR COST ₱ 160,078.80

6 FORMS AND SCAFFOLDINGS


Lumpsum ₱ 75,000.00

MATERIAL COST ₱ 75,000.00


LABOR COST ₱ 41,250.00

7 PLUMBING WORKS
Water Line
PVC Pipes (12.7mm) 6.00 pcs ₱ 76.22 ₱ 457.32
PVC Coupling (12.7mm) 8.00 pcs ₱ 10.00 ₱ 80.00
PVC Tee (12.7mm) 12.00 pcs ₱ 15.00 ₱ 180.00
PVC Elbow (12.7mm) 15.00 pcs ₱ 15.00 ₱ 225.00
Female Adaptor 8.00 pcs ₱ 8.00 ₱ 64.00
Solvent 4.00 can ₱ 184.00 ₱ 70.00
Sanitary Line
100mm Dia. PVC 6.00 pcs ₱ 480.00 ₱ 2,880.00
50mm Dia. PVC 8.00 pcs ₱ 320.00 ₱ 2,560.00
PVC Clean Out 100mm dia. 4.00 pcs ₱ 100.00 ₱ 400.00
PVC Clean Out 50mm dia. 4.00 pcs ₱ 75.00 ₱ 300.00
PVC P-Trap 50mm dia. w/ plug 4.00 pcs ₱ 70.00 ₱ 70.00
PVC Tee 100mm dia. 2.00 pcs ₱ 92.00 ₱ 184.00
PVC Wye 100mm 6.00 pcs ₱ 97.00 ₱ 582.00
PVC Wye 50mm 6.00 pcs ₱ 70.00 ₱ 420.00
PVC Elbow 90 deg. (100mm) 2.00 pcs ₱ 64.00 ₱ 128.00
PVC Elbow 90 deg. (50mm) 7.00 pcs ₱ 64.00 ₱ 448.00
Plumbing Fixtures and Acce.
Bronze Faucets- 1/2" diameter 3.00 pcs ₱ 175.00 ₱ 525.00
Lavatory with Fittings and Acc. 2.00 sets ₱ 6,000.00 ₱ 12,000.00
Kitchen Sink 1.00 pcs ₱ 900.00 ₱ 900.00
4" Floor Drain 3.00 pcs ₱ 250.00 ₱ 750.00
Gate Valve 1" 2.00 pcs ₱ 394.00 ₱ 788.00
GI Nipple 1/2 diameter 5.00 pcs ₱ 23.00 ₱ 115.00
Tefflon Tape 10.00 pcs ₱ 10.00 ₱ 100.00
Elongatedd Water Closet with
2.00 sets ₱ 12,000.00 ₱ 24,000.00
Accessories
Toilet Paper Holder 2.00 pcs ₱ 262.00 ₱ 524.00
Soap Holder 2.00 sets ₱ 750.00 ₱ 1,500.00
Solvent 8.00 can ₱ 184.00 ₱ 1,472.00

MATERIAL COST ₱ 51,722.32


LABOR COST ₱ 36,205.62

8 ELECTRICAL WORKS
Rough-ins
Panel box 1.00 pcs ₱ 6,000.00 ₱ 6,000.00
GE Circuit Breaker 20A 2P 2.00 pcs ₱ 500.00 ₱ 1,000.00
GE Circuit Breaker 50A 2P 4.00 pcs ₱ 650.00 ₱ 2,600.00
GE Circuit Breaker 100A 2P 1.00 pcs ₱ 950.00 ₱ 950.00
Weather Proof Outlet 6.00 pcs ₱ 798.00 ₱ 4,788.00
Convinience outlet 24.00 pcs ₱ 250.00 ₱ 6,000.00
Stranded Wire #14, THHN 2.0 (Phelp
6.00 boxes ₱ 2,700.00 ₱ 16,200.00
Dodge 150m)
Stranded Wire #14, THHN 3.5 (Phelp
3.00 boxes ₱ 2,700.00 ₱ 8,100.00
Dodge 150m)
Stranded Wire #14, THHN 5.5 (Phelp
3.00 boxes ₱ 2,700.00 ₱ 8,100.00
Dodge 150m)
1 - Gang Switch 2.00 pcs ₱ 120.00 ₱ 240.00
2 - Gang Switch 7.00 pcs ₱ 150.00 ₱ 1,050.00
3 - Gang Switch 5.00 pcs ₱ 190.00 ₱ 950.00
Junction Box 50.00 pcs ₱ 30.00 ₱ 1,500.00
Utility Box 45.00 pcs ₱ 25.00 ₱ 1,125.00
1/2" ELECTRICAL PVC PIPE 50.00 pcs ₱ 75.00 ₱ 3,750.00
3/4" ELECTRICAL PVC PIPE 35.00 pcs ₱ 90.00 ₱ 3,150.00
1/2" PVC LONG ELBOW 30.00 pcs ₱ 30.00 ₱ 900.00
3/4" PVC LONG ELBOW 25.00 pcs ₱ 75.00 ₱ 1,875.00
Electrical tape 8.00 pcs ₱ 65.00 ₱ 520.00
Rubber Tape 6.00 pcs ₱ 80.00 ₱ 480.00
Butane Gas 4.00 pcs ₱ 100.00 ₱ 400.00
Lighting Fixtures
Pinlights 38.00 pcs ₱ 350.00 ₱ 13,300.00
Center Light 10.00 pcs ₱ 1,200.00 ₱ 12,000.00
Wall light 7.00 pcs ₱ 750.00 ₱ 5,250.00
Downlight 10.00 pcs ₱ 500.00 ₱ 5,000.00
Strip Light 50.00 mts ₱ 150.00 ₱ 7,500.00

MATERIAL COST ₱ 114,528.00


LABOR COST ₱ 74,443.20

9 FENESTRATION
note:complete with accessories
DOOR
D-1 (1.00 x 2.50m )- 1 set 1.00 set/s ₱ 15,000.00 ₱ 15,000.00
D-2 (0.90 x 2.10m )- 3 sets 3.00 set/s ₱ 8,000.00 ₱ 24,000.00
D-3 (0.60 x 2.10m )- 1 set 1.00 set/s ₱ 5,500.00 ₱ 5,500.00
D-4 (0.60 x 2.10m)- 2 sets 2.00 set/s ₱ 4,800.00 ₱ 9,600.00
WINDOWS
W-1 (3.70 x 1.80m) - 1 set 6.60 sqm ₱ 3,000.00 ₱ 19,800.00
W-2 (4.80 x 1.20m) - 2 sets 11.52 sqm ₱ 3,000.00 ₱ 34,560.00
W-3 (0.60 x 2.00m) - 4 sets 4.80 sqm ₱ 3,000.00 ₱ 14,400.00
W-4 (2.40 x 1.20m) - 1 set 2.88 sqm ₱ 3,000.00 ₱ 8,640.00
W-5 (1.20 x 0.60m) - 1 set 0.72 sqm ₱ 3,000.00 ₱ 2,160.00
W-6 (0.60 x 0.60m) - 2 sets 0.72 sqm ₱ 3,000.00 ₱ 2,160.00

MATERIAL COST ₱ 135,820.00


LABOR COST ₱ 54,328.00
10 TILEWORKS
.60 x .60 Ceramic Tile 596.00 pcs ₱ 250.00 ₱ 149,000.00
.60 x .60 Non-Skid Tile 198.00 pcs ₱ 250.00 ₱ 49,500.00
.30 x .60 Wall Tiles(Comfort Room) 162.00 pcs ₱ 90.00 ₱ 14,580.00
.30 x .30 Ceramic Tiles 112.00 pcs ₱ 45.00 ₱ 5,040.00
.30 x .60 Accent Wall (Kitchen) 6.00 pcs ₱ 175.00 ₱ 1,050.00
.60 x .60 Ceramic Tile (Kitchen Counter) 6.00 pcs ₱ 200.00 ₱ 1,200.00
Portland Cement 25.00 bags ₱ 240.00 ₱ 6,000.00
Pure Sand 9.50 cu.m ₱ 500.00 ₱ 4,750.00
Tile Adhesive 32.00 bags ₱ 250.00 ₱ 8,000.00
Tile Grout 2kg 64.00 bags ₱ 50.00 ₱ 3,200.00
Diamond Cutter 4.00 pcs ₱ 50.00 ₱ 200.00

MATERIAL COST ₱ 242,520.00


LABOR COST ₱ 121,260.00

11 CEILING WORKS
1/4" thk Hardiflex 78.00 pcs ₱ 420.00 ₱ 32,760.00
Wall Angle (3.0 m L) 84.00 pcs ₱ 55.00 ₱ 4,620.00
Metal Furring 203.00 pcs ₱ 95.00 ₱ 19,285.00
Carrying Channel 163.00 pcs ₱ 110.00 ₱ 17,930.00
W-Clip 600.00 pcs ₱ 7.00 ₱ 4,200.00
1/8" Drill Bit (concrete) 10.00 pcs ₱ 90.00 ₱ 900.00
1/8" Drill Bit (steel) 30.00 pcs ₱ 80.00 ₱ 2,400.00
Blind Rivets 1/8 x 3/4 8.00 box ₱ 320.00 ₱ 2,560.00
Blind Rivets 1/8 x 1/2 6.00 box ₱ 280.00 ₱ 1,680.00

MATERIAL COST ₱ 86,335.00


LABOR COST ₱ 56,117.75

12 PAINTING WORKS
Walls
a. Penetrating Sealer 4.00 pails ₱ 2,100.00 ₱ 8,400.00
b. Primer 6.00 pails ₱ 2,300.00 ₱ 13,800.00
c. SkimCoat 4.00 bags ₱ 320.00 ₱ 1,280.00
d. Wall Putty 12.00 gal ₱ 400.00 ₱ 4,800.00
e. Topcoat (Semi-gloss)-Ready
8.00 pails ₱ 2,800.00 ₱ 22,400.00
Mixed
f. AcryColor 4.00 ltr ₱ 300.00 ₱ 1,200.00
g. Water Proofing 16.00 gal ₱ 650.00 ₱ 10,400.00

OTHERS
Painting Materials 1.00 lumpsum ₱ 15,000.00 ₱ 15,000.00

MATERIAL COST ₱ 77,280.00


LABOR COST ₱ 69,552.00

13 ROOFING WORKS
Roofing Sheet 240.00 lm ₱ 270.00 ₱ 64,800.00
C-Purlins (2"x4"x6m) 79.00 pcs ₱ 415.00 ₱ 32,785.00
Angle Bar (2''x2''x20') 37.00 pcs ₱ 1,350.00 ₱ 49,950.00
Gutter 12.00 pcs ₱ 750.00 ₱ 9,000.00
Laquer thinner 6.00 gal ₱ 410.00 ₱ 2,460.00
Epoxy Primer 8.00 gal ₱ 715.00 ₱ 5,720.00
Welding Rod 30.00 kgs ₱ 100.00 ₱ 3,000.00
Tekscrew 500.00 pcs ₱ 2.00 ₱ 1,000.00
Sealant 6.00 tubes ₱ 300.00 ₱ 1,800.00
Vulca Seal 6.00 litr ₱ 550.00 ₱ 3,300.00

MATERIAL COST ₱ 173,815.00


LABOR COST ₱ 95,598.25

14 MISCELLANEOUS ITEM
STAIR
2x2 Tubular Bar 16.00 pcs ₱ 600.00 ₱ 9,600.00
2x3 Tubular Bar 4.00 pcs ₱ 750.00 ₱ 3,000.00
Laquer thinner 1.00 gal ₱ 410.00 ₱ 410.00
Epoxy Primer 3.00 gal ₱ 715.00 ₱ 2,145.00
Welding Rod 3.00 box ₱ 450.00 ₱ 1,350.00

MATERIAL COST ₱ 16,505.00


LABOR COST ₱ 11,553.50

15 TOTAL MATERIAL COST ₱ 1,505,652.32


16 TOTAL LABOR COST ₱ 775,227.72
17 SUPERVISION ₱ 45,169.57
CONTINGENCY ₱ 30,113.05
TOTAL PROJECT COST ₱ 2,356,162.66

Prepared by: Approved by:

MARLON C. DUMLAO, UAP


ARCHITECT OWNER