Project Title: PROPOSED CARWASH

Owner:
Location:

BILL OF MATERIALS

Description Quantity Unit Price Amount


II. CONCRETE AND MASONRY WORK
 Portland Cement 50 bags P220.00/bag P 11,000.00
 Washed Sand 4 cu.m. 1,200.00/cu.m. 4,400.00
 ¾ crushed gravel 6 cu.m. 1,3000.00/cu.m. 7,500.00
 G. I. Tie wire #16 6 kgs. 85/kg 510.00
Sub Total P 23,410.00
III. REINFORCING CONCRETE BARS
 10 mm dia. X 6m dsb 85 pcs. P140.00/pc. P 11,900.00
Sub Total P 11,900.00
V. ROOFING WORKS
 L.S. L.S. L.S. P 22,720.00
Sub Total P 22,720.00
VII. STEEL WORKS
 1-1/2" x 1-1/2" x 1/4 Angle bar 4 pcs. P680.00/pc. P 2,720.00
 2" x 4" C-Channel 15 pcs. 1,750.00/pc. 26,250.00
 2" x 3" x 6m C-Purlins 15 pcs. 370.00/pc. 5,500.00
 2" x 8" x 6m C-Purlins 3 pcs. 990.00/pc. 2,970.00
 3" G.I. Pipe 4 pcs. 4,000.00/pc. 16,000.00
 Tecksrcew 1,130 pcs. 3.50/pc. 3,955.00
 Welding Rod 5 kgs. 105.00/kg. 525.00
Sub Total P 57,970.00

X. PLUMBING WORKS
 L.S. L.S. L.S. P 5,000.00
Sub Total P 5,000.00
XI. ELECTRICAL WORKS WITH FIXTURES
 L.S. L.S. L.S. P 4,000.00
Sub Total P 4,000.00

Materials 125,000.00
Labor 25,000.00
GRAND TOTAL ₱ 150,000.00

Prepared by: