KaymonCon REV No 1
REV DATE 23/11/2022
1. PURPOSE
To ensure that installation of tiles and related activities are executed safely and following the
contract requirements and that all quality assurance/control tasks are carried out methodically,
works are observed and conformance is verified and recorded.
2. SCOPE
This procedure applies to the following works associated with Tiles
3. RESPONSIBILITIES
CONTRACTOR Project Manager shall be responsible for the overall implementation of
this procedure.
CONTRACTOR Site Engineer / Site Supervisor / Surveyor/ Foreman shall ensure that
plastering works are carried out as per specification, drawings and method statements.
CONTRACTOR Quality Assurance /Quality Control Engineer along with QC Engineer
shall ensure that works are carried out as per the project’s requirements. He is responsible for
the implementation of related QA/QC works as detailed in the Quality procedure and Quality plan
for plastering works. He shall also coordinate with the worksite laboratory for testing of
material/substances related to plasterwork activities.
CONTRACTOR HSE Officer along with safety officer shall ensure implementation of
all safety Procedure, safety measures related to the nature of works being carried out and
following the HSE Plan.
4. EQUIPMENT
The Personal equipment, devices and machinery involved in Acoustic works are listed
below:
Tile Cutters
trawel
Rubber Mallet
Water Levelling Tool
5. SAFETY HAZARDS AND CONTROL MEASURES
A. Hazards and Control Measures
Dust: Dust entering eyes and breathing system.
Control Measure: Use PPE- Mask, Goggles.
B. Housekeeping: Unauthorized movement of persons. Bad housekeeping.
Control Measure: Barricade area. Warning signs. Toolbox talk.
C. Scaffolding: Defective scaffolding.
Control Measure: Use Approved Materials. Use experienced scaffolders and check it regularly.
6. PROCEDURE
6.1 General
Submittals, Fabrication and manufacture, Product delivery, storage, materials shall be as
SOR item’s description and recommendations.
Necessary Work Permit and materials approvals shall be secured from
MANAGER/COMPANY. All necessary precautions shall be complied with.
Before any application, final inspection for surface preparation of substrate shall be
made.
6.2 Installation
6.2.1 Wall Tiling (Ceramic)-Internal walls
Back up plastering shall be done all following method statement Ref. 1
DOC No SWP 1
KaymonCon REV No 1
REV DATE 23/11/2022