Project Title: PROPOSED SWIMMING POOL

Owner:
Location:

BILL OF MATERIALS

Description Quantity Unit Price Amount


I. EARTHWORK
 Excavation L.S. L.S. P 35,000.00
 Backfilling Materials L.S. L.S. 10,000.00
Sub Total P 45,000.00
II. FORM WORKS
 ½ thk. Ordinary plywood 65 pcs. P460.00/pc P 29,900.00
 G. I. Tie wire #16 22 kgs. 85.00/kg 1,870.00
 C.W. Nail Assorted size 12 kgs. 80.00/kg. 960.00
 Coco lumber 40-2x3x12 950 pcs. 25.00/pc. 23,750.00
Sub Total P 56,480.00
III. CONCRETE AND MASONRY WORK
 Portland Cement 682 bags P235.00/bag P 156,860.00
 Washed Sand 42 cu.m. 1,100.00/cu.m. 46,200.00
 ¾ crushed gravel 40 cu.m. 1,300.00/cu.m. 52,000.00
 5” CHB 1150 pcs. 9.50/pc. 10,925.00
Sub Total P 265,985.00
IV. REINFORCING CONCRETE BARS
 10 mm dia. X 6m dsb 50 pcs. P145.00/pc. P 7,250.00
 12 mm dia. X 6m dsb 144 pcs. 225.00/pc. 32,400.00
 16 mm dia. X 6m dsb 75 pcs. 360.00/pc. 27,000.00
Sub Total P 66,650.00

V. PLUMBING WORKS
 L.S. L.S. L.S. P 40,000.00
Sub Total P 40,000.00

VI. FINISHING WORKS


 L.S. L.S. L.S. P 68,470.00
Sub Total P 68,470.00

Materials 542,585.00
Labor 170,415.00
GRAND TOTAL ₱ 713,00.00