PLUMBING

(2) TOILET LEAKAGES IN THE STAFF QUARTERS


S/N MATERIALS QUANTIT UNIT PRICE PRICE (N)
Y (N)
1. 1216 PIPE 30M 700 21,000
2. 1216 ELBOW 16 750 12,000
3. 1216 TEE 8 800 6,400
4. 1216 CONTROL 2 3,700 7,400
5. 1216 STRAIGHT UNION 6 600 3,600
6. 1216 X 1620 STRAGHT UNION 6 600 3,600
7. 1216 X 1620 MALE STRAGHT UNION 1 550 550
8. PLASTER SAND 7 250 1,750
9. ONE HELPER 5 DAYS 4,000 20,000
TOTAL 76,300

KITCHEN WASTE PIPING BLOCKAGE


S/N MATERIALS QUANTIT UNIT PRICE PRICE (N)
Y (N)
1. 2” PIPE 1 1,500 1,500
2. 2” ELBOW 6 200 1,200
3. 2” TEE 1 300 300
4. 2” 45 BEND 3 200 600
5. CEMENT 1 2,600 2,600
6. SAND 6 250 1,500
7. LABOR FOR DIGGING 1 PERSON 3,000 3,000
TOTAL 10,700

BOYS’ HOSTEL
S/N MATERIALS QUANTIT UNIT PRICE PRICE (N)
Y (N)
PUMP WASTE 1 2,000 2,000
SHOWER HEAD 1 2,500 2,500
WATER HEATER (30 LTR) (HOUSE PRNT’S ROOM) 1 33,000 33,000
TOTAL 37,500
GIRLS’ HOSTEL
S/N MATERIALS QUANTIT UNIT PRICE PRICE (N)
Y (N)
1. 11/2 BLACK NUTE 1 2,000 2,000
2. 14/3 NIPPLE 6 600 600
3. 14/3 REDUCER 2 1,000 2,000
4. 11/4 X 1” REDUCER 2 1,500 3,000
5. BATH MIXER 2 8,000 16,000
TOTAL 23,600

CAFETERIA
S/N MATERIALS QUANTIT UNIT PRICE PRICE (N)
Y (N)
1. BASIN TAP 4 2,500 2,500
2. WASHING TANKS 30,000 30,000
3. CHLORINE 5,000 5,000
4. EVACUATION OF SOAKAWAY 10 TRIPS 15,000 150,000
TOTAL 187,500

SCHOOL BLOCK
S/N MATERIALS QUANTIT UNIT PRICE PRICE (N)
Y (N)
1. ANGLE VALVE 7 1,200 8,400
2. W.C. NUBS 2 3,000 6,000
3. FLEXIBLE CONNECTOR 10 350 3,500
4. CABINET BASIN 1 9,000 9,000
5. FLOW MASTER 2 3,000 6,000
6. ADJUSTABLE WASTE 4 600 600
7. LAB TAP 3 7,000 21,000
8. ADJUSTABLE WASTE 4 600 2,400
9. ANGLE VALVE 4 1,200 4,800
TOTAL 61,700

EARLY YEARS
S/N MATERIALS QUANTIT UNIT PRICE PRICE (N)
Y (N)
1. W.C (POPOOLA) 1 25,000 25,000
2. BASIN TAP 1 2,500 2,500
3. SILICON GUM 4 1,200 4,800
4. FLEXIBLES 10 350 3,500
TOTAL 35,800
MASONROY
1. DOOR FRAME REFIXING (EARLY YEARS)
2. CHINA DOOR REFIXING (EARLY YEARS)
3. CASTINGOF SAOKAWAY SIDES
4. MINOR PLASTERINGS

MATERIALS

S/N ITEM QUANTIT UNIT PRICE PRICE (N)


Y (N)
1. SHARP SAND 3 BAGS 300 900
2. GRAVEL 2 BAGS 300 600
3. PLASTER SAND 2 BAGS 300 600
4. CEMENT 11/2 BAGS 2600 3,900
5. 4” NAILS 1 PAN 350 350
6. LABOR 13,500 13,500
TOTAL 19,850
TILING

S/N ITEM QUANTITY UNIT PRICE PRICE (N)


(N)
1. BOYS’ HOSTEL: 40 X 40 mm TILES 6m2 1,300 7,800
2. NEW HALL: 40 X 40 mm TILES 10m2 1,300 13,000
3. KITCHEN FLOOR: 30 X 60 mm TILES 6m2 3,000 18,000
4. KITCHEN WALLS: 25 x 50 mm TILES 1.5m2 2,850 2,850
2
5. S. Q. KTCHN/BTHROOM WALL: 25 X 40 mm TILES 1.5+6=7.5m 1,300 9,750
6. SHARP SAND 17 BAGS 200 3,400
7. CEMENT 6 BAGS 2,600 15,600
8. TILE GUM 2 BAGS 2,000 4,000
9. LABOR - 49,000 49,000
TOTAL 123,400
WELDING
S/N ITEM QUANTIT UNIT PRICE PRICE (N)
Y (N)
1. BOLT FOR GIRLS’ HOSTEL 7 500 3,500
2. SMALL PIPE FOR BOYS’ HOSTEL 1 1,000 1,000
3. ENTRANCE PROTECTOR PIPE 1 1,000 1,000
4. PAINT 2 2,000 4,000
5. SMALL U-CHANNEL FOR CHAIRS 1 1,000 1,000
6. FLYBATH 1 200 200
7. DRILLING OF TILES - - -
8. HINGE REPLACEMENT 2 600 600
9. DOOR KEY 1 2,500 2,500
10. BOLT FOR DOOR KEY 2 150 300
11. U-BOLT FOR CLASSROM DOOR 1 150 150
12. WIRE MESH 1 BUNDLE 19,000 19,000
13. SMALL PIPE AND U-BOLT FOR STAFF GATE 1 500 500
14. LABOR - 28,000 28,000
TOTAL 61,750