PT.

MITRA MINERAL PERKASA


JOBSITE BCPM
RENCANA KERJA HARIAN
UNIT READY FOR USE
Excavator XE 215C = 21 Unit Motor Grader GR 215 = 2 Unit GR215
Excavator XE 370CA = 15 Unit Vibro XS203 = 1 Unit XS203
Date : Tuesday, 26 July 2022
Excavator XE 490 = 0 Unit Rock Breaker XE 370A = 1 Unit
Dozer TY230 = 2 Unit Water Truck = 1 Unit
Shift : Day Shift
DT Hanvan G7 = 44 Unit Fuel Truck NXG525 = 1 Unit
ADT XDA40 = 2 Unit Service Truck = 1 Unit
Target :
6
Pit & Loading point Material Dumping point Loading Support Dumping Capacity # Hauler Unit
Pit Athena OB WD Anggrek Ban 3-001 1440 MT 4 1-002, 1-007, 1-010, 1-022
Loading point 6

Pit Anggrek OB WD Anggrek Ban 3-007 1440 MT 4 1-035, 1-038, 1-039, 1-083

Pit Athena OB WD Athena 3-009 1620 MT 3 ADT 0-002, ADT 0-003, ADT 0-004(P)
Loading Point 6 Utara

Pit Athena High Ni EFO 3-017 1560 MT 13 1-013, 1-021, 1-023(P), 1-024, 1-026, 1-029, 1-
Loading point 3 bawah
031, 1-032, 1-034(P), 1-059, 1-082, 1-084, 1-
085
Pit Anggrek Top Soil Bank Soil Ares Barat 3-018 600 MT 5 1-001, R1-001, R1-002, R1-003, R1-004

ETO Moskow NiCo EFO 3-019 1440 MT 12 1-006, 1-008, 1-012, 1-014, 1-016, 1-018, 1-020,
1-027, 1-030, 1-042, 1-044, 1-050

Pit Athena OB WD Mataram Bawah 3-004 1800 MT 5 1-004, 1-005, 1-055, 1-058, 1-086
Loading point 3 bawah

Segmen E Quarry ALL AREA 3-003 3-008 3 1-003, 1-009, 1-043


Mine Service

Maintenance WD Mataram 2-005

Recontouring Ares Timur 2-009

Jalan WD Anggrek Ban 2-011

>>> POSISI UNIT Unit Capacity >>> BREAKDOWN


2-003, 2-016, 2-019, 2-020 (RB), 3-017, 3-020, = Jetty 1-011, 1-017, 1-019, 1-025, 1-028, ADT 0-001, 2-018,
6300 MT 3600 MT
3-021, R2-003 10-002, 4-003, 5-002, 6-001
5-003 = MHR OB ORE Barging Quarry
2-001, 2-007, 2-008, 2-009, 2-010, 2-022, 3- = Pit Athena
001, 3-004, 3-005, 3-006, 3-007, 3-009, 3-018,
10-002, 4-001, 4-003, 4-004
= Pit Anggrek

= ETO Segmen D Prioritas Fleet >>> PENDINGAN


= WD Cermin 1 2 3 1-023, 1-034, ADT 0-004, 2-005, 2-022
3-019 = WD Anggrek Utara Tinggi Sedang Rendah
2-015 = WD Ares Barat
2-002, 2-004, 2-017, 3-003 = WD Mataram Bawah
2-021 (RB), 3-002 (RB), 3-008, 5-001 = Segmen E
= Salwa
= Rostov
= Hera BD 2-018, 10-002, 4-003, 5-002, 6-001
= Ares 1-011, 1-017, 1-019, 1-025, 1-028, ADT 0-001
= PT Transon Pend 2-005, 2-022
2-005, 6-002 = MHR-Transon 1-023, 1-034, ADT 0-004
2-006, 2-018, 4-002, 5-002, R2-001, R2-002, = Workshop
>>> Other Information