Professional Documents
Culture Documents
BCOPL Page i
Contents
Page Number
1. Introduction 2
BCOPL Page i
8. Reporting 20
List of Tables
Table 5.1 Blasting criteria 9
Table 6.1 Approved hours 10
Table 6.2 Mitigation measures for blasting activities 12
Table 7.1 Monitoring parameters 18
Table 7.2 Monitoring locations 18
Table 7.3 Meteorological monitoring parameters 19
Table 12.1 Roles and Responsibilities 24
List of Appendices
Appendix A
Blast monitoring and locality plan
Appendix B
Statutory requirements
Appendix C
Blast Fume Management Protocol
Appendix D
Record of stakeholder consultation
Appendix E
BTM Complex Blast Management Strategy
BCOPL Page ii
Abbreviations
Term Description
AEISG Australian Explosives Industry and Safety Group
AEMR Annual Environmental Management Report
AS Australian Standard
BCM Boggabri Coal Mine
BCOPL Boggabri Coal Operations Pty Limited
CHPP Coal Handling and Preparation Plant
BLMP Blast Management Plan
BTM Complex Boggabri-Tarrawonga-Maules Creek Complex
CCC Community Consultative Committee
DP&E Department of Planning and Environment
DRE NSW Department of Resources and Energy
EA Environmental Assessment
EP&A Act Environmental Planning and Assessment Act 1979 (NSW)
EPA Environment Protection Authority
EPL Environment Protection Licence under the POEO Act
MCCM Maules Creek Coal Mine
MET Meteorological monitoring station
MIC Maximum Instantaneous Charge
Mt Million tonnes
Mtpa Million tonnes per annum
NO Nitric oxide
NO2 Nitrogen dioxide
OEH NSW Office of Environment and Heritage
PAC NSW Planning Assessment Commission
POEO Act Protection of the Environment (Operations) Act 1997 (NSW)
ROM Run-of-mine
TCM Tarrawonga Coal Mine
BCOPL Page 1
1. Introduction
This Blast Management Plan (BLMP) has been developed for Boggabri Coal Operations Pty
Ltd (BCOPL), a wholly owned subsidiary of Idemitsu Australia Resources Pty Limited (80%),
Chugoku Electric Power Australia Resources Pty Ltd (10%) and NS Boggabri Pty Limited
(10%). Boggabri Coal Mine (BCM) is located 15 km north-east of the township of Boggabri in
north-western New South Wales. The project is an open cut coal mine that has been
operating since 2006. Truck and excavator operations are undertaken to produce a crushed
and screened run-of-mine (ROM) coal product. Coal is loaded onto trains at the mine site
and transported by rail for overseas consumption via the Port of Newcastle.
BCM is managed by BCOPL who also operate the Coal Handling and Preparation Plant
(CHPP). BCOPL engages a Mining Operator to undertake open cut mining activities.
Project approval number 09_0182 for the BCM granted by the NSW Planning Assessment
Commission under the now-repealed Part 3A of the Environmental Planning and
Assessment Act 1979 (NSW) (EP&A Act) on 18 July 2012, as modified from time to time
(Project Approval) allows BCOPL to extend its mining operations for a further 21 years, and
increase its production rate to 7 million tonnes per annum (Mtpa) of ROM coal from a total
resource of 145 million tonnes (Mt).
Schedule 3, Condition 22 of the Project Approval requires the preparation of a BLMP. The
specific requirements of the BLMP are listed in Table 2.2. Staff and contractors working at
BCM are required to comply with this BLMP.
BCOPL Page 2
2. Statutory requirements
Schedule 3, Condition 22 of the Project Approval requires the preparation of a BLMP. The
specific requirements of the BLMP are set out in table 2.1 together with a reference to where
each condition is addressed in this document. Additional conditions of the Project Approval
relevant to blast management are provided in Appendix B.
Note: The Blast Management Strategy will be developed in stages and be subject to ongoing review dependent
upon the determination of and commencement of other mining projects in the area.
BCOPL Page 3
3. Existing environment
3.1 Location of sensitive receptors
The BCM operates primarily within the Leard State Forest and adjoins rural and residential
receptors on all sides. The properties immediately adjoining the BCM have either been
purchased by BCOPL to provide an environmental buffer around the mine, or are owned by
Whitehaven Coal Mining Pty Ltd (Whitehaven Coal). Properties and residences owned by
BCOPL and Whitehaven Coal are not "privately owned land". These properties are not
considered to be blast sensitive receivers and were not specifically assessed in the
Environmental Assessment (EA) (Hansen Bailey, 2010).
The acoustic impact assessment (Bridge Acoustics, 2010) in the EA concluded that blasting
associated with the operations at BCM would produce ground vibration and overpressure
levels below relevant amenity criteria at all privately owned residences surrounding the BCM.
The locations of privately owned residences relative to the BCM operations are shown in the
figure provided in Appendix A of the BLMP.
3.3 Heritage
All non-indigenous heritage items identified in the EA are located at least 2km from proposed
blasting activities. On this basis it is unlikely that blasting impacts from ground vibration will
cause damage to any non-indigenous heritage items.
Aboriginal cultural heritage items identified in the EA are located within 2km of proposed
blasting activities however, these items are limited to artefact scatters, isolated artefacts and
scarred trees. It is unlikely that these items of Aboriginal cultural heritage will be subject to
impacts from blasting activities.
All measures related to the salvage and preservation of items of cultural significance in the
vicinity of the BCM are outlined in the BCOPL Cultural Heritage Management Plan, which
provides for the salvage and curation of artefacts, demarcation of heritage areas and
ongoing monitoring of heritage items. It also outlines a process for the management of any
heritage related incidents. No actions specific to the management of heritage impacts from
blasting activities are detailed in this BLMP.
BCOPL Page 4
Tarrawonga Coal Pty Limited , a subsidiary of Whitehaven Coal, currently operates the TCM,
which is an open cut mining operation located southeast of and adjacent to the BCM. The
mine has been in operation since June 2006. The Maules Creek Coal Mine (MCCM), also
owned by Whitehaven Coal is an open cut mine located northwest of BCM, which, received
project approval under the EP&A Act in October 2012 and commenced operations in early
2015. The process for managing the cumulative impacts of blasting from these mining
operations is briefly described in Section 6.5. Further detail on the management of
cumulative impacts is found in the BTM Complex Blast Management Strategy (Appendix E).1
Summer months are typically hot and winter periods are relatively short with frequent frosts.
January is typically the hottest month, reaching an average maximum temperature of 34oC.
July is typically the coolest month, reaching an average maximum temperature of 16.9oC.
Temperature inversions are most common in winter months, forming in later afternoon and
reaching maximum resistance at dawn. These conditions have the potential to propagate
blasting noise and air blast emissions.
Summer months have higher mean rainfall (approximately 80 mm) compared to winter
months (approximately 50 mm).
The BCM typically receives wind from the south-east in summer and the north-west in winter.
Winds in Autumn and Spring months are more variable. Autumn is generally the windiest
season.
1Negotiations are underway with Tarrawonga Coal Mine for sharing of blast monitoring data, as discussed in the
BTM Complex Blast Management Strategy.
BCOPL Page 5
4. Sources and types of blast impacts
There are inherent risks associated with blasting that, if managed poorly, may result in
reduced safety, environmental and operational performance. These hazards include, but are
not limited to:
overpressure exceedances;
misfires.
the characteristics of the intervening material (rock, soils, geological structures, etc.)
through which the ground vibration wave propagates.
If not managed appropriately, ground vibration has the potential to cause damage to
buildings and other infrastructure. Management measures for the control of ground vibration
are detailed in Section 6.4.
4.3 Flyrock
Flyrock is any rock or stone that is propelled beyond defined blast limits by the force of the
explosion. It can pose a serious safety hazard and cause damage to buildings and
BCOPL Page 7
infrastructure if not managed appropriately. Management measures for the control of flyrock
are detailed in Section 6.4.
4.4 Fume
The use of ammonium nitrate based explosives under variable conditions can lead to
unwanted explosive reactions and the generation of nitric oxide (NO) and nitrogen dioxide
(NO2). Nitric oxide is unstable in air and readily oxidises to nitrogen dioxide. Nitrogen dioxide
is identifiable as an orange or brown cloud which can be harmful if inhaled. Blast fume is a
result of an explosive not reacting completely with the detonation.
There are a number of potential causes of blast fume including geological conditions,
weather, blast design, explosive product selection, explosive quality, blast-hole
contamination and bench preparation.
Management measures for the control of blast fume are detailed in Section 6.2 and
Appendix C.
4.5 Misfires
Misfires refer to the complete or partial failure of a blasting charge to explode as planned.
The explosives that remain after the blast is detonated may be triggered to explode by
mechanical means during post-blasting excavation activities, potentially leading to incidents.
Measures that will be implemented to prevent misfires are detailed in Section 6.4.
BCOPL Page 8
5. Blasting criteria
5.1 Blasting assessment criteria
BCOPL’s blasting assessment criteria, as outlined in Schedule 3, Condition 15 of the Project
Approval, are shown in Table 5.1.
BCOPL Page 9
6. Management measures
The following general management measures will be applied by all BCOPL employees and
contractors.
These frequencies do not apply to blasts that generate ground vibration of 0.5 mm/s or less
at any residence on privately-owned land, or to blasts required to ensure the safety of people
working or visiting the operations.
BCOPL Page 10
a public road, a road closure management plan will be developed in consultation with
Narrabri Shire Council and submitted to the DP&E for approval.
BCOPL will verify that drilling and blasting subcontractors develop adequate and
documented work instructions for compliance with the relevant requirements provided in
Table 6.2. Drilling and blasting subcontractor are responsible for ensuring their staff (and
relevant sub-contractors) are adequately trained and competent in these work instructions.
BCOPL Page 11
Table 6.2 Mitigation measures for blasting activities
Activity Management mitigation measure Responsibility
Subcontractor
Subcontractor
Operator
Blasting
BCOPL
Drilling
Mining
Notification provide verbal or written notification of individual blasts to any person who requests to be notified. Notification will generally ●
consist of an email or phone call a day prior to the blast and/or on the day of the blast (if the blasting schedule changes)
notify the general public about proposed blasting dates and times via the blast notification sign at the entrance to the mine site ●
notify the general public about blasting activities by listing proposed blasting dates and times on the BCOPL website ●
(www.idemitsu.com.au/boggabri)
provide email notification to BCOPL of proposed blasting dates and time the day before a scheduled blast ● ●
Where a planned blast is either 60 minutes prior or 60 minutes after the planned blast event the new blast times will be issued ● ●
by email or phone call to personnel (refer to section 6.5) at BTM complex Mines and to the general public on the BCOPL
website
Exclusion zones where required locate sentries so the public are excluded within 500m of the blast immediately prior to firing ● ●
Areas designated as exclusion zones will be inspected immediately prior to blasting to confirm the area is clear of people and ● ●
livestock. Within forested areas, at risk tracks and access roads within exclusion zones will be inspected. Sentries will be
stationed at exclusion zone entry points to ensure access is restricted until after each blast is fired.
Due diligence ensure personnel undertaking drilling and blasting activities are suitably qualified and experienced for the task that they are ● ● ●
undertaking
ensure equipment used in drilling and blasting activities is inspected and cleared by the Mining Operator prior to use
Storage of construct and maintain explosive magazines in accordance with the Explosives Act 2003 ● ●
explosives appoint suitably qualified personnel to oversee the safe and secure storage, handling and record keeping of all explosives on
site
manage the storage of explosives in a way that minimises the potential for fume generation from faulty explosive product, as
outlined in the Blast Fume Management Protocol (Appendix C)
dispose of old or deteriorated explosives in an approved manner
BCOPL Page 12
Activity Management mitigation measure Responsibility
Subcontractor
Subcontractor
Operator
Blasting
BCOPL
Drilling
Mining
Hazard in the event of a storm drilling and blasting contractors are to respond in accordance with the relevant statutory Lightning ● ●
minimisation Management Plan
personnel are to be located an appropriate distance away from blasting activities to minimise the potential for contact with
flyrock and blast fume (as detailed in the Blast Fume Management Protocol in Appendix C)
maintain a distance of at least 10 m between any energised high voltage electrical cable and a charged blast hole
develop and implement a system for the safe management of misfires during blasting activities generally in accordance with
AS 2187.2 and provide for the following:
o methods for locating misfires
o procedures for marking and identifying misfires
o procedures to establish and maintain an exclusion zone related to misfires
o the introduction, removal or control of potential detonation or ignition sources
o communication/notification of misfires to relevant personnel
o a procedure for the treatment of misfires
prevent any flame or smoking material within 20 m of any explosive magazine, vehicle carrying explosives, loaded blast hole
or explosive material
develop a specific hot ground procedure generally in accordance with AS 2187.2 for blasting in coal seams liable to
spontaneous combustion
inspect blast holes for hot ground (greater than 57C) and, if required, suspend loading operations and seek guidance from ●
the Mining Operator on a proposed course of action
Design the maximum weight of explosive detonated in a given delay period is to be limited to design levels ● ●
charges are to detonate in the correct sequence and with inter-row delays that provide good progressive release of burden
burden distance and stemming lengths are designed to minimise the potential for ground vibration, face blow-outs and
venting of explosive force
design each blast to consider :
o hardness and nature of the strata
BCOPL Page 13
Activity Management mitigation measure Responsibility
Subcontractor
Subcontractor
Operator
Blasting
BCOPL
Drilling
Mining
o blast geometry including available free faces and the proximity of surface structures and neighbours
o mining equipment to be used to load out materials
o overpressure and vibration limits (as detailed in Section 5.1)
provide the following details in each blast design:
o drill pattern
o diameter, angle and depth of each blasthole
o amount of explosive per blasthole
o firing sequence including all delays or firing times
blast designs are to be provided to relevant personnel when undertaking preparation for a blast (e.g. drillers, shotfirers, etc.)
design the size of blasts to allow charging and firing as soon as operationally possible to reduce sleep times
fume risk management strategies outlined in the Blast Fume Management Protocol (Appendix C) are to be considered during
the blast design process
develop and implement a procedure for managing blasts that are not fired on the same day as they are loaded
Drilling blast holes are to be drilled at appropriate spacing in accordance with blast design ● ● ●
blast hole cave-ins are identified and where necessary, filled in and re-drilled
clearly demarcate and set out drilling areas and drill holes
drill blast holes in the correct position, at the correct angle, diameter and depth, in accordance with blast designs
develop and implement a process so any variations to drilling designs are approved by the Mining Operator and
communicated to relevant parties prior to the commencement of drilling
develop and implement a process so any abnormalities (e.g. cavities or changes in strata) encountered by the driller when
drilling blast holes are recorded on the blast design plan and communicated to relevant parties
notify the Mining Operator immediately of any lost steels or snapped rods
BCOPL Page 14
Activity Management mitigation measure Responsibility
Subcontractor
Subcontractor
Operator
Blasting
BCOPL
Drilling
Mining
Preparation of check exposed down hole lines for damage and rectify any faults ●
charges connections are to be made as close as practical to blast holes
keep connections between blast holes to a minimum without stretching connectors
connect all Nonel tubes consistently
only an industry recognised Nonel starter or electronic blasting box is used for initiating shots
develop and implement a procedure for the use of Nonel starters and electric blasting boxes to ensure blasts are fired in a
safe, appropriate manner
starters and blasting boxes are to be inspected and maintained in good working condition
Loading utilise predictive and real-time weather monitoring network to guide blast loading activities. Loading of blasts will be ● ●
postponed, or the type of explosive that is loaded into the shot will be varied, if significant periods of wet weather are forecast
appropriate materials (e.g. 20 mm aggregates) are to be used in stemming to minimise potential for venting explosion gases,
blowouts and flyrock
stemming columns are such that they are not ejected for considerable distances into the atmosphere. Stemming column
lengths must be such that their ejection velocities are low
use ‘Nonel delay’ type or electronic detonators to initiate charges. Restrict the use of detonating cord to presplit blasts only
and minimise the potential for dust cloud formation
develop a procedure and appoint a suitably qualified overseer to ensure all loading activities are undertaken in a safe,
appropriate manner and in accordance with blast designs
all loading activities are undertaken to minimise the potential for fume generation where practicable, as outlined in the Blast
Fume Management Protocol (Appendix C)
Firing utilise predictive and real-time weather monitoring data to guide the timing of firing blasts. ● ●
Blasts will be postponed during wet weather, periods of low cloud cover, low (< 1.5 m/s) or high wind speeds (>7 m/s) and
during stability class G (or higher) temperature inversions. If blasts must be fired during these conditions, under extraordinary
circumstances, then the Mining Operator will seek the permission of the BCOPL beforehand
blast clearance plans are to be reviewed and approved by the Blasting Subcontractor and Mining Operator prior to firing a
blast
BCOPL Page 15
Activity Management mitigation measure Responsibility
Subcontractor
Subcontractor
Operator
Blasting
BCOPL
Drilling
Mining
Unplanned identify any changes to planned blasting activities, complete and setting out risk identification, risk assessment and control ● ●
circumstances measures are to be implemented prior to recommencing blasting activities. This includes consideration of the fume
generation risks detailed in the Blast Fume Management Protocol (Appendix C).
changes to blasting activities that have the potential to cause fume or trigger an exceedance of the blasting assessment
criteria (detailed in Section 5.1) are documented and communicated to Mining Operator for approval, prior to firing the blast
gain approval of the BCOPL prior to blasting outside of the approved blasting hours (as outlined in Section 6.1)
gain approval of the Secretary of DP&E and the NSW Environment Protection Agency (EPA) prior to blasting outside of the ●
approved blasting hours (as outlined in Section 6.1)
if required, review and approve any changes to blasting activities that are outside of the Mining Operator’s normal operating
protocols
BCOPL Page 16
6.5 Management of cumulative impacts
BCOPL’s Mining Operator will send notification of scheduled blasts, via email to TCM the
day prior to the scheduled time. If there is no conflict regarding scheduled blast times
between the two mines, there will be no further correspondence. If BCOPL’s proposed blast
time conflicts with TCPL’s proposed blast time, then further discussion will be undertaken
between the two mines and a schedule for blasting will be agreed upon. The scheduling of
blasts will aim to allow for a considerable gap between firing times to reduce any potential for
cumulative blast impacts. Once the blast schedule has been confirmed, BCOPL’s Mining
Operator will send email notification to nominated BCOPL representatives prior to the blast.
On the day of the blast, BCOPL will liaise with the Mining Operator to verify that monitoring
equipment has been deployed at the blast monitoring locations.
Where a planned blast event is either 60 minutes prior, or 60 minutes after the planned event
a new notification will be issued (by email or phone call) to the below listed personnel and
updated on the BCOPL website.
Personnel who will be notified of blast times by the BCOPL Mining Operator include:
In addition to blast scheduling, BCOPL, in consultation with other mines within the BTM
Complex, has developed a strategy for the management of cumulative impacts from blasting
activities. The strategy covers the following aspects of cumulative impacts management:
a description of the monitoring network for all mines within the BTM Complex;
a process for identifying the mine that was the likely cause of a given blast exceedance;
and
A copy of the BTM Complex Blast Management Strategy will be kept and implemented by
each mining operation’s respective Environment Superintendent (or equivalent).
Page 17
7. Monitoring
7.1 Blast monitoring
7.1.1 Parameters and frequency
Data obtained from blast monitors will be recorded and analysed to determine compliance
with the blasting criteria (refer Section 5.1) in accordance with Schedule 3, Condition 15 of
the Project Approval.
In addition to collecting blast data, as described in Table 7.1, BCOPL’s Mining Operator will
also inspect the area around the blast for flyrock distribution.
7.1.2 Locations
In accordance with the requirements of the EPL, BCOPL will monitor blasting at two
neighbouring residences, ‘Goonbri’ and ‘Wilberoi East’, to record overpressure and ground
vibration for each blast event. The locations of these blast monitoring sites are shown on the
figure provided in Appendix A.
Compliance against the blast criteria (refer to Section 5.1) will be assessed using the
identified monitoring locations irrespective of land ownership or distance from dwellings.
All blast monitoring will be undertaken in accordance with the methodology outlined in
AS2187.2 Explosives – Storage and Use Part 2: Use of explosives (Standards Australia,
2006).
Page 18
7.2 Predictive meteorology system
A predictive meteorology system is implemented to guide the planning and firing of blasts.
The proposed system will include a website that will make data immediately available for
site, with hourly forecasts up to 48 hours in advance. This system will download global
meteorological data and forecasts on a daily basis.
As with any predictive forecast, confidence reduces with longer predictions, however the
hourly 48-hour predictions will provide useful planning information for blasting operations.
The forecasts for the next 24-hour and 12-hour periods provide more confidence in
predictions for the day ahead and how weather may affect blast events.
A range of user interfaces or simple reports or templates will be generated and used as part
of the standard blasting procedure.
The BCM MET station will provide monitoring data to a BCOPL website
(http://www.novecom.net/sentinex/) in real-time. Nominated employees and contractors will
be provided with a login to the website, allowing them to investigate meteorological
conditions and respond accordingly by modifying or delaying blasting activities to minimise
fume, airblast overpressure and ground vibration impacts.
The parameters recorded by the BCM MET station and the method by which they will be
sampled are outlined in Table 7.3.
Page 19
8. Reporting
8.1 Blast pack
A blast pack will be maintained on file by the Mining Operator for each blast that is fired. This
pack will include:
a blast clearance plan, which includes pre-blast weather checks, pre-blast and pre-shot
fume risk assessments (undertaken in accordance with the Blast Fume Management
Protocol)
a blast shot report, which includes blast monitoring for overpressure, vibration and fume
rating (as per the Blast Fume Management Protocol).
The blast pack will be made available to the BCOPL Operations Team within 48 hours of a
blast event or as directed by BCOPL.
Page 20
9. Incident and complaint management
All environmental incidents, complaints, non-conformance or exceedance will be managed
as per the BCOPL Incident Management Standard. All environment incidents will be reported
to the BCOPL HSEC Manager using the BCOPL Incident Report Form. Following an
incident, the BCOPL HSEC Manager is responsible for assigning any corrective or
preventative actions.
In accordance with Schedule 5, Conditions 2, and 8 of the Project Approval, and the relevant
conditions of the EPL, BCOPL will notifiy, at the earliest opportunity, the Department of
Planning and Environment and any other relevant agencies of any incident that has cause,
or threatens to cause, material harm to the environment. For any other incident associated
with the project, BCOPL will notify the Department of Planning and Environment and any
other agencies as soon as practicable after BCOPL becomes aware of the incident. Within 7
days of the date of the incident, BCOPL will provide the Department of Planning and
Environment and any other relevant agencies with a detailed report on the incident, and such
further reports as may be requested.
Where an exceedance of criteria and/or performance measure(s) has occurred, BCOPL will,
at the earliest opportunity:
Take all reasonable and feasible steps to ensure that the exceedance ceases and
does not recur;
Consider all reasonable and feasible options for remediation (where relevant) and
submit a report to the Department of Planning and Environment describing those
options and any preferred remediation measures or other courses of action; and
A copy of relevant blast monitoring data for the month leading up to and including the
date of the exceedance.
If ongoing monitoring indicates continued exceedances, BCOPL will continue to provide the
affected sensitive receptor with monitoring data, until levels return to below the exceedance
level.
Page 21
10. Corrective and preventative actions
Contractors and BCOPL employees are to be involved in implementation of corrective and
preventative actions at the BCM.
Preventative actions will be identified and agreed with BCOPL management prior to
being implemented.
Where necessary, corrective actions will include a review of relevant plans and
procedures.
Page 22
11. Property Inspections
In accordance with the Project Approval, if a written request from a landholder within 2 km of
the open-cut pit at BCOPL is received, then BCOPL will commission a suitably qualified
experienced and independent person to undertake an inspection of the property. The
inspection will be undertaken to:
establish the baseline conditions of any buildings and/or structures on the land, or
update the previous property inspection report; and/or
identify any measures that should be implemented to minimise the potential blasting
impacts of the project on these buildings and/or structures.
An inspection will also be undertaken if the landholder claims that damage to buildings
and/or structures has been caused by blasting activities from BCOPL. BCOPL will undertake
an inspection within 2 months of receiving the landholder request. If an independent
inspection confirms that damage has been caused as a result of blasting activities and both
parties agree with these findings, BCOPL will repair the damage to the satisfaction of the
Secretary.
If there is a dispute over the selection of the suitably qualified, experienced and independent
person, or BCOPL or the landowner disagree with the findings of the independent property
investigation, the matter will be referred to the Secretary for resolution.
The timeframe for completion of the inspection and provision of the report is subject to
suitable access arrangement being granted by the landholder.
Page 23
12. Roles and responsibilities
Roles and responsibilities for the implementation of this management plan are outlined in
Table 11.1.
BCOPL Mining liaise with the Mining Operator with regard to blast scheduling so blasts
Manager from Tarrawonga Coal Mine and Operations BCM are fired at
appropriately timed intervals to minimise cumulative impacts
providing sufficient resources for the effective implementation of this
management plan
mitigation measures outlined in this management plan are achieved on
site
BCOPL Health liaise with the Mining Operator with regard to blast scheduling so blasts
Safety and from Tarrawonga Coal Mine and Operations BCM are fired at
Environment appropriately timed intervals to minimise cumulative impacts
Manager providing sufficient resources for the effective implementation of this
management plan
mitigation measures outlined in this management plan are achieved on
site
BCOPL Environment blast monitoring is undertaken according to the requirements of this
Superintendent management plan and relevant Australian standards
maintain blast awareness amongst mine personnel and contractors via
inductions
respond to community complaints (including the completion of
appropriate corrective and preventive actions)
liaise with regulatory authorities regarding blast management
coordinate property inspections and repairs to landholders of properties
if required
report blast-related incidents to the relevant regulatory authority
maintain the site’s meteorological monitoring system
review and update this management plan
relevant employees and contractors are aware of their obligations under
this management plan
BCOPL Mining implement blast mitigation measures in accordance with Section 5 of
Operator this management plan
develop and implement specific procedures for employees and
subcontractors to uphold their responsibility to facilitate compliance with
this management plan
liaise with the TCPL Mining Manager regarding blast scheduling to
ensure blasts from TCPL and BCOPL are fired at appropriately timed
intervals to minimise cumulative impacts
ensure relevant employees and subcontractors under their control are
aware of their obligations under this management plan
provide relevant environmental data to assist BCOPL with their
reporting requirements, in accordance with Section 8 of this
management plan
inspect the area around the blast for flyrock distribution
Page 24
Role Responsibility
undertake all blast design management in accordance with Section 6 of
this management plan
BCOPL Blasting undertake relevant blast management activities in accordance with
Subcontractor Section 6 of this management plan
employees
BCOPL Drilling undertake all drilling activities in accordance with Section 6 of this
Subcontractor management plan
employees
TCPL Environment liaise with the BCOPL Mining Operator with regard to blast scheduling
Manager to ensure blasts from TCPL and BCOPL are fired at appropriately timed
intervals to minimise cumulative impacts
All BCOPL undertake activities, as required, in accordance with this management
employees and plan under instruction from their supervisor
contractors inform their direct supervisor of any blast related issues as that arise
Page 25
13. Review
Review of the BLMP will be undertaken by BCOPL in accordance with Project Approval
Schedule 5 Condition 5, within 3 months of submitting the following:
Where this review results in revisions to any such document, then within 4 weeks of the
completion of the revision, unless the Secretary agrees otherwise, the revised document will
be submitted to the Secretary for approval.
Page 26
14. References
14.1 Internal
BCOPL Environmental Incident Response Management Plan
14.2 External
Australian Explosives Industry and Safety Group Inc. (2011) Code of Practice: Prevention
and Management of Blast Generated NOx Gases in Surface Blasting, Edition 1
Department of Environment and Conservation (2006) Approved Methods for Sampling and
Analysis of Air Pollutants in New South Wales.
Standards Australia (2006) AS 2187.2 Explosives – Storage and Use Part 2: Use of
Explosives
Page 27
Appendix A
!
(
!
(
!
(
( WIRRILAH
!
\\APNTLFPS01\proj\I\Idemitsu_Aus_Resources\2200519A_MGT_Plan_Update\10_GIS\Projects\Drawings_Figures_Sketches\2200545A_GIS_F015_A3.mxd Author: SuansriR 9/11/2018
!
( !
Goonbri
(
( GOONBRI
!
( GOONBRI
! !
O !
(
CL368
AUTH355 AUTH339
! !
(
( !
(
!
(
!
(
MERRIOWN
ML1685 ( SYLVANIA
!
( DAISYMEDE
!
( BELLEVIEW !
( ( NAGERO
!
( HEATHCLIFFE COOBOOBINDI
!
!
(
! #
* AWS !
(
( COOBOOBINDI
! ( VICTORIA PARK ML1755
!
( BOLLOL CREEK
!
!
( ( TEMPLEMORE
! ( COOMALGAH
!
( THE ROCK
! ( ROMA
! ( !
! (
BILLABONG
!
( ( GLENHOPE Wilberoi East
!
( JERALONG
!
!
( !
O
!
(
WILBEROI EAST
( TARRAWONGA
! !
( !
( !
(
( !( ( AMBARDO
!
!
( ( SPRINGFIELD
! ! !
(
BARBERS
!
( !
( LAGOON !
(
( !
( !
( ( KYALLA !
! ( PINE GROVE
! ( NORTHAM
!
( EASTVIEW
!
!
(
!
( ( CALLANDAR
!
!
(
!
(
!
( !
(
!
( !
( ( BUNGALOW
! !
(
( Jointly owned residence Boggabri Coal property Tarrawonga property Boggabri Coal Mine project 0 1 2 3 km
!
(
* Meteorological station
# !
approval area [
( Maules Creek residence Mine jointly owned property Crown
O Boggabri Coal Blast !
Mining leases or authority
! Monitoring Location ( Tarrawonga residence
! Maules Creek property Private landholder/Unknown Figure 1
( Boggabri residence Leard State Conservation Area Boggabri Coal Mine Blast
! ( Privately owned
Monitoring Locations
!
Appendix B
Statutory requirements
Statutory requirements
The various Project Approval conditions relevant to blast management are detailed in Table
B.1, together with a reference to where these conditions are addressed in this BLMP.
BCOPL Page i
Contents
1 Introduction 4
7 References 25
8 Appendix 26
BCOPL Page i
List of Tables
Table 2.1: Aspects, risks, impacts and management controls for fume mitigation 8
Table 6.1: Roles and responsibilities for implementation of this protocol 23
List of Figures
Figure 1: Blast Fume Event Tree 17
Figure 2: Fume Cloud Appearance and Rating (Source: AEISG, 2011) 20
BCOPL Page ii
Abbreviations and Definitions
Acronym/Term Meaning
AEISG Australian Explosives Industry and Safety Group- a group of explosives company
working in a collaborative manner to improve explosives safety in Australia
AN Ammonium Nitrate
ANE Ammonium nitrate emulsions classed as UN No 3375. These include both
emulsions and water gels
ANFO A mixture of ammonium nitrate and fuel oil with or without a dye colouring agent
(definition from AS2187.0)
BEZ Blast Exclusion Zone
BCM Boggabri Coal Mine
BCOPL Boggabri Coal Operations Pty Limited
Bench Assistant A person assisting the shotfirer on the bench in blasting activities
BFMP Blast Fume Management Protocol
Blast Designer The person with direct management responsibility for the design of blasting
practices in any mining situation, including the selection of explosive products
Blasting The person supervising blasting activities of the shotfirer and shot crew. My also be
Supervisor/Contractor the lead shotfirer
(BS)
BLMP Blast Management Plan
Bulling or bull hole The formation of voids in a blasted area as a result of energy being released in soft
material
Burden relief A measure of the time delay, provided by the initiation design, between two
consecutive burdens, measured in ms/m
Confinement A measure of the effort required from detonation gasses to displace the fractured
rock
D&B Drilling and blasting
Deep hole A blast hole of greater than 30 metres
Desensitisation The process of reducing or removing the sensitivity of an explosives, whether
temporarily or permanent
Dewatered hole A blast hole which has had rain or surface water removed using an in-hole pump or
other mechanical means
DP&E NSW Department of Planning and Environment
DRE Division of Resources and Energy
DRG Division of Resources and Geoscience
Drill and blast The nominated drill and blast person accountable for the performance, safety as
superintendent well as meeting production requirements of the Department of some mines
Drill and blast Supervisor The person supervising blasting activities of the shotfirer and shot crew. He/she may
be the lead shotfirer
Driller The contractor or individual responsible for drilling the blast pattern to the blast
design specification. Data and information on actual conditions encountered and
variations to the pattern are to be recorded and advised to the blast designer and
shotfirer
Dry hole A blast hole which contains no detectable water
Dust Airborne particulate matter ranging in diameter from 10 to 50 microns
Dynamic water Water that’s in motion (i.e. flowing water)
EA Environmental Assessment
EP&A Act Environmental Planning and Assessment Act 1979 (NSW)
BCOPL Page 1
Acronym/Term Meaning
EPA Environment Protection Authority
EPL Environment Protection Licence under the POEO Act
FMP Fume Management Plan
FMZ Fume Management Zone - a predicted zone where fume is likely to be present after
a blast. The FMZ is managed to ensure that persons are not exposed to fume in
this area
Fumes Gases belonging to oxides of nitrogen, particularly NO2, the most prevalent and
harmful. Fume is a combination of post blast gases, which are predominately
nitrogen dioxide but may also include nitrous oxide, nitric oxide, carbon monoxide
and carbon dioxide. Nitrogen dioxide is the only one of the post blast gases that is
visible
Gas bag An inflatable bladder used to block off a blast hole and support explosives or
stemming
Gassing Chemical reaction creating small gas bubbles in explosives blends with the addition
of chemical gassing agents. This process increases the sensitivity of the explosives
Hole liner A flexible plastic tube which is placed into a blast hole before product is loaded into
the tube, providing some protection from water or broken ground
Hole saver A plastic funnel which is placed in the collar of a hole, allowing product to be loaded,
but preventing fallback of dirt or water ingress
ICAM Incident Cause Analysis Method
Ideal explosion A chemical reaction that produces products (solids, liquids, gasses) at volumes,
concentrations and of type in accordance with conventional theoretical reaction
equations
MET Meteorological monitoring station
MIC Maximum instantaneous charge
MMU Mobile Manufacturing Unit - a vehicle built to strict specifications to manufacture and
deliver explosives onto a bench
MMU Operator Person trained, assessed and found competent to operate an MMU, and who is
authorised and appointed as the MMU operator by the company or mine site
Mt Million tonnes
Mtpa Million tonnes per annum
NO Nitric oxide
NO2 Nitrogen dioxide
NOx Oxides of nitrogen - nitrogen bases gases such as nitric oxide, nitrogen oxide,
nitrogen dioxide, nitrogen monoxide and mononitrogen monoxide
NOx Multiple combinations of oxides of nitrogen (N2O, NO, NO2, N2O4, N2O3, N2O5)
with nitrogen dioxide (NO2) being the principle hazardous nitrous fume
Non ideal explosion A chemical reaction that does not produce products (solids, liquids, gasses) at
volumes, concentrations and of type in accordance with conventional theoretical
reaction equations
OEH NSW Office of Environment and Heritage
POEO Act Protection of the Environment (Operations) Act 1997 (NSW)
Post-blast fume Gases generated by the explosive reaction during blasting
Potentially Exposed A site that is potentially exposed to the effect of a hazard. In this case ‘fume’
Site
Precursor A material resulting from a chemical or physical change when two or more
substances consisting of fuels and oxidisers are mixed and where the material is
intended to be used exclusively in the production of an explosive (definition from
AEMSC Code of good practice precursors for explosives)
Project Approval Project Approval 09_0182
BCOPL Page 2
Acronym/Term Meaning
Recharge A term used to describe the re-entry of water back into a blast hole after it has been
dewatered
ROM Run-of-mine
Sensitivity A measure on how easily an explosive can be initiated. Highly sensitive = easily
initiated
Shotfirer This is a statutory appointment directly responsible for the safety, security and
outcomes of a blast
Sleep time The time between explosives being loaded into a blasthole and their initiation
(Definition from AS2187.0)
SMS Safety and Health Management System required by legislation for a site to operate
under the Coal Mining, Quarrying and Metals Mine or Explosives Act
Stemming The material used to plug a blast hole
STEL Short term exposure limit
Senior Site Executive The person appointed as the Senior Site executive under mining legislation
TDS Technical Data Sheets
TWA Time Weighted Average
Wet hole A blast hole that contains any amount of detectable water
Wet sides A description of a section of blast hole that is not filled with water, but is, however
wet at the sides
BCOPL Page 3
1 Introduction
This Blast Fume Management Protocol (BFMP) has been developed for Boggabri Coal Operations Pty Ltd
(BCOPL), a wholly owned subsidiary of Idemitsu Australia Resources Pty Limited (80%), Chugoku Electric
Power Australia Resources Pty Ltd (10%) and NS Boggabri Pty Limited (10%). Boggabri Coal Operations
Mine (BCM) is located 15 km north-east of the township of Boggabri in north-western New South Wales.
The project is an open cut coal mine that has been operating since 2006. Truck and excavator operations
are undertaken to produce a crushed and screened run-of-mine (ROM) coal product. Coal is loaded onto
trains via a train loading facility at the mine site and transported by rail to overseas consumption via the
Port of Newcastle.
BCM is managed by BCOPL who also operate the Coal Handling and Preparation Plant (CHPP). BCOPL
engages a mining operator to undertake open cut mining activities.
Project Approval (09_0182) for the BCM granted by the NSW Planning Assessment Commission under the
now-repealed Part 3A of the Environmental Planning and Assessment Act 1979 (NSW) ((EP&A Act) on 18
July 2012, as modified from time to time (Project Approval) allows BCOPL to extend its mining operations
for a further 21 years, and increase its production rate to 7 million tonnes per annum (Mtpa) of ROM coal
from a total resource of 145 million tonnes (Mt).
Schedule 3, Condition 22 of the PA requires the preparation of a Blast Management Plan (BLMP). This
BFMP is required as part of the BLMP. All staff and contractors working at BCM are required to operate in
compliance with this BFMP.
BCOPL Page 4
This BFMP describes monitoring and recording that will be undertaken, incident response, notification to
regulatory authorities and the provision of training and general awareness requirements. It is important to
note that all blasting related activities at BCM are undertaken by contactors.
The management actions listed in this BFMP will therefore be implemented by all relevant contractors
through their own internal procedures. The use of internal contractor procedures does not negate the
requirement for all contractors and suppliers associated with blasting activities to adhere to the
commitments in this BFMP.
BCOPL Page 5
2 Blast fume management
2.1 Risks, impacts and management measures
Relevant aspects of blasting activities and associated risks, impacts and management measures that will
be implemented at BCM are outlined below in Table 2.1. Also detailed are the key parties responsible for
implementation of these management measures.
BCOPL Page 6
Table 2.1: Aspects, risks, impacts and management controls for fume mitigation
Responsibility
Contractor
Aspect Risk Impacts/Indicators Management Measure(s)
Drill/Blast
Operator
BCOPL
Mining
Explosive Explosive quality Poor blast performance e.g. Ensure precursors have batch traceability and quality control documentation with ●
Formulation & incomplete detonation of tolerances for each batch held at manufacturing facilities.
Quality explosive leading to fume
No bulk, packaged or initiation explosives shall be used at the mine unless the vendor ● ● ●
Assurance generation.
has been approved by site management and has supplied the relevant material safety
Precursor delivered to mine site data sheets and technical data sheet documents. Copies of all relevant documents will
out of specification. Precursor be retained on site for reference.
degraded during transport and
storage. Visual inspections of materials at all stages of processing ● ●
Incomplete detonation of the Recording bench conditions and variations to blast design and communicating to all
explosive column. affected parties. Information that will be recorded includes:
Oxygen imbalance Incorrectly drilled holes;
missing holes; ●
collapsed/slumping holes;
density & amount of product loaded;
presence of water (surface and sub-surface); and ● ●
depth of holes. ●
Review as-loaded data versus design to look for inconsistencies. ●
Review fume events to verify if event was caused by specific product or MMU.
Quality assurance & Failure to conduct quality tests Quality check all raw materials used in the precursors for compatibility, including visual ●
auditing inspections of bulk and initiating explosives.
QA sheets for delivery can be obtained from relevant suppliers. ●
Diesel quantities are tracked on every blast and recorded in blast packs. ●
Mixing of raw Failure to conduct quality tests Use dye with ANFO based products and visual inspection of bulk explosives. ●
materials Incomplete detonation of the
explosive column. On bench quality control testing to be undertaken and recorded for every MMU load. ●
Oxygen imbalance This includes density, gassing rates and product temperature, which will be stored in
blast packs.
Review as-loaded data versus design to look for inconsistencies. ● ●
BCOPL Page 7
Responsibility
Contractor
Aspect Risk Impacts/Indicators Management Measure(s)
Drill/Blast
Operator
BCOPL
Mining
Review fume events to verify if event was caused by specific product or MMU. ●
Fines in Ammonium Poor diesel absorption by AN prill. AN prill to be consumed as per the stock rotation process, current stock of AN is ●
Nitrate (AN) prill and Impacts to product densities and generally consumed within 2-5 days. This minimises the effects of weather and
crystallisation of stability. deterioration.
emulsion due to
temperature cycling.
Bulk explosive Poor blast performance e.g. Where a product change is suggested by the Blasting Contractor, approval will be ● ● ●
development incomplete detonation of sought from BCOPL in consultation with the Mining operator to ensure the proposed
explosive leading to fume change does not increase the potential for fume generation.
generation
Product rotation Product past used by date. Raw materials to be consumed as per the stock rotation process, initiating explosives ●
will be managed as per magazine management rules and checked during stocktake.
AN prill to be consumed as per the stock rotation process, current stock of AN is ●
generally consumed within 2-5 days. This minimises the effects of weather and
deterioration.
Delivery System Failure to conduct quality tests Monthly calibration of MMU’s metering systems, undertaking density and visual checks ●
during mixing of raw materials.
Contractor Failure to conduct quality tests Auditing schedule to ensure compliance of storage and procedures. ● ●
BCOPL to undertake annual audit of blasting operations and systems ●
Geology Blasting to base of Fume issues from blasts in areas Develop and maintain Horizon Risk Matrix with rules to match each level of risk ●
weathering and other known to contain weak/soft strata
areas which have a Modifying blast design and/or explosive product selection to suit geological conditions, ● ●
lack of relief in methodology should be to reduce the explosive density/energy in soft strata
weak/soft strata.
Planning schedule should also consider the size of the blast and where appropriate the ● ●
extent of the blast boundaries
Drill logs to be reviewed to map areas of concern, e.g. soft/broken/faulted ground ● ●
Load sheets to contain specific instructions on loading so there is no overloading/over ● ●
powering in blast holes
Slumping holes, no drill cuttings, Planning schedule should also consider the size of the blast and where appropriate the ●
fume from known specific areas extent of the blast boundaries
BCOPL Page 8
Responsibility
Contractor
Aspect Risk Impacts/Indicators Management Measure(s)
Drill/Blast
Operator
BCOPL
Mining
Loading in Review drill logs and consider loading holes with air/gravel decks or hole liners to ●
faulted/fractured mitigate product runaway. Ensure design, explosive product selection and stem height
ground is suitable for conditions observed
Review loading sequence to minimise delay, utilise collar protectors and gas bags ● ●
Back break & broken where slumping, broken ground or faulting occurs
ground
Drill logs to be reviewed to map areas of concern, e.g. soft/broken/faulted ground. ● ●
Ensure loading practices suit any conditions observed
Shotfirer to inspect sleeping shots daily, record and report on any changes e.g. ● ●
slumping
Design blast geometry and timing to promote adequate movement and relief ●
Areas with high clay Hole ‘bulling’ and fume Review drill logs to map areas of concern ●
content
Consider the use of hole liners and decking techniques ●
Modifying blast design and/or explosive product selection to suit geological and
moisture conditions, methodology should be to reduce the explosive density/energy
Ground Slumped blast holes & explosive Design blast geometry and timing to promote adequate movement and relief ●
movement/product column dislocation
Ensure primer is positioned in the column of explosive as per contractor procedures ●
sensitisation
Holes to be primed as per manufacturers specifications, further priming to be used in ●
areas of faulting
Blast design Explosives Incomplete detonation of the Selecting suitable explosives and accessories for the hole depth, diameter, moisture ● ●
desensitisation during explosives column level, ground hardness and density. Products selected will be capable of mitigating
blast Desensitisation of adjacent against the presence of wet holes/extreme weather events (where appropriate)
columns Selecting initiating devices that are suitable to initiate and maintain the detonation, ● ●
Minimal or uncontrolled movement compatible with the explosives and used in accordance with explosive manufacturer's
in blast recommendations
Design blast geometry and timing to promote adequate movement and relief ●
Optimise loading and timing around back and side walls to promote relief
Shotfirer to inspect hole locations prior to loading & D&B Engineer to check as drilled ● ●
data to ensure pattern is drilled to design
Utilise face scans to optimise face burden design ●
BCOPL Page 9
Responsibility
Contractor
Aspect Risk Impacts/Indicators Management Measure(s)
Drill/Blast
Operator
BCOPL
Mining
Blast layout and Minimal or uncontrolled movement Design blast geometry and timing to promote adequate movement and relief ●
delays in blast
Ensure primer is positioned in the column of explosive as per manufacturers ●
Fume from back or ends of blast recommendation
Utilise face scans to optimise face burden design ●
Inadequate Hole cratering or flyrock Use appropriate/proven stemming heights, stemming will ideally be crushed aggregate ● ●
confinement
Utilise face scans to optimise face burden design ●
Optimise loading and timing around back and side walls to promote relief ●
Lack of Repeated significant fume Following blast design parameters, capturing and recording changes and storing all ●
understanding of the events/poor blast performance design records in ‘Blast Packs’. Ensuring all personnel involved in the design of blasts
possible causes, and are appropriately qualified and experienced and have a comprehensive understanding
prevention techniques of the factors that can lead to the generation of blast fume
of fume Inexperienced designer
Blast design parameters to be approved by Mining Technical Services Superintendent ●
Fume spread sheet to be reviewed for trend analysis ●
Product Choice of explosive Desensitisation of adjacent Select suitable explosives and accessories for the hole depth, diameter, moisture level, ● ●
selection product columns ground hardness and density. Products selected will be capable of mitigating against
the presence of wet holes/extreme weather events (where appropriate)
Compliance with Repeated significant fume Explosives technical data sheets to be followed when selecting appropriate explosives, ● ●
manufacturers events/poor blast performance if the technical data sheets cannot be adhered to then the design needs to be risk
recommendations assessed with all appropriate parties. Consent by the Mining operator’s, Operations
Manager would need to be given prior to loading/firing
Blast design parameters to be approved by Mining Technical Services Superintendent ●
Fume spread sheet to be reviewed for trend analysis and captured in end of month ● ●
reporting
Explosive product is Fume issues from blasts in areas Selecting suitable explosives and accessories for the hole depth, diameter, moisture ●
not suitable for known to contain weak/soft strata level, ground hardness and density. Products selected will be capable of mitigating
ground conditions against the presence of wet holes/extreme weather events (where appropriate)
(water, rock mass,
strength etc.).
BCOPL Page 10
Responsibility
Contractor
Aspect Risk Impacts/Indicators Management Measure(s)
Drill/Blast
Operator
BCOPL
Mining
Priming explosives Incomplete detonation of the Initiating explosives will be managed as per magazine management rules and checked ●
are not suitable for explosives column during stocktake process
the explosive product Desensitisation of adjacent Holes to be primed as per manufacturers specifications, additional priming to be ●
columns considered in areas of faulted or broken ground
Ensure primer is positioned in the column of explosive as per procedure ●
Contamination Managing wet holes Slumped blast holes Holes with damp walls or water within the blast hole will be treated as ‘wet’ and will ● ●
require appropriate bulk explosives
Holes adjoining ‘wet’ hole will also be treated as being wet to mitigate impact of ●
potential runoff or subsurface water
Discharged water run-off to be kept away from blast holes as per blasting contractor ● ●
procedure
Dynamic holes will be assessed as having 1m (column height) per hour recharge after ● ●
dewatering. Extra attention to explosives selection and sleep time needs to be
considered for dynamic holes
Mud/sediment in the Fume from product contamination Dip and record depths of mud, water and wet walls. Load suitable products as per ● ●
base of holes Slumping blast holes explosive supplier’s recommendations
Consider the use of gas bags or hole liners to mitigate product contamination ● ●
Shotfirer to inspect sleeping shots daily ●
Definition of Slumping holes Holes with damp walls or water within the blast hole will be treated as ‘wet’ and will ●
dry/wet/dynamic require appropriate bulk explosives
holes
Holes adjoining ‘wet’ hole will also be treated as being wet to mitigate impact of ●
potential runoff or subsurface water
Dynamic holes will be assessed as having 1m (column height) per hour recharge after ●
dewatering. Extra attention to explosives selection and sleep time needs to be
considered for dynamic holes
Dip and record depths of mud, water and wet walls. Load suitable products as per ●
explosive supplier’s recommendations. Utilise gas bags to keep explosive product
separated from water
BCOPL Page 11
Responsibility
Contractor
Aspect Risk Impacts/Indicators Management Measure(s)
Drill/Blast
Operator
BCOPL
Mining
Stemming material Cratering and fly rock The stemming material shall be crushed aggregate, the stemming should be free from ●
and techniques contamination and free flowing to allow accurate and controlled loading into the blast
holes. Stemming should be stored so that there is minimised risk of contamination
caused by larger rock/fines/clay.
On bench Education and Repeated significant fume Ensuring all personnel involved in on bench activities are appropriately qualified and ●
practices training on product events/poor blast performance experienced and have a comprehensive understanding around the factors that can lead
selection and bench to the generation of blast fume
practices Appropriate supervision/management of blasts crews
As loaded data to be recorded and reviewed for compliance ●
On bench quality control testing will carried out for every load of product and recorded ● ●
on load sheets (which are stored in blast packs)
Blast designs parameters to be approved by appropriate superintendent ●
Induction process to familiarise all personnel onsite of post blast fume ●
Bench drainage Slumping holes, water laying on Bench preparation sign off prior to loading ● ●
techniques bench
Adequate bunding and drainage in place prior to drilling and loading ● ●
Minimise dewatered holes running into adjoining holes ●
Process for Slumping holes, changes to the Manufacturers sleep times should be strictly adhered to and cannot be exceeded ● ● ●
exceeding conditions of the shot during without BCOPL approval
recommended or loading (i.e. rainfall on a sleeping
Understand technical specifications of explosive products, blast crew training and ● ●
maximum sleep times shot).
manage blast schedule with loading, weather and sleep times being considered
Load sequence to allow for blasts to be cut-off ● ●
Previous 12 months of blasts have an average sleep time of 3.3 days per blast,
emphasis is to always minimise sleep time
Dynamic water in Slumped blast holes (usually Dip and record depths of mud, water and wet walls. Load suitable products as per ● ●
holes when using non water-resistant explosive supplier’s recommendations.
explosives).
Dewater and monitor recharge rate from confirmation if dynamic. Discharged water run- ● ●
off to be kept away from blast holes
Minimising the sleep times of shots ● ●
BCOPL Page 12
Responsibility
Contractor
Aspect Risk Impacts/Indicators Management Measure(s)
Drill/Blast
Operator
BCOPL
Mining
Choosing explosive products according to manufacturer’s recommendations and ●
amount of water in holes
Inspection regime of Slumping holes Ensure shots that are slept have daily inspections to check for visible signs of slumping ●
sleeping shots
Load sequence to allow for blasts to be cut-off if required ●
Delay between drilling Collapsed, short holes Scheduling sequence to minimise the delay between drilling and loading of the blast ● ●
and loading in broken Water ingress and sleep time of the explosives
ground
Planning schedule should also consider the size of the blast and where appropriate the ●
extent of the blast boundaries, and avoid blast joins near areas of concern (faults,
broken ground)
Utilise collar protectors and gas bags where required ●
Tolerance of error Holes out of position, desensitized Compare ‘as drilled’ data to design and consider redrilling holes if necessary +/-1 m ● ●
allowable for the explosives and dislocated
Shotfirer to inspect hole locations prior to loading to ensure pattern is drilled to design ●
location of the drill columns
holes
Product variation from Powder factor too high Load rules need to state the allowable variances of loading before contacting the D&B ● ●
approved blast plan Engineer
Blast contactors maintain auditing and inspection schedule ●
Loading sequence Slumping holes, water laying on Loading sequence should consider location of wet holes, broken ground, overall sleep ● ●
and techniques bench time and surface drainage so to mitigate water spreading across dry areas of the blast
Holes with damp walls or water within the blast hole will be treated as ‘wet’ and will ●
require appropriate bulk explosives
Holes adjoining ‘wet’ hole will also be treated as being wet to mitigate impact of ● ●
potential runoff or subsurface water
Dynamic holes will be assessed as having 1m (column height) per hour recharge after ●
dewatering. Extra attention to explosives selection and sleep time needs to be
considered for dynamic holes
Firing a blast outside Impacts to public amenity Blasting will only be undertaken between the hours of 9:00am – 5:00pm Monday to ● ● ●
of approved hours or Saturday unless written approval of the Secretary of DP&E has been obtained. The
frequency frequency of blasts will also be limited to a maximum of 1 blast per day and 4 blasts per
week (averaged over a calendar year). These frequencies do not apply to blasts that
BCOPL Page 13
Responsibility
Contractor
Aspect Risk Impacts/Indicators Management Measure(s)
Drill/Blast
Operator
BCOPL
Mining
generate ground vibration of 0.5mm/s or less at any residence on privately-owned land,
or to blasts required to ensure the safety of people working or visiting the BCM
Weather Fume cloud drift Fume cloud is generated and is Undertake pre firing risk assessment to determine risk and potential level of fume ●
Rainfall causes carried by wind towards a public
explosive to become area or private residence Assessing weather conditions prior to firing each shot. Shots will not be fired during ● ●
‘wet’ in blast hole Water in blast hole limits adverse weather conditions (i.e. wet weather, periods of low cloud cover, wind speeds
detonation of explosive resulting >7 m/s and during stability class G (or higher) temperature inversions), unless for safety
in excessive fume reasons, or to minimise further deterioration of the explosive product
Any shot that is fired during adverse weather conditions will be approved by the
BCOPL. Relevant parameters for consideration prior to firing a shot will be:
wind speed and direction;
the presence of a temperature inversion;
low continuous cloud cover; and
pre firing risk assessment
Review blast clearance plans for sensitive site locations and ensure contact details are ● ●
available
Use forecasts from the predictive weather system to guide the scheduling of blast ● ●
preparation activities
Research Repetitive fume Fume events directly contributable End of month review of fume levels to determine frequency and trends. This will include ● ●
events directly related to a specific parameter analysis of fume rating per pit or specific area of the pit to understand whether
to: pits/areas of pits are performing worse than others. If a pit is found to record higher
Specific blast fume levels then an assessment of the fume results from each horizon will be
horizon undertaken to understand the fume risk each horizon presents.
Pit location If a horizon has been determined to be a high or medium risk, measures will be put in
place to reduce fume. These may include product choice, reduced sleep time, reduced
Sleep time shot size or a combination of all.
Bulk All fume events will require an investigation to determine contributing factors and ●
explosive develop corrective actions. This will include carrying out an investigation to determine
type any correlation between sleep time and recorded fume levels.
BCOPL Page 14
Responsibility
Contractor
Aspect Risk Impacts/Indicators Management Measure(s)
Drill/Blast
Operator
BCOPL
Mining
Presence of Should the six monthly fume target (98% of shots recording 0-2 fume rating) be ●
water exceeded, a review between all parties will be held to determine if independent
Geological consultation is required to determine contributing factors.
features
Occurrence of fume
frequency too high
Post blast Public access to Ingestion of NOx gases from Sensitive receivers within 2 kilometres of active blasting areas will be provided with ●
fume potential fume area contact with blast fume cloud information advising them of potential actions to take in a declared emergency. Updates
management following a blast to sensitive receivers will be provided annually, as required.
No blasting will be undertaken within 500 m of a public road unless a road closure ●
management plan has been developed and approved
Relevant personnel will be provided with appropriate training regarding the identification ● ● ●
of blast fume events and response protocols in the event of a blast fume emergency
BCOPL Page 15
2.2 Incident response
All incidents related to blasting at BCM will be managed in accordance with the process described in the
Blast Management Plan. It is unlikely that exposure to blast fume in a well-ventilated environment will cause
impacts to human health, however NOx gases are still considered a potential threat and will be managed
accordingly. Generally NOx plumes generated during blasting will dissipate to background levels in a
relatively short time. Dissipation is highly dependent on local atmospheric conditions.
In cases where a NOx plume does not dissipate and has the potential to result in human exposure, the
following actions will be taken:
No personnel will be permitted to enter the plume.
Personnel will be instructed to move away from the path of the plume.
If indoors, personnel will be instructed to close all windows and doors, stay inside and cease operating
air conditioning units if possible.
If in a vehicle, personnel will stay inside and use recirculated air conditioning if possible.
If a person has been exposed to NOx gases, medical attention will be provided as soon as it is safe to do
so (i.e. once the fume cloud has cleared). The possibility of delayed and life-threatening pulmonary oedema
dictates that:
Any person exposed to a visible plume of NOx, and/or any person experiencing sudden acute effects
of coughing, shortness of breath or irritation of the mucous membranes of the eyes, nose or throat
following post-blast NOx events will be examined by a medical practitioner without delay, even if no
NOx smell was noticed or symptoms are mild.
The treating medical practitioner will be informed of the potential NOx exposure.
In accordance with the requirements of the Australian Explosives Industry Safety Group (AEISG) Code of
Good Practice, information will be provided to the medical practitioner as per Appendix 8.1
In the event that a blast produces fume that rates a 3C at its highest extent and leaves site, or any blast
that rates 4 or 5 (refer to section 3.1), the BCOPL will report to the Department of Planning and Environment
(DP&E) compliance officer.
In accordance with the Project Approval and the EPL, BCOPL will provide verbal and written notification to
relevant agencies of any incident that has caused, or threatens to cause, material harm to the environment
in accordance with the process described in the Blast Management Plan.
Additionally, all contractors at BCM are required to notify the BCOPL Health Safety and Environment
Manager immediately, should they become aware of an environmental incident.
BCOPL Page 16
2.2.4 Post-fume incident investigation
Should blast fume be generated from a blast, the Blast Fume Event Tree shown in Figure 1 below will be
used during the subsequent incident investigation to identify which of the fundamental causes was the
significant contributor to the generation of NOx.
The Blast Fume Post Incident Investigation template is shown in Appendix 8.7 will be completed for all
blasts with post blast fume. If required an Incident Cause Analysis Method (ICAM) incident investigation
will be completed for fume events that are reportable to the DP&E.
BCOPL Operations Manager, Technical Services Superintendent and Health, Safety and Environmental
Manager will be provided with the investigation report once the likely causes have been identified. Then
appropriate action plans will be put in place to mitigate and reduce the generation of fume from future blasts
under similar circumstances.
The Blast Fume Event Tree will also be used to educate relevant personnel to ensure appropriate steps
are taken in the design, loading and firing of the blast to minimise the likelihood of generating fume from
the blast.
BCOPL Page 17
BCOPL Page 18
3 Rating and recording
All blasts will be rated for fume in accordance with the fume rating system described below in Section 3.1.
Fume ratings will be recorded in ‘Blast Packs’ by the Blasting Contractor, which will be stored onsite. The
fume is to be rated when it is at its greatest extent and where possible be rated by a team consisting of a
Shotfirer, Blast Engineer and BCOPL representative.
All blast results will be recorded in the template provided by QLD Explosive Inspectorate, so that historical
analysis can be undertaken. These results are used to determine trends for BCOPL internal monthly
reporting. The data recorded for each blast consists of the following:
A video record of each blast fired will be taken, and if possible, a second video camera will be used to
record at a different angle. Any video should be a minimum duration of one minute following the blast and
should capture any post blast fume until the fume dissipates, leaves the site, or leaves the view of the
camera. All video records will be kept on site for a minimum of two years.
Each blast will be rated according to the appearance and extent of the fume cloud that is produced.
Assessing the amount of NOx gases produced from a blast will depend on the distance the observer is
from the blast and the prevailing weather conditions.
The rating scale will range from 0 – 5 and will be based on the colour and density of the fume cloud. The
extent of the NOx gases will also be assessed and will be done on a simple scale from A to C where:
A = Localised (i.e. NOx gases localised across only a few blast holes)
B = Medium (i.e. NOx gases from up to 50% of blast holes in the shot)
C = Extensive (i.e. extensive generation of NOx gases across the whole blast).
BCOPL Page 19
Figure 2: Fume Cloud Appearance and Rating (Source: AEISG, 2011)
BCOPL Page 20
4 Training and awareness
All BCOPL employees and contractors will complete general blast fume awareness training in their site
familiarisation induction.
Additional education and awareness programs will be provided for relevant personnel consistent with their
roles and responsibilities as detailed in relevant contractor explosives and shotfiring management
documents. Training records will be kept by each relevant contractor.
Training on the management actions outlined in this document will be provided by suitably experienced or
qualified personnel. Training will typically cover the following aspects associated with blast fume
management:
The identification and rating of post-blast NOx gases.
The potential health impacts of NOx gases.
Potential causes of blast fume.
Fume mitigating actions as detailed in this document.
Site specific blasting operation procedures (provided by relevant contractors).
Reporting procedures in the event of a post-blast fume event.
Incident and emergency response procedures for blast fume management.
BCOPL Page 21
5 Document Review
Review of the of the BFMP will be undertaken by BCOPL in accordance with Project Approval schedule 5
condition 5, within 3 months of submitting the following:
Annual Review under Schedule 5, condition 4 of the Project Approval.
Incident report under Schedule 5, condition 8 of the Project Approval.
Independent audit under Schedule 5, condition 10 of the Project Approval.
Any relevant modification to the Project Approval.
Where this review results in revisions to any such document, then within 4 weeks of the completion of the
revision, unless the Secretary agrees otherwise, the revised document will be submitted to the Secretary
for approval.
BCOPL Page 22
6 Roles and responsibilities
Roles and responsibilities for the implementation of this management protocol are detailed in Table 6.1.
Mining Operator Ensure all employees and subcontractors under their responsibility are aware of
Operations Manager their obligations under this management protocol
Develop and implement internal procedures to facilitate compliance with this
management protocol
Drilling Contractor Drill Drill the drill pattern to plan
Operator Notify the Drill Supervisor of changes in ground conditions
BCOPL Page 23
Role Responsibility
Record on drill logs the following:
o geological/ground conditions;
o depth to coal seam; and
o moisture conditions
Ensure adequate hole protection is in place
Drilling Contractor Drill Coordinate drill activities in consultation with the D&B engineer
Supervisor Ensure drillers are fulfilling their responsibilities
Coordinate water management activities on the pattern from the bench
preparation stage through the completion of drilling
Blasting Contractor Ensure the charging plan is followed
Shotfirer Ensure that any changes to the charging plan are discussed with the D&B
Engineer prior to their implementation
Supervise trainee shot firers and blast crew
Ensure explosive quantities are recorded hole by hole
Monitor product usage during loading
Ensure blasting activities are completed in accordance with the drill and blast
procedures, in particular:
o managing loading activities to prevent contamination of explosives;
o primer location and quantity is complaint;
o appropriate stemming practices are employed;
o accurate placement of gas bags;
o ensure adequate hose handling techniques are employed; and
o cup density checks are conducted to ensure correct densities are met
Identify and record any hole slumping
Ensure all reporting is completed to requirements
Blasting Contractor Blast Ensure that all personnel working on the shot are trained and competent
Supervisor/Manager Ensure adequate resources are assigned to blasting activities
Ensure the charge plan is followed
Ensure any changes to the charge plan are approved
Ensure shot firers are fulfilling the shot firer’s responsibility
Ensure all blasts are monitored for overpressure and ground vibration
Ensure all blasts are observed and/or video recorded
Report all fume events to a BCOPL supervisor
Ensure approvals for blasting are in place before initiating a shot
Ensure the sentries are placed at the appropriate locations to reduce the risk of
fume exposure for personnel on site
Ensure blasting activities follow procedures for shot prep, charging, stemming,
blast guarding and post blast inspections
Ensure equipment delivers explosives within calibration
Review raw material quantities against manufacture and load specifications
Manage stock rotation and precursor material quality checks
Monitor sleep time of all blasts
Develop and implement internal blasting procedures to facilitate compliance with
this management protocol
BCOPL Page 24
7 References
7.1 Internal
BCOPL Blast Management Plan.
7.2 External
Australian Explosives Industry and Safety Group Inc. (August, 2011) Code of Good Practice: Prevention
and Management of Blast Generated NOx Gases in Surface Blasting, Edition 2.
Standards Australia (2006) AS 2187.2 Explosives – Storage and Use Part 2: Use of Explosives.
BCOPL Page 25
8 Appendix
8.1 Information for medical staff
The following effects may be encountered after NOx exposure:
Acute:
Cough
Shortness of breath
Short term:
Medium term:
In rare cases, bronchiolitis obliterans, which may take from 2-6 weeks to appear
Long term:
High level exposure particularly associated with methhaemoglobinaemia can cause chest pain, cyanosis,
and shortness of breath, tachapnea, and tachycardia. Deaths have been reported after exposure and are
usually delayed. Even non-irritant concentrations of NOx may cause pulmonary oedema. Symptoms of
pulmonary oedema often don’t become manifest until a few hours after exposure and are aggravated by
physical effort. The patient will be advised to rest and if any respiratory symptoms were present, will have
been administered oxygen. The patient will need to be treated symptomatically but as a base line it is
suggested that the following investigations are required:
Spirometry
Chest x-ray
Methhaemoglobin estimation
Because of the risk of delayed onset pulmonary oedema, it is recommended that as a precaution, the
patient be observed for up to 12 hours. As no specific antidote for NOx exists, symptoms will have to be
treated on their merits.
BCOPL Page 26
8.3 Horizon Risk Matrix
High Risk Horizons (Weathered material & Braymont Horizon)
Use primarily ANFO in high risk horizons
Ensure the blast pattern is designed for a suitable powder factor to reduce fume potential and maintain
suitable fragmentation
Limit use Heavy ANFO (60/40) product in these horizons
Minimise use of emulsion products in these horizons
Follow an uninterrupted load-tie-fire process in these horizons
Hole liners to be used where required in adverse conditions (E.g. Broken, Faulted, Wet)
Minimise sleep time.
Medium Risk Horizons (Weathered material, Bollol Creek & Jeralong Horizon)
Limit use Heavy ANFO (60/40) product in these horizons
Ensure the blast pattern is designed for a suitable powder factor to reduce fume potential and maintain
suitable fragmentation
Follow an uninterrupted load-tie-fire process in these horizons
Hole liners to be used where required in adverse conditions (E.g. Broken, Faulted, Wet)
Minimise sleep time.
Low Risk Horizons (Merriown, Jeralong & <15m Braymont Upper Horizon)
Ensure the blast pattern is designed for a suitable powder factor to reduce fume potential and maintain
suitable fragmentation
Hole liners to be used where required in adverse conditions (E.g. Broken, Faulted, Wet).
BCOPL Page 27
8.4 Example of Blasting Environmental Assessment & Sign-off
BCOPL Page 28
8.5 Example of Blast Specific Clearance Plan
BCOPL Page 29
BCOPL Page 30
8.6 Example of Shotfirer Report & Summary
BCOPL Page 31
8.7 Example of Blast Fume – Post Incident Investigation
BCOPL Page 32
BCOPL Page 33
Appendix D
Tarrawonga Coal Mine Various Consultation with Tarrawonga Coal Mine has been
undertaken regularly as part of the BTM Complex meetings.
Maules Creek Coal Various Consultation with Maules Creek Coal has been undertaken
regularly as part of the BTM Complex meetings.
Boggabri Coal Operations Mine – 30 April 2013 A summary of the Blast Management Plan was presented to
Community Consultation the CCC. Representatives of the CCC were invited to review
Committee (CCC) the document in full and provide further feedback if desired.
No additional comments have been received to date.
EPA 7 June 2013 A copy of the BLMP has been submitted to the EPA for
comment.
EPA and CCC August 2016 A summary of the BLMP was presented to the CCC.
Representatives of the CCC were invited to review the
document in full and provide further feedback if desired. A
copy of the BLMP was provided to the EPA for comments.
DPE October 2017 Revised BLMP sent to DPE for review and approval. Review
comments provided to Boggabri Coal in February and
revised plan re-issued to DPE for approval in July 2018.
Appendix E