ENGINEERING ITEMS
LATEST STAGE (16.03.2020)
2.1.6 Infrastructure:

It is submitted that the APREI society has submitted the following proposals from
time to time to the Government to release funds for construction of balance building for
individual schools and also total APR Institutions. The details of works requested to
Government are as follows.

Sl. Proposal File


Item of works Amount Scheme
No Number
Rc.No.Engg/A4/160 construction of additional buildings
Additional Funds
/13-14, dt 10-10- and also for maintenance for Rs 679.25
1 under Capital
2014, dt existing buildings at Mukkavaripalli, lakhs
Grants
30.03.2015 Kadapa District
To improve the infrastructure
Rc.No.Engg/A4/160 Additional Funds
facilities in APR Schools & Junior Rs.631.73
2 /83-15, dated under Capital
Colleges over a period of six years crores
06-10-2015 Grants
under Capital Grants
Towards improvement of minimum
Lr.Rc.No.Engg/A4/1
requirement of infrastructure Additional Funds
60/83-16, dt: Rs.314.37
3 faculties in APR Schools & Junior under Capital
09.02.2016, dt: crores
Colleges under Capital Grants Grants
17.03.2016
head.
crores towards providing additional
Rc.No.Engg/A4/160 toilet block, maintenance/ repairs Additional Funds
Rs 25.04
4 /83-15, dt: to the existing toilet block and under Capital
Crores
22.08.2015 improving the water supply Grants
facilities in APRE Institutions
Rc.No.Engg/A4/760 Additional Funds
For completion of ongoing works in Rs.1177.00
5 /15-16, dt: under Capital
13 institutions. lakhs
01.07.2016 Grants
Lr.No.Engg/A4/785/
17-18, dt: Construction of additional buildings Rs.114.05 RIDF NAABARD
6
21.09.2016 & in 30 APR Institutions Crores
03.08.2017
Lr.No.Engg/A4/786/
Construction of additional buildings Rs 196.00
7 17-18, dt: ANNUITY BASIS
in 32 APR Institutions. Crores
05.08.2017

The Government have sanctioned the following funds under varies schemes for
construction of additional buildings in APR Institutions
(Rs. IN LAKHS)

SL Amount
Sanction GOs Name the works Expr Stage of work
No sanctioned
G.O.Rt.No.173, Construction of full-fledged
Completed and
School Education works including compound wall
1 1493.00 1058.51 handed over to the
(TRG) Dept, at S,N.Padu Prakasham
Principal
dt.4.09.2015 District
G.O.Rt.No.1433, Construction of full-fledged
Completed and
School Education works Excluding compound
2 1300.00 889.51 handed over to the
(SE Genl II)Dept, wall at Atmakur, Nellore
Principal
Dt.16.11.2013 District.
2

Dormitory
completed and
handed over, for
G.O.Rt.No.290.
Construction of dormitory, Staff quarters
,School Education
3 Principal Quarters and 4 TSQs 198.00 124.99 flooring, painting
SE Genl II)Dept,
at Vayalpadu, Chittoor District. works are to be
Dt.08.02.2013
completed. Work
stopped for want of
funds
Retenders are to be
called for. Recently
the earlier land was
G.O.Rt.No.351
cancelled and
School Education
Construction of dining hall at allotted new
4 (SE Genl 107.40 0.00
Pileru, Chittoor District. land.(7.00.Acers)
II)Dept,Dt.08.03.20
at Gudarevupalle
13
village, Piler
Mandal, Chittoor
dist.
G.O.Rt.No.22 School Completion of first floor rooms
Education and construction of compound
5 193.00 143.67 Works completed,
(TRG)Dept, wall at Vomaravalli,
Dt.04.02.2015 Srikakulam District.
OHSR Completed,
G.O.Rt.No.103, Repairs to class room, repairs to class
School Education dormitories, construction of rooms, dormitory
6 126.00 45.40
(TRG)Dept, OHSR 40000 Lts at work completed.
Dt.30.04.2015 Bheemunipatnam, Vizag Dt. Final bill pending at
PAO
Budget sanctioned in
2016-17
(U.O.Note.No.440/A Details submitted
7 For construction of buildings 2500.00 2441.51
.III/2016-17, dt: (Annexure A)
04.04.2016) of C &
DSE
Towards maintenance/ Repairs
G.O Rt.No.281,
to the existing Toilet blocks,
School Education Details submitted
8 providing new toilet blocks, 2504.00 1225.80
(TRG) Department, (Annexure B)
improving water supply
dated 28.11.2016
facilities in APR Institutions.

In addition to the above sanctions, the Government have approved the proposals
under NAABARD vide Lr No 26021/1/NAABARD. SP/ 2017 dt 19-06-2017 and allocated an
amount of Rs 50.00 Crores. The DPRs were also submitted by the APREI Society to the
Finance Department for sanction of funds. The orders are awaited.
3

PRESENT STAGE AS ON 22.07.2021

The Government has sanctioned Rs. 50.00 crores to 20 APRE Institutions under NABARD
RIDF-XXIII vide Go No 273. The details are as follows:

Sl. Sanctioned
Types of Buildings Completed progress
No Nos / halls
1 Class rooms 38 26 12
2 Dormitories 57 34 23
3 Kitchen 7 2 5
4 Dining hall 10 4 6
5 Principal Quarters 4 1 3
6 Teaching Quarters 28 15 13
Non-Teaching
7 12 8 4
Quarters
8 Compound wall 3300 1933 1367
2.1.6.1 Buildings:
• Although land was available in respect of five schools, they were running in private
buildings due to non-release of funds for construction of buildings.
EXPLANATORY NOTES:
The Government has sanctioned each Rs. 600.00 lakhs to APR School Nutimadugu
& APR School Chilakaluripeta under NABARD RIDF XXIII towards Construction of full-
fledged buildings. The stages of works are as follows:
Sl. Type of Nos / STAGE OF THE WORKS
NO building Halls NUTIMADUGU CHILAKALURIPETA
01 Class rooms 10 Slab laid Construction Completed
02 Dormitories 04 Basement level Construction Completed
03 Kitchen 01 Construction Completed
04 Dining Hall 01 Construction Completed
Basement level
05 Principal Qr 01 Construction Completed
06 Teaching Qrs 04 Construction Completed
Construction
07 01 Completed Construction Completed
of OHSR
Construction of school building including dormitories, staff quarters for APRS, Atmakur

(SPS Nellore district) was sanctioned in 2012-13 at an estimated cost of 13 crores.
The works remained incomplete at slab level (June 2016) for want of funds after
incurring an amount of 5.23 crore.
EXPLANATORY NOTES:
Regarding construction of buildings at APR School Atmakur Nellore District, it is submitted
that the works are completed and handed over to the Principal. The buildings are put in
use by students and staff.
• Construction of dormitories and staff quarters for APRS, Vayalpadu (Chittoor district) was
sanctioned in 2012-13 at an estimated cost of 1.98 crore. The works remained
incomplete (June 2016) for want of funds after incurring 1 .25 crore.

EXPLANATORY NOTES:
i. It is submitted that regarding construction works at APR School Vayalpadu Chittoor
District, the construction of dormitory block was completed and construction of Principal
Quarters-1 and Teaching Quarters-4 are under progress (plastering, flooring and
4

painting works are in pending). The Executive Engineer APEWIDC Chittoor was
requested for early completion of works.

PRESENT STAGE AS ON 22.07.2021

Sl Type of Nos /
Stage Remarks
NO building Halls
The society has already requested the
01 Dormitories 6 Completed Government to release funds for
completion of Principal quarters and
02 Principal Qr 01 Plastering, flooring teaching quarters vide letter Rc.
and painting works No.Engg/A4/782/2014-21 dt:
Teaching are pending 06.07.2020. After receipt of funds the
03 04
Qrs works will be completed in full shape.

2.1.6.2 Classrooms, Laboratories and other rooms:

As per the formulation of the Engineering wing of APREIS, each residential school is
required to be provided with 27 rooms for accommodating classes, laboratories, library
etc. Audit scrutiny/ physical verification showed the following.
i) In 29 out of 34 residential schools in the State,
there was a shortage of 314 rooms (34 percent) against the requirement of 918
rooms intended for Classrooms, laboratory, library, etc. In 17 out of 36 schools,
the shortfall was more than 10 rooms.

ii) Although additional classrooms were taken up in Girls' schools at Venkatagiri (two
rooms at Rs. 7.29 lakh) and Ammanabrolu (four rooms at Rs. 12 lakh) in 2010-
11 with Rajiv Vidya Mission (RVM) funds, they remained incomplete due to devoid of
flooring, fitting of doors and windows and electrical works. The Principals stated
(February 2016) that works were not completed for want of funds. Shortages of
class rooms were noticed in both the schools.

EXPLANATORY NOTES:

i) Out of total required 779 Classrooms, Laboratories and other rooms 271 rooms are
proposed to construct for the year 2017-18 from the sanctioned funds by the
Government under various schemes.

PRESENT STAGE AS ON 22.07.2021

Out of 271 classrooms, laboratories and other rooms, the Government have
sanctioned 141 classrooms, laboratories and other rooms from 2016-17. The status of
buildings is as detailed below:

Tenders were Tenders


Progress
Sl. Types of finalized and to be
Sanctioned Completed at various
No Buildings works to be finalized
stages
Grounded
Classrooms,
1 Laboratories 141 115 16 10 0
and other rooms

ii) Regarding APR School Ammanabrolu Prakasham District, the APREI Society the
additional class rooms were completed and handed over to the Principal and they are
using.
5

2.1.6.3 Dormitories

Government instructions (2008) stipulated that all residential schools should be


provided with adequate dormitories, recreation hall, etc. fir the students.

As per the data furnished by the Engineering wing of APREIS, each residential school
is required to be provided with 10 dormitories to accommodate the children. Audit scrutiny/
physical verification showed the following:

i) Shortage of dormitories was noticed in all the 34 residential schools. There


was shortage of 257 dormitories (76 per cent) against the requirement of 340
dormitories to accommodate the children in the 34 schools.

ii) Dormitories were not at all provided in lives out of 34 schools, and in 29 schools
the shortage was more than five against 10 dormitories. As a result, the
existing classrooms were used as dormitories during night.

EXPLANATORY NOTES:

Out of total required 362 Dormitories 146 dormitories are proposed to construct for
the year 2017-18 from the sanctioned funds by the Government under various schemes.

PRESENT STAGE AS ON 22.07.2021

Out of 146 dormitories, the Government have sanctioned 125 Dormitories from
2016-17 to 2020-21 and the status of progress is as follows:

Progress Tenders were


Sl. Types of at finalized and
Sanctioned Completed
No Buildings various works to be
stages Grounded
1 Dormitories 125 74 41 10

2.1.6.4 Dining Hall

Government instructions (2008) stipulated that all residential schools should be


provided with adequate dining halls, kitchen, stores, etc.

As per the Engineering wing of APREIS, each residential school is required to be


provided with three halls and one kitchen.

Audit scrutiny/ physical verification showed that there were shortages of dining
halls were noticed in all the 34 schools. There was shortage of 69 dining halls (68 per
cent) against the requirement of 102 halls in the 34 schools. As a result, it was noticed
that the students were dining in open spaces available in the school premises.

EXPLANATORY NOTES:

Out of total required 109 Dining halls 36 dining halls are proposed to construct for
the year 2017-18 from the sanctioned funds by the Government under various schemes.

PRESENT STAGE AS ON 22.07.2021


Out of 36 Dining halls, the Government have sanctioned 20 Dining halls from 2016-
17 to 2020-21 and the status of works is as follows:
6

Progress Tenders were


Sl. Types of
Sanctioned Completed at various finalized and works
No Buildings
stages to be Grounded
Dining
1 20 7 11 2
hall

2.1.6.5. WATER SUPPLY

Government instructions (2008) stipulated that all residual schools should be


provided with adequate water supply facilities.
It was seen in audit that Overhead tanks were not available in 25 out of 34
schools to ensure running water supply to toilets and other purposes.

In test checked APRS (Girls), Venkatagiri, it was observed that 'overhead tank'
was constructed during 2008-09 at a cost of Rs. 9.50 lakh. However, it was not put to
use for want of new bore well which would cost another Rs.1.50 lakh. Thus, due to the
failure in providing a bore well, the tank built at a cost of Rs. 9.50 lakh remained
unutilized.

EXPLANATORY NOTES: -

The Government in G.O. Rt. No. 281, Dt. 28-11-2016, School Education, (Trg.)
Dept. issued sanction orders for an amount of Rs. 25.04 Crores for maintenance/repairs
to the existing Toilet Block and providing Toilet Blocks and improving the water supply
facilities in APRE Institutions under “Capital Grants” head. Accordingly, administrative
sanction orders for the proposed works were issued by the Society. The works have
been entrusted to the Executive Engineer, SSA of the concerned District.

Further, it is submitted that at APRS (Girls), Venkatagiri a separate bore well was
dug and provided water supply to the Overhead tanks and is put in use.

2.1.6.5. Toilets and Bathrooms

Government stipulated that all residential schools should be provided with


adequate toilets and bathrooms, etc. for the students.
As per the Engineering wing of APREIS, each residential school is required to
be provided with 40 Toilets and bathrooms. Audit scrutiny/ physical verification showed
the following: -

i) In 32 of 34 residential schools, there was a shortage of 638 toilets and bathrooms


(47 percent) against the requirement of 1,360 toilets and bathrooms.

In 10 out 34 schools the shortfall was more than 20 (29 per cent) against 40 toilets
and bathrooms required. The shortfall was particularly high in five 9 residential schools,
where only less than five toilets were provided against the requirement of 40.

Out of total required 2880 Toilets & Bathrooms 1160 Toilets & Bathrooms are
proposed to construct for the year 2017-18 from the sanctioned funds by the Government
under various schemes.

PRESENT STAGE AS ON 22.07.2021

Further it is submitted that 1120 Toilets & Bathrooms from 2016-17 to 2020-21
were sanctioned and the status of the works is as detailed:
7

Sl.
Types of Buildings Sanctioned Completed Progress To be Grounded
No
1 Toilets & Bath rooms 1120 999 25 96

2.1.6.6. Staff Quarters.

In the Residential school pattern, the children were to be supervised round the clock
by the teachers where they were treated as loco parents of the students. Hence, staff
quarters are very much essential. Government stipulated that all residential schools should
have adequate staff quarters for Principal, Vice-Principal, teaching and non-teaching
staff.

As per the formulation of Engineering wing of APREIS, each residential school is


required to be provided with a Principal's quarter along with 24 teaching and 16 non-
teaching staff quarters. Audit scrutiny showed that quarters were not at all provided to
Principals in 14 out of 34 residential schools. In four out of 20 schools where available
they were in dilapidated condition. The Principals of these schools were residing away from
the school premises. Further, there was shortage of quarters for teaching and non-teaching
staff in all the 34 schools.

During test check, it was observed in APRS (Girls), Venkatagiri that construction
of 16 staff quarters was taken up in 2006 at an estimated cost of Rs.1.15 crore. However,
construction remained incomplete at basement/ pillars/ slab level and works were
abandoned (January 2008) for want of funds after incurring Rs.33 lakh

EXPLANATORY NOTES:-

The Society vide proceeding Rc.No. Engg/A4/676/06-16 (18) DT: 26.09.2017 has
issued administrative Sanction for Rs. 50.00 lakhs towards Completion of incomplete
quarters and Repairs to existing school and dormitory buildings, but the Principal vide
letter Rc.no.03-2/B/2018 dt: 05.03.2019 has requested the Secretary APREI Society to
divert the funds for construction of 02 class rooms and 02 Laboratories. The work was not
started by Executive Engineer, SSA and the sanctioned funds are lapsed.
a) Principal Quarters:
Out of total required 40 Principal Quarters 17 Quarters were proposed to construct
for the year 2017-18 and out of 17 only, 09 quarters were sanctioned from 2016-17 to
2020-21.
Sl.
Types of Buildings Sanctioned Completed Progress
No
1 Principal Quarters 7 3 4
b) Teaching staff quarters:
Out of total required 906 Teaching staff Quarters 277 Quarters were proposed to
construct for the year 2017-18 out of 277 only 40 Quarters were sanctioned from 2016-
17 to 2020-21.
Sl.
Types of Buildings Sanctioned Completed Progress
No
1 Teaching Quarters 40 23 17
8

c) Non-Teaching Staff quarters:


Out of total required 684 Non-Teaching Staff Quarters 153 Non-Teaching staff Quarters
are proposed to construct for the year 2017-18 and out of 153 Quarters, only 20 Non-
Teaching Quarters were sanctioned from 2016-17 to 2020-21.

The Present status of the Staff Quarters is as detailed below:

Sl.
Types of Buildings Sanctioned Completed Progress
No
1 Non-Teaching Quarters 20 16 4

2.1.6.7 Compound Wall

As per Government's stipulation, all residential schools should have a compound


wall all around the school.

Audit scrutiny/physical verification by Audit team showed that compound wall was
not provided in 10 out of 34 residential schools including four 1° girls' schools. In another
15 schools including six 11 girls' schools, compound wall was only partially available.

EXPLANATORY NOTES: -

Out of total required 28 Schools (78427 Mts) 04 Institutions (3100 Mts) are
proposed to construct compound wall for the year 2017-18 from the sanctioned funds by
the Government under various schemes

PRESENT STAGE AS ON 22.07.2021

Out of 78427 Rmts of compound wall the Government have sanctioned 6971 Rmts
from 2016-17 to 2020-21 and the status of progress is as follows:

Sl. Types of To be
Sanctioned Completed Progress
No Buildings Grounded
1 Compound wall 6971 2385 2481 2105

2.1.6.8 INFRASTRUCTURE IN RESIDENTIAL DEGREE / JUNIOR COLLEGES.

Nine out of 11 Residential colleges (Degree College: 1, Junior Colleges: 10) were
functioning in own buildings. The remaining two 12 colleges were running in rented
buildings. Audit scrutiny of data/ details furnished by APREIS and physical verification
of five out of 11 colleges showed that adequate infrastructure facilities were not provided
in the colleges. There was shortage of classrooms (91 against 203 required), dormitories
(39 against 58 required), toilets & bathrooms (224 against 360 required).

In test-checked APRJC (Boys), Gyarampalli, nine staff quarters were constructed


(December 2008) at a cost Rs.25 lakh. However, only four out of the nine were
completed fully and occupied by staff. The remaining five quarters which remained
incomplete without amenities like toilets, water facility etc were being used as
dormitories as there was shortage of dormitories for boarders. Thus, the purpose of
constructions was not achieved and the students were forced to stay in accommodation
without basic amenities.
9

Sl. Total Proposed in


Name of works
No required year 2017-18
Classrooms, Laboratories and
1 113 28
other rooms
2 Dormitories 60 19
3 Dining Hall 21 08
4 Toilet & Bathrooms 720 397
Staff Quarters
a)
5 Principal quarter 8 2
b) Teaching staff quarters 182 32
c) Non-teaching staff quarters 170 20
06 Colleges 01 college (600
6 Compound wall
(3155 Mts) Mts)

PRESENT STAGE AS ON 22.07.2021


SATGE OF WORKS
Tenders
Proposed Sanctioned Progress were
Sl.
Name of works in year by in finalized Tender
No Completed
2017-18 Government various and works stage
stage to be
Grounded
Classrooms,
1 Laboratories 28 08 02 0 00 06
and other rooms
2 Dormitories 19 09 02 06 0 0
3 Dining Hall 08 04 0 3 1 0
4 Toilet & Bathrooms 397 20 20 0 0 0
Staff Quarters
a) Principal quarter 2 0 0 0 0 0
5b) Teaching staff quarters 32 0 0 0 0 0
c) Non-teaching staff
20 0 0 0 0 0
quarters
3755
6 Compound wall 600 Mts 500 100 Mts 0 0
Mts

Superintending Engineer
APREI Society
10

ENGINEERING ITEMS
LATEST STAGE AS ON 22-07-2021
2.1.6 Infrastructure:
It is submitted that the APREI society has submitted the following proposals
from time to time to the Government to release funds for construction of balance
building for individual schools and also total APR Institutions. The details of works
requested to Government are as follows.
Sl.
Proposal File
N Item of works Amount Scheme
Number
o
construction of additional
Rc.No.Engg/A4/160/1 buildings and also for
Rs 679.25 Additional Funds
1 3-14, dt 10-10- maintenance for existing
lakhs under Capital Grants
2014, dt 30.03.2015 buildings at Mukkavaripalli,
Kadapa District
To improve the infrastructure
Rc.No.Engg/A4/160/8
facilities in APR Schools & Junior Rs.631.73 Additional Funds
2 3-15, dated 06-
Colleges over a period of six crores under Capital Grants
10-2015
years under Capital Grants
Towards improvement of
Lr.Rc.No.Engg/A4/16
minimum requirement of
0/83-16, dt: Rs.314.37 Additional Funds
3 infrastructure faculties in APR
09.02.2016, dt: crores under Capital Grants
Schools & Junior Colleges under
17.03.2016
Capital Grants head.
crores towards providing
additional toilet block,
Rc.No.Engg/A4/160/8 maintenance/ repairs to the Rs 25.04 Additional Funds
4
3-15, dt: 22.08.2015 existing toilet block and Crores under Capital Grants
improving the water supply
facilities in APRE Institutions
Rc.No.Engg/A4/760/1 For completion of ongoing works Rs.1177.00 Additional Funds
5
5-16, dt: 01.07.2016 in 13 institutions. lakhs under Capital Grants
Lr.No.Engg/A4/785/1
Construction of additional Rs.114.05 RIDF NAABARD
6 7-18, dt: 21.09.2016
buildings in 30 APR Institutions Crores
& 03.08.2017
Lr.No.Engg/A4/786/1 Construction of additional Rs 196.00
7 ANNUITY BASIS
7-18, dt: 05.08.2017 buildings in 32 APR Institutions. Crores

The Government have sanctioned the following funds under varies schemes
for construction of additional buildings in APR Institutions

SL Amount
Sanction GOs Name the works Expr Stage of work
No sanctioned
Construction of full-fledged
G.O.Rt.No.173, School
works including compound Completed and handed
1 Education (TRG) Dept, 1493.00 1058.51
wall at S,N.Padu Prakasham over to the Principal
dt.4.09.2015
District
G.O.Rt.No.1433, Construction of full-fledged
School Education works Excluding compound Completed and handed
2 1300.00 889.51
(SE Genl II) Dept, wall at Atmakur, Nellore over to the Principal
Dt.16.11.2013 District.
Dormitory completed and
G.O.Rt.No.290. Construction of dormitory, handed over, for Staff
,School Education SE Principal Quarters and 4 quarters flooring, painting
3 198.00 124.99
Genl II)Dept, TSQs at Vayalpadu, Chittoor works are to be completed.
Dt.08.02.2013 District. Work stopped for want of
funds
11

Retenders are to be called


for. Recently the earlier
G.O.Rt.No.351 School land was cancelled and
Construction of dining hall at
4 Education (SE Genl 107.40 0.00 allotted new land
Piler, Chittoor District.
II)Dept,Dt.08.03.2013 (7.00.Acers) at
Gudarevupalle village, Piler
Mandal, Chittoor dist.
Completion of first floor
G.O.Rt.No.22 School rooms and construction of
5 Education (TRG)Dept, compound wall at 193.00 143.67 Works completed,
Dt.04.02.2015 Vomaravalli, Srikakulam
District.
Repairs to class room, OHSR Completed, repairs
G.O.Rt.No.103, School
dormitories, construction of to class rooms, dormitory
6 Education (TRG)Dept, 126.00 45.40
OHSR 40000 Lts at work completed. Final bill
Dt.30.04.2015
Bheemunipatnam, Vizag Dt. pending at PAO
Budget sanctioned in
2016-17
(U.O.Note.No.440/A.II Details submitted
7 For construction of buildings 2500.00 2441.51
I/2016-17, dt: (Annexure A)
04.04.2016) of C &
DSE
Towards maintenance/
G.O Rt.No.281, School Repairs to the existing Toilet
Education (TRG) blocks, providing new toilet Details submitted
8 2504.00 1225.80
Department, dated blocks, improving water (Annexure B)
28.11.2016 supply facilities in APR
Institutions.

In addition to the above sanctions, the Government have approved the


proposals under NAABARD vide Lr No 26021/1/NAABARD. SP/ 2017 dt 19-06-2017
and allocated an amount of Rs 50.00 Crores. The DPRs were also submitted by the
APREI Society to the Finance Department for sanction of funds. The orders are
awaited.
PRESENT STAGE AS ON 22.07.2021
The Government have sanctioned Rs. 50.00 crores to 20 APRE Institutions under
NABARD RIDF-XXIII vide Go No 273. The details of works and stage are as follows:
Sl. Sanctioned
Types of Buildings Completed progress
No Nos / halls
1 Class rooms 38 26 12
2 Dormitories 57 34 23
3 Kitchen 7 2 5
4 Dining hall 10 4 6
5 Principal Quarters 4 1 3
6 Teaching Quarters 28 15 13
Non-Teaching
7 12 8 4
Quarters
8 Compound wall 3300 1933 1367
2.1.6.1 Buildings:

• Although land was available in respect of five schools, they were running in
private buildings due to non-release of funds for construction of buildings.
12

EXPLANATORY NOTES:
The Government has sanctioned each Rs. 600.00 lakhs to APR School
Nutimadugu & APR School Chilakaluripeta under NABARD RIDF XXIII towards
Construction of full-fledged buildings. The stages of works are as follows:

STAGE OF THE WORKS


Sl. Type of Nos / APRS APRS
NO building Halls NUTIMADUGU, CHILAKALURIPETA,
Anantapur dist Guntur dist
01 Class rooms 10 Slab laid
All the works are
02 Dormitories 04 Basement level
completed. The electricity
03 Kitchen 01
Department has to give
04 Dining Hall 01
Basement level power connection. After
05 Principal Qrs 01
getting power connection
06 Teaching Qrs 04
the school will be shifted
Construction immediately
07 01 Completed
of OHSR

• Construction of school building including dormitories, staff quarters for APRS,


Atmakur (SPS Nellore district) was sanctioned in 2012-13 at an estimated cost
of 13 crores. The works remained incomplete at slab level (June 2016) for
want of funds after incurring an amount of 5.23 crore.
EXPLANATORY NOTES:
Regarding construction of buildings at APR School Atmakur Nellore District, it is
submitted that the works are completed and handed over to the Principal. The
school was shifted and the buildings are put in use by students and staff.
• Construction of dormitories and staff quarters for APRS, Vayalpadu (Chittoor
district) was sanctioned in 2012-13 at an estimated cost of 1.98 crore. The
works remained incomplete (June 2016) for want of funds after incurring 1 .25
crore.
EXPLANATORY NOTES:
i) It is submitted that regarding construction works at APR School Vayalpadu
Chittoor District, the construction of dormitory block was completed and
construction of Principal Quarters-1 and Teaching Quarters-4 are under
progress (plastering, flooring and painting works are in pending). The
Executive Engineer APEWIDC Chittoor was requested for early completion of
works.
PRESENT STAGE AS ON 22.07.2021
Sl Type of Nos /
Stage Remarks
NO building Halls
Completed and The society has already requested the
01 Dormitories 6 being used by the Government to release funds for
students completion of Principal quarters and
teaching quarters vide letter Rc.
02 Principal Qr 01 No.Engg/A4/782/2014-21 dt:
Plastering, flooring, 06.07.2020. The Government have
and painting works included this college under NAADU NEDU
Teaching are pending Phase-II programme. The finishing works
03 04
Qrs may be completed under NAADU NEDU
Phase-II programme and put in to use.
13

2.1.6.2 Classrooms, Laboratories and other rooms:


As per the formulation of the Engineering wing of APREIS, each residential school
is required to be provided with 27 rooms for accommodating classes,
laboratories, library etc. Audit scrutiny/ physical verification showed the
following.
In 29 out of 34 residential schools in the State,
there was a shortage of 314 rooms (34 percent) against the requirement of 918
rooms intended for Classrooms, laboratory, library, etc. In 17 out of 36 schools,
the shortfall was more than 10 rooms.

i) Although additional classrooms were taken up in Girls' schools at


Venkatagiri (two rooms at Rs. 7.29 lakh) and Ammanabrolu (four rooms
at Rs. 12 lakh) in 2010-11 with Rajiv Vidya Mission (RVM) funds, they
remained incomplete due to devoid of flooring, fitting of doors and windows
and electrical works. The Principals stated (February 2016) that works were
not completed for want of funds. Shortages of class rooms were noticed in
both the schools.
EXPLANATORY NOTES:
i) Out of total required 779 Classrooms, Laboratories and other rooms, 271
rooms are proposed to construct for the year 2017-18 from the sanctioned
funds by the Government under various schemes.
PRESENT STAGE AS ON 22.07.2021
Out of 271 classrooms, laboratories and other rooms, the Government have
sanctioned 141 classrooms, laboratories and other rooms from 2016-17 to 2020-
21. The status of buildings is as detailed below:
Not started works are
cancelled vide Memo No.
Sl. Fin01-FMUASD(WR-
Types of Buildings Sanctioned Completed Progress
No 1)/18/2019,
(Comp.No.898809) dt:
01.08.2019
Classrooms,
1 Laboratories and 141 115 16 10
other rooms

ii) Regarding APR School Ammanabrolu Prakasham District, the APREI


Society the additional class rooms were completed and handed over to the
Principal and they are in use.
2.1.6.3 Dormitories
Government instructions (2008) stipulated that all residential schools should
be provided with adequate dormitories, recreation hall, etc. for the students.

As per the data furnished by the Engineering wing of APREIS, each residential
school is required to be provided with 10 dormitories to accommodate the children.
Audit scrutiny/ physical verification showed the following:
i) Shortage of dormitories was noticed in all the 34 residential schools.
There was shortage of 257 dormitories (76 per cent) against the
14

requirement of 340 dormitories to accommodate the children in the 34


schools.
ii) Dormitories were not at all provided in lives out of 34 schools, and in 29
schools the shortage was more than five against 10 dormitories. As a
result, the existing classrooms were used as dormitories during night.
EXPLANATORY NOTES:
Out of total required 340 Dormitories, 146 dormitories are proposed to
construct for the year 2017-18 from the sanctioned funds by the Government under
various schemes.

PRESENT STAGE AS ON 22.07.2021


Out of 146 dormitories, the Government have sanctioned 125 Dormitories
from 2016-17 to 2020-21 and the status of progress is as follows:

Not started works are


cancelled vide Memo No.
Sl. Types of Fin01-FMUASD(WR-
Sanctioned Completed Progress
No Buildings 1)/18/2019,
(Comp.No.898809) dt:
01.08.2019
1 Dormitories 125 74 41 10

2.1.6.4 Dining Hall


Government instructions (2008) stipulated that all residential schools should
be provided with adequate dining halls, kitchen, stores, etc.

As per the Engineering wing of APREIS, each residential school is required


to be provided with three halls and one kitchen.

Audit scrutiny/ physical verification showed that there were shortages of


dining halls were noticed in all the 34 schools. There was shortage of 69 dining
halls (68 per cent) against the requirement of 102 halls in the 34 schools. As a
result, it was noticed that the students were dining in open spaces available in
the school premises.
EXPLANATORY NOTES:
Out of total required 109 Dining halls 36 dining halls are proposed to
construct for the year 2017-18 from the sanctioned funds by the Government under
various schemes.
PRESENT STAGE AS ON 22.07.2021
Out of 36 Dining halls, the Government have sanctioned 20 Dining halls from
2016-17 to 2020-21 and the status of works is as follows:
Not started works are cancelled
Progress
Sl. Types of vide Memo No. Fin01-
Sanctioned Completed at various
No Buildings FMUASD(WR-1)/18/2019,
stages
(Comp.No.898809) dt: 01.08.2019
1 Dining hall 20 7 11 2
15

2.1.6.5. WATER SUPPLY


Government instructions (2008) stipulated that all residual schools should
be provided with adequate water supply facilities.
It was seen in audit that Overhead tanks were not available in 25 out of
34 schools to ensure running water supply to toilets and other purposes.

In test checked APRS (Girls), Venkatagiri, it was observed that 'overhead


tank' was constructed during 2008-09 at a cost of Rs. 9.50 lakh. However, it
was not put to use for want of new bore well which would cost another Rs.1.50
lakh. Thus, due to the failure in providing a bore well, the tank built at a cost of
Rs. 9.50 lakh remained unutilized.
EXPLANATORY NOTES: -
The Government in G.O. Rt. No. 281, Dt. 28-11-2016, School Education,
(Trg.) Dept. issued sanction orders for an amount of Rs. 25.04 Crores for
maintenance/repairs to the existing Toilet Block and providing Toilet Blocks and
improving the water supply facilities in APRE Institutions under “Capital Grants”
head. Accordingly, administrative sanction orders for the proposed works were
issued by the Society. The works have been entrusted to the Executive Engineer,
SSA of the concerned District.
Further, it is submitted that at APRS (Girls), Venkatagiri a separate bore
well was dug and provided water supply to the Overhead tank and now it is being
used by the school.
2.1.6.5. Toilets and Bathrooms
Government stipulated that all residential schools should be provided with
adequate toilets and bathrooms, etc. for the students.
As per the Engineering wing of APREIS, each residential school is
required to be provided with 40 Toilets and bathrooms. Audit scrutiny/ physical
verification showed the following: -
i) In 32 of 34 residential schools, there was a shortage of 638 toilets and
bathrooms (47 percent) against the requirement of 1,360 toilets and
bathrooms.
In 10 out 34 schools the shortfall was more than 20 (29 per cent) against 40
toilets and bathrooms required. The shortfall was particularly high in five 9
residential schools, where only less than five toilets were provided against the
requirement of 40.
Out of total required 2880 Toilets & Bathrooms 1075 Toilets & Bathrooms are
proposed to construct for the year 2017-18 from the sanctioned funds by the
Government under various schemes.
PRESENT STAGE AS ON 22.07.2021
Further it is submitted that 1475 Toilets & Bathrooms from 2016-17 to 2020-
21 were sanctioned by Government. The status of the works is as detailed:
Sl.
Types of Buildings Sanctioned Completed Progress
No
1 Toilets & Bath rooms 1475 1408 163
16

2.1.6.6. Staff Quarters.


In the Residential school pattern, the children were to be supervised round
the clock by the teachers where they were treated as loco parents of the students.
Hence, staff quarters are very much essential. Government stipulated that all
residential schools should have adequate staff quarters for Principal, Vice-
Principal, teaching and non-teaching staff.
As per the formulation of Engineering wing of APREIS, each residential
school is required to be provided with a Principal's quarter along with 24 teaching
and 16 non-teaching staff quarters. Audit scrutiny showed that quarters were not
at all provided to Principals in 14 out of 34 residential schools. In four out of 20
schools where available they were in dilapidated condition. The Principals of these
schools were residing away from the school premises. Further, there was shortage
of quarters for teaching and non-teaching staff in all the 34 schools.

During test check, it was observed in APRS (Girls), Venkatagiri that


construction of 16 staff quarters was taken up in 2006 at an estimated cost of
Rs.1.15 crore. However, construction remained incomplete at basement/ pillars/
slab level and works were abandoned (January 2008) for want of funds after
incurring Rs.33 lakh
EXPLANATORY NOTES:
The Society vide proceeding Rc.No. Engg/A4/676/06-16 (18) DT: 26.09.2017
has issued administrative Sanction for Rs. 50.00 lakhs towards Completion of
incomplete quarters and Repairs to existing school and dormitory buildings, but the
Principal vide letter Rc.no.03-2/B/2018 dt: 05.03.2019 has requested the
Secretary APREI Society to divert the funds for construction of 02 class rooms and
02 Laboratories. The work was not started by Executive Engineer, SSA and the
sanctioned funds are lapsed.
a) Principal Quarters:
Out of total required 40 Principal Quarters 17 Quarters were proposed to
construct for the year 2017-18 and out of 17 only, 07 quarters were sanctioned
from 2016-17 to 2020-21.
Sl.
Types of Buildings Sanctioned Completed Progress
No
1 Principal Quarters 7 3 4
b) Teaching staff quarters:
Out of total required 906 Teaching staff Quarters 277 Quarters were
proposed to construct for the year 2017-18 out of 277 only 40 Quarters were
sanctioned from 2016-17 to 2020-21.
Sl.
Types of Buildings Sanctioned Completed Progress
No
1 Teaching Quarters 40 23 17
17

c) Non-Teaching Staff quarters:


Out of total required 684 Non-Teaching Staff Quarters 153 Non-Teaching staff
Quarters are proposed to construct for the year 2017-18 and out of 153 Quarters,
only 20 Non-Teaching Quarters were sanctioned from 2016-17 to 2020-21.
The Present status of the Staff Quarters is as detailed below:

Sl.
Types of Buildings Sanctioned Completed Progress
No
1 Non-Teaching Quarters 20 16 4
2.1.6.7 Compound Wall
As per Government's stipulation, all residential schools should have a
compound wall all around the school.
Audit scrutiny/physical verification by Audit team showed that compound wall
was not provided in 10 out of 34 residential schools including four 1° girls' schools.
In another 15 schools including six girls' schools, compound wall was only
partially available.
EXPLANATORY NOTES: -
Out of total required 28 Schools (78427 Mts) 04 Institutions (3100 Mts) are
proposed to construct compound wall for the year 2017-18 from the sanctioned
funds by the Government under various schemes.

PRESENT STAGE AS ON 22.07.2021


Out of 78427 Rmts of compound wall the Government have sanctioned
11864 Rmts from 2016-17 to 2020-21 and the status of progress is as follows:
Not started works are cancelled
vide Memo No. Fin01-
Sl. Types of
Sanctioned Completed Progress FMUASD(WR-1)/18/2019,
No Buildings (Comp.No.898809) dt:
01.08.2019
1 Compound wall 11864 5935 4824 1105
2.1.6.8 INFRASTRUCTURE IN RESIDENTIAL DEGREE / JUNIOR COLLEGES.
Nine out of 11 Residential colleges (Degree College: 1, Junior Colleges:
10) were functioning in own buildings. The remaining two 12 colleges were
running in rented buildings. Audit scrutiny of data/ details furnished by APREIS
and physical verification of five out of 11 colleges showed that adequate
infrastructure facilities were not provided in the colleges. There was shortage of
classrooms (91 against 203 required), dormitories (39 against 58 required),
toilets & bathrooms (224 against 360 required).
In test-checked APRJC (Boys), Gyarampalli, nine staff quarters were
constructed (December 2008) at a cost Rs.25 lakh. However, only four out of
the nine were completed fully and occupied by staff. The remaining five quarters
which remained incomplete without amenities like toilets, water facility etc were
being used as dormitories as there was shortage of dormitories for boarders.
Thus, the purpose of constructions was not achieved and the students were forced
to stay in accommodation without basic amenities.
18

Sl. Proposed in year


Name of works Total required
No 2017-18
Classrooms, Laboratories and
1 113 28
other rooms
2 Dormitories 60 19
3 Dining Hall 21 08
4 Toilet & Bathrooms 720 397
Staff Quarters
d)
5 Principal quarter 8 2
e) Teaching staff quarters 182 32
f) Non-teaching staff quarters 170 20
06 Colleges
6 Compound wall 01 college (600 Mts)
(3805 Mts)
PRESENT STAGE AS ON 22.07.2021
Proposed SATGE OF WORKS
from Sanctioned
Sl.
Name of works 2017-18 by Tender
No Completed Progress
to Government stage
2020-21
Classrooms,
1 Laboratories 28 08 04 04 00
and other rooms
2 Dormitories 19 09 03 05 01
3 Dining Hall 08 04 01 2 01
4 Toilet & Bathrooms 397 20 20 0 0
Staff Quarters
i) Principal quarter 2 0 0 0 0
5j) Teaching staff quarters 32 0 0 0 0
k) Non-teaching staff
20 0 0 0 0
quarters
6 Compound wall 3805 Mts 600 Mts 500 100 Mts 0

SANCTIONS UNDER NAADU NEDU PHASE-I & PHASI-II PROJECTS:

APR SCHOOLS:
The Government have included 43 APR Schools under NAADU NEDU
Phase-I project towards maintenance of existing buildings & providing
additional infrastructure facilities. In this project the works are taken up like
repairs to main school block, electrification, paintings, providing of green
chalk boards and construction of new toilet block works are taken up and
completed.

Further, the Government again included these 43 APR Schools under


NAADU NEDU Phase-II project. In this project it is proposed to maintenance
& providing additional infrastructure facilities in the hostel buildings will be
taken up and completed.

APR JUNIOR COLLEGES:


The Government have included all 07 Junior Colleges under NAADU
NEDU Phase-II project. In this project maintenance of existing buildings and
providing additional infrastructure facilities i.e., construction of toilet block,
providing electrification to existing buildings, paintings and providing of
green chalk boards will be taken up in this project.
19

APR DEGREE COLLEGE NAGARJUNA SAGAR, GUNTUR DIST:


➢ The Government have sanctioned 190.00 lakhs towards construction
of additional dormitories and dining hall under NABARD funds. These
works are under progress.
➢ The Government have included this College under NAADU NEDU
Phase-II project. In this project maintenance of existing buildings and
providing additional infrastructure facilities i.e., construction of toilet
block, providing electrification to existing buildings, paintings and
providing of green chalk bords will be taken up in this project.
➢ RUSA has sanctioned an amount of Rs. 200.00 lakhs for improvement
of infrastructure facilities and renovation of existing buildings including
construction of additional class rooms – Tenders were finalized and
works will be started very soon.

Superintending Engineer