List of CMPs in respect of I.B.Division, Ananthapuramu as on 21.08.2023.

Sl.No. Computer No. CMP No. From District Subject File No. / C.No. Status of the file Action taken Report

1 2 3 4 5 6 7 8 9

Estimates for
1. Estimate submitted to Superintending Engineer,
Irrigation Circle, Ananthapuramu for the work of
Improvements to Venkatampalli MI tank Venkatam palli
(V) in Vajrakarur (M) Rs. 34.00 lakhs vide this office lr
no. 623SE dt. 22.12.2020 obtaining Administrative
approval.
2.Estimate submitted to Superintending Engineer,
Requesting Construction of
CMP.1528/Addl. Irrigation Circle, Ananthapuramu for the work of
check dam and improvement Report awaaited from
secy (DR)/2020, Sri Y.Visweswara Reddy Improvements to Donekal MI tank
1 1205935 Ananthapuramu to Irrigation tanks to improve MINR/127/2020 the CE,MI vide Memo
Dt:22.07.2020 Honble EX MLA, Uravakonda Donekal (V) in Vdapanakal (M) for Rs. 180.00 lakhs vide
the ground water in Dt: 10.08.2020.
this office lr no. 11SE dt.05.01.2021 obtaining
Uravakonda Constituency.
Administrative approval.
3. For construction of Check Dam across Doddivanka
near Tatrkallu (V) in Vajrakarur (M) Ground Water
Department clearance received vide lr no.
632/CD/SSD/PT/T5/2020, Dt. 19.08.2023. Estimate will be
submitted Chief Engineer, Minor Irrigation, Vijayawada,
duly recassting with latest SSR2022-23 in due course for
obtaining approval.

It is submitted that during last 4 years Irrigation potential is


CMP/1490/Addl. Suggesting certain messures Report awaaited from
Sri Talari Rangaiah, MP,(Lok increased due to release of water to all posible tanks from
secy /2020, for improving the Irrigation the CE,MI vide Memo
2 1248909 Sabha) Ananthapuramu Ananthapuramu MINR/150/2020 HLC &HNSS canal appart from the considable rain fall in
Dt:17.07.2020 potential of Ananthapuramu Dt: 07.10.2020
District the district an account of Ground water in borewells raised
District &12.11.2021.
te irrigation optietial is increased last 4 years.

This site is not suitable to construct check dam. It is only


suitable to construct sub-surface dam only.
The formation of new sub-surface dam estimate was re-
CMP/1772/Addl. Requesting sanction of Check Report awaaited from
Sri Kerthi reddy Pedda reddy submitted by the SE/IC/ATP to the CE, Minor & Medium
Secy/ 2020, dams across Penna river at the CE,MI vide Memo
3 1257946 ,MLA Tadipatri Constituency, Ananthapuramu MINR/153/2020 Irrigation, Vijayawada vide SE's Letter
Dt:06.10.2020 sajjaladinne villageTadipatri Dt: 19.10.2020
Anathapuram District F:H-15(Vol-3)/DB/JTO-1/ No. 190 CE, Dated: 04-12-2021
(M) to improve ground water &27.12.2021.
for Rs. 26.50 Crores for obtaining Administrative
Approval .
Requesting to supplyment
the 33 Tanks/Kuntas alleviate
Smt.Jonnalagadda GoAP issued orders to allocation of water vide
CMP/2137/Addl. the drinking water problem Report awaaited from
Padmavathy, G.O.Rt.No.1339, dt:31-05-2022.The DPR for supply of
4 1317293 Secy/2020, Ananthapuramu and to improve the ground MINR/17/2021 the CE,MI vide Memo
MLA,Singanamala Assembly water to 33 tanks in six mandals of Singanamala
Dt:12.12.2020. water level in all six mandals Dt: 06.01.2021.
Constituency. Assembly Constituency is under preparation.
of Singanamala constituency,
Ananthapuramu District.

Estimates for
1. Estimate submitted to Superintending Engineer,
Irrigation Circle, Ananthapuramu for the work of
Improvements to Venkatampalli MI tank Venkatam palli
(V) in Vajrakarur (M) Rs. 34.00 lakhs vide this office lr
no. 623SE dt. 22.12.2020 obtaining Administrative
approval.
2.Estimate submitted to Superintending Engineer,
Requesting sanction of funds
Irrigation Circle, Ananthapuramu for the work of
CMP/2399/Addl. for Construction of check Report awaaited from
Sri Y.Visweswara Reddy Improvements to Donekal MI tank
5 1224890 Secy/2021, Ananthapuramu dams and development of MINR/139/2021 the CE,MI vide Memo
Honble EX MLA, Uravakonda Donekal (V) in Vdapanakal (M) for Rs. 180.00 lakhs vide
Dt:13.1.2021. tanks in Uravakonda Dt: 01.11.2019.
this office lr no. 11SE dt.05.01.2021 obtaining
Constituency.
Administrative approval.
3. For construction of Check Dam across Doddivanka
near Tatrkallu (V) in Vajrakarur (M) Ground Water
Department clearance received vide lr no.
632/CD/SSD/PT/T5/2020, Dt. 19.08.2023. Estimate will be
submitted Chief Engineer, Minor Irrigation, Vijayawada,
duly recassting with latest SSR2022-23 in due course for
obtaining approval.

Estimates for
1. Estimate submitted to Superintending Engineer,
Irrigation Circle, Ananthapuramu for the work of
Improvements to Venkatampalli MI tank Venkatam palli
(V) in Vajrakarur (M) Rs. 34.00 lakhs vide this office lr
no. 623SE dt. 22.12.2020 obtaining Administrative
approval.
2.Estimate submitted to Superintending Engineer,
Requesting sanction of funds
Irrigation Circle, Ananthapuramu for the work of
CMP. No.600/Addl. for improvement of 2 tanks Report awaaited from
Sri Y.Visweswara Reddy Improvements to Donekal MI tank
6 1017713 Secy/2019, Ananthapuramu and Construction of MINR/75/2019 the CE,MI vide Memo
Honble EX MLA, Uravakonda Donekal (V) in Vdapanakal (M) for Rs. 180.00 lakhs vide
Dt:23.10.2019. checkldams in Uravakonda Dt: 06.01.2021.
this office lr no. 11SE dt.05.01.2021 obtaining
Constituency.
Administrative approval.
3. For construction of Check Dam across Doddivanka
near Tatrkallu (V) in Vajrakarur (M) Ground Water
Department clearance received vide lr no.
632/CD/SSD/PT/T5/2020, Dt. 19.08.2023. Estimate will be
submitted Chief Engineer, Minor Irrigation, Vijayawada,
duly recassting with latest SSR2022-23 in due course for
obtaining approval.
Requesting sanction of work
improvement to supply
Smt.Jonnalagadda Estimate submitted to Superintending Engineer, irrigation
CMP. No.5497/ channel leading from Report awaaited from
Padmavathy, Circle Ananthapuramu vide this office lr no. 315SE
7 2032297 Secy to CM/2023, Ananthapuramu Janthaluru kattukalava across MINR/29/2023 the CE,MI vide Memo
MLA,Singanamala Assembly Dt.21.06.2023 in (Sl.no.24) under HAZARD Specification
Dt:17.03.2023. Tadakaleru to feed direct Dt: 28.03.2023.
Constituency. Mitigation Measures
ayacut near Janthaluru Village
Bukkarayasamudram.

Endt.EE/IB/ATP/2C3 (CMP)/DB/JTO-2/No. Dt. .

Submitted to Superintending Engineer, Irrigation Circle Ananthapuramu for favour information and necessary action.

Executive Engineer,
I.B.Division, Ananthapuramu.