Departmental Issues Pending at State

S.No. Department Issue


1 2 3

Clear the pending for Payment Major


works of PABR Groutting work for an
1
amount of Rs.1.74 Crores. (Water
Resource Dept. Major Irrigation)

Construction of New Balancing reservoir


near Unthakal village of Bommanahal
2 Mandal with an estimated cost
Rs.1605.00 Crores and clearing the
pending payment for Major works of
Unthakallu Balancing Reservoir (NABR)

Construction of Pressure Relief wells on


3 downstream of Chagallu barrage to
arrest seepage of water at Pedda
Yekkalur village of Peddapappur mandal

Water Resources Department


( TBP- HLC System)
Water Resources Department
( TBP- HLC System)

Estimate for the work of “Replacement


of rubber seals, erection of new walk
way bridge, sand blasting and painting to
Radial crest gates, supply and erection of
4 new main control panel boards, Sub-
distribution panel boards, control panel
boards, Dam Beautification to MID
Pennar project in
Anantapuramu(District)

Estimate for the work of “providing CC


Lining to the Irrigation Canal of
5
Pendekallu Balancing Reservoir from
Km 1.850 to Km 3.00"

Construction of Distributory System


under PABR Right Canal for creation of
6 ID Ayacut to an extent of 50000 Acres
and 7500 Acres stabilization under tanks
enroute canal

High Level Main Canal(HLMC)-


7 Submission of Estimates for Critical
Structures
Pending at State Level
Estimated Cost
Remarks
(Rs. in Lakhs)
4 5

The bill was uploaded in CFMS module with


CFMs ID : 2023-216265 for Rs.1.08 Crs (pending
for payment) and bils for an amount of Rs.0.86
174 Cr are not uploaded due to insufficinet funds
and allocation of funds 0f Rs. 1.74 Cr is required
to clear the pending payment by the
Government and the same is awaited.

Engineer-in-Chief (Irrigation), Vijayawada vide


letter No.
ENCI/DCE-GDS/OT2/AEE10/TBP.HLC-Genl/CM
297 P, Dated: 13.04.2023 has requested the
Government to release budget of Rs.2.97 Crores
to clear the pending payments to resume the
balance work to finalise the DPR for onward
submission to the Government.

submitted to the Principal Secretary to


Government, Water Resources Department,
Velagapudi for according administrative
approval vide LrNo.CE(P)/ATP/ 255 M
Dated:26.08.2022.
The Collector & District Magistrate has
addressed a DO letter to Prl.Secretary to Govt.
296 Water Resource department to accord
administrative sanction for the work
construction of pressure relief wells vide DO
Rc.No. 39/CCO/2022 dated 03.11.2022 and
Rc.No. E4/5565 dated 28.05.2023

The administrative approval is awaited from the


Government to take up the work.
Submitted to the Principal Secretary to
Government, Water Resources Department,
Velagapudi for according administrative
520 approval vide LrNo.CE(P)/ATP/ 205 M
Dated:20.06.2023.
The Proposal is covered under Hon'ble CM
Assurances

Submitted to the Principal Secretary to


Government, Water Resources Department,
138 Velagapudi for according administrative
approval vide LrNo.CE(P)/ATP/ 180 M
Dated:06.06.2023.

Submitted to the Special Chief Secretary to


Government, Water Resources Department,
13830 Velagapudi for according administrative
approval vide LrNo.CE(P)/ATP/ 20 M
Dated:01.02.2022.

submitted to Engineer-in-Chief (Irrigation),


Vijayawada for obtaining administrative
3346 approval from Government g vide
LrNo.CE(P)/ATP/ 88 ENC & 89 ENC
Dated:06.06.2023.

Superintending Engineer
TBP HLC Circle, Ananthapuramu.