Appendix D.

Construction Schedule - Remaining Boundary wall Work


PJT :Obra “C” 2x660MW Thermal Power Extension Project R0, 2022.06.
Schedule 2022 2023
S/N Description Remarks
Start Finish Duration 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3
1 SCHEDULE
Project Schedule 0 Finish of Boundary wall Installation

Civil Work of Remaining Boundary Wall Work

1 PCC 7/15/2022 5/30/2023 319

2 RCC of footing,Column,Top Beam 8/1/2022 8/28/2023 392

3 Brick work (T=230mm) 8/31/2022 9/27/2023 392

Plastering internal,External
4 8/31/2022 10/27/2023 422
(18THK Cement plaster with Decorative water proofing paint)

5 Painting(Decorative water proofing paint on plastered surface 9/30/2022 10/30/2023 395

6 Concertina coil fixing 10/30/2022 10/30/2023 365

7 Logo precast & Fixing 6/30/2023 10/30/2023 122

8 Settlement 10/31/2023 12/29/2023 59

Note
1. This is reference only, above project schedule would be revised as per site conditions within the Subcontract Period.
2. Human resource and construction equipment are reference only as minimum, the subcontractor shall mobilize all required resources without any additional cost according to the work progress to meet a construction schedule.