PIT BARAT

KDC - AKG PROJECT


Field Observation and Monitoring
Name Pradana Budi I
Change Shift SIANG Easting
21-Aug-22
Date/Time
Pit / Block Yakut/Bacan PIT YAKUT DAN PIT BACAN Northing
RL
Clasification

(1) Exca 110 continue stripping OB


Block 7 Pit Yakut
(2) Exsa 107 continue stripping OB
Block 4 Pit Yakut
(3) Exsa 84 continue stripping OB
Block 2 Pit Yakut
(4) Exsa 88 continue Stripping IB
seam 7/8 Pit Bacan
(5) Exsa 117 continue Stripping Soil
Block 8 Pit Yakut
(6) Dumpingan soil dari exsa 117
4 (7) Dumpingan7
OB dari exsa 110
5
1
pembentukan R.L rencana SP
2
(8) Dumpingan OB dari exsa 107 &
3 84 jika material pasir "layer
8
7 tengah"
9 (9) Dumpingan OB dari exsa 107,
6
84 & 88 jika material bagus "layer
bawah"
PT AKG Observer By, Operation PT AKG Operation PT. KDC

(Pit Engineering AKG) ( Mine Spv. Operation ) ( Mine Spv. PRODUKSI )


PIT BARAT

KDC - AKG PROJECT


Field Observation and Monitoring
Name Pradana Budi I
Change Shift SIANG Easting
21-Aug-22
Date/Time
Pit / Block Yakut/Bacan PIT YAKUT Northing
RL
Clasification

Exsa R-01 clearing dan Front loading Exsa 117


bersihkan kayu "shift siang"

General area ini agar tidak ada


beda tinggi

Front loading Exsa 110


Exsa 116 coal getting
seam 5 block 7

PT AKG Observer By, Operation PT AKG Operation PT.KDC

(Pit Engineering AKG) ( Mine Spv. Operation ) ( Mine Spv. PRODUKSI )


PIT BARAT

KDC - AKG PROJECT


Field Observation and Monitoring
Name Pradana Budi I
Change Shift SIANG Easting
21-Aug-22
Date/Time
Pit / Block Yakut/Bacan PIT YAKUT Northing
RL
Clasification

Exsa 84 Stripping OB
Block 2/3

Exsa 107 Stripping OB


Block 4 GARIS BATAS
BOUNDARY PITA
POSISI RL 120 WARNA MERAH BIRU

PT AKG Observer By, Operation PT AKG Operation PT. KDC

(Engineering AKG) ( Mine Spv. Operation ) ( Mine Spv. PRODUKSI )


PIT BARAT

KDC - AKG PROJECT


Field Observation and Monitoring
Name Pradana Budi I
Change Shift SIANG Easting
21-Aug-22
Date/Time
Pit / Block Yakut/Bacan DISPOSAL IPD KARET KARET Northing
RL
Clasification

Area Dumpingan Soil

Dumpingan dari Exsa 110/material


bagus untuk pembentukan R.L
rencana SP "elevasi sudah pas"

Safety line

PT AKG Observer By, Operation PT AKG, Operation PT. AKG

(Engineering AKG) ( Mine Spv. Operation ) ( Mine Spv. Operation )


PIT BARAT

KDC - AKG PROJECT


Field Observation and Monitoring
Name Pradana Budi I
Change Shift SIANG Easting
21-Aug-22
Date/Time
Pit / Block Yakut/Bacan DISPOSAL OPD B Northing
RL
Clasification

Area Dumpingan material bagus/clay Exsa R-02 Coal Getting


Seam 8 Bacan

Exsa 88 Striping IB Seam 7/8 Bacan

Area Dumpingan material pasir "hindari


metode freedump potong pucuk"

PT AKG Observer By, Operation PT AKG, Operation PT. AKG

(Engineering AKG) ( Mine Spv. Operation ) ( Mine Spv. Operation )


PIT BARAT

KDC - AKG PROJECT


Field Observation and Monitoring
Name Pradana Budi I
Change Shift SIANG Easting
21-Aug-22
Date/Time
Pit / Block Yakut/Bacan AREA WORKSHOP Northing
RL
Clasification

Exsa R-01 perapian slope kaki


Lanjut penimbunan batupalu di workshop "shift malam"
jalan hauling bacan

Exsa R-03 & 108 Lanjut


pembuatan badan jalan

PT AKG Observer By, Operation PT AKG, Operation PT. AKG

(Engineering AKG) ( Mine Spv. Operation ) ( Mine Spv. Operation )